M/S National Construction Company INDIA vs. State Of Hp And Another

ARB.C/42/2026HC Himachal PradeshGSTCNR HPHC01004982202606 November 2026Bench: HON'BLE THE CHIEF JUSTICE GURMEET SINGH SANDHAWALIA6 pages
AI SummaryAllowed

Held

The Court held that since the respondents themselves had been communicating with the petitioner regarding the supply of documents for GST refund, and there was a dispute as to whether these documents were indeed supplied, it was appropriate to refer the matter to an Arbitrator. The Court found no denial of the arbitration clause itself, which is meant to resolve disputes between parties. Therefore, the Court decided to appoint an Arbitrator to adjudicate the issues. The petition was allowed, and Mr. Arjun Lal, Advocate, was appointed as the Arbitrator. The Arbitrator is to obtain his disclosure in writing as per Section 11(8) of the Act, and his appointment will come into force thereafter. The Arbitrator will enter into the reference, pass an award in accordance with law, and his fee will be as per the Fourth Schedule of the Arbitration and Conciliation Act, 1996. The record is to be sent to the Registrar (Judicial) for safe custody after the proceedings conclude.

Facts

The petitioner, M/s National Construction Company India, filed a petition under Section 11(6) of the Arbitration and Conciliation Act, 1996, seeking the appointment of an Arbitrator. The dispute arose from a contract for the construction of a bridge, awarded for Rs.4,34,97,980/-. A change in the bridge's span led to delays and the imposition of liquidated damages, initially at 2% and later enhanced to 10% (Rs.43,49,798/-), with the contract rescinded on 03.03.2020. Subsequently, a departmental committee declared the liquidated damages illegal and withdrew them. The petitioner invoked the arbitration clause due to disputes over payments, including a demand for GST amounting to Rs.22.50 lacs, which the State stated was payable only upon documentary evidence of payment. A fresh demand for GST of Rs.26,91,258/- with interest was made, which the petitioner contested, claiming documents were already supplied.

Key Issues

1. Whether the petition for the appointment of an Arbitrator is barred by limitation, given that the contract was rescinded in March 2020, as argued by the respondents. 2. Whether the petitioner is entitled to claim GST payment along with interest, and if the necessary documentary evidence for GST payment has been duly furnished, as contended by the petitioner. Petitioner's arguments: The petitioner contended that the undertaking given on 15.03.2021, which the respondents relied upon to claim the petition was barred by limitation, was obtained collusively to withdraw liquidated damages. They asserted that GST documents had already been submitted and that the respondents' demand for GST was not legitimate. The petitioner also stated that if legitimate GST payments with interest were released, they would not pursue the petition further. Respondents' arguments: The respondents argued that the claim was barred by limitation as the contract was rescinded in March 2020. They also contended that the petitioner had given an undertaking on 15.03.2021, agreeing not to claim anything extra except legitimate dues in exchange for the waiver of liquidated damages. Furthermore, the respondents claimed that the petitioner failed to submit the required GST documents despite repeated requests.

Sections Cited

Section 11(6), Section 11(8)

AI-generated summary — verify with the full judgment below

( 2026:HHC:49847 )

IN THE HIGH COURT OF HIMACHAL PRADESH, SHIMLA

Arb. Case No.42 of 2026

Decided on: 06.11.2026 M/s National Construction Company India .....Petitioner

Versus The State of Himachal Pradesh …..Respondents and another Coram: The Hon'ble Mr. Justice G.S. Sandhawalia, Chief Justice. Whether approved for reporting? For the petitioner: Mr. Suneet Goel, Senior Advocate with Mr. Vishwas Kaushal, Advocate. For the respondents: Mr. Navlesh Verma, Additional Advocate General. G.S. Sandhawalia, Chief Justice. The present petition has been filed by the petitioner under Section 11(6) of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as ‘the Act’) for the appointment of an Arbitrator. The work in question pertained to the construction of a 40.00-meter span PSC Box Girder Double Lane Bridge over Sirhali Khad near Harsour at RD 7/050 on the Barsar-Shahtalai road under CRF (MDR-37), awarded vide Letter of Award dated 26.09.2016 (Annexure P-1) for an amount of Rs.4,34,97,980/-, pursuant to which an agreement (Annexure P-2) was executed. 2026:HHC:49847

2

2.

Apparentl

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Himachal Pradesh High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.