M/S National Construction Company INDIA vs. State Of Hp And Another

ARB.C/40/2026HC Himachal PradeshGSTCNR HPHC01004981202606 November 2026Bench: HON'BLE THE CHIEF JUSTICE GURMEET SINGH SANDHAWALIA7 pages
AI SummaryAllowed

Held

The Court held that the petition for the appointment of an Arbitrator is maintainable. While the respondents raised the issue of limitation, arguing that the work was completed on 30.04.2021 and final payments accepted without protest, the Court found that the respondents' continued engagement in correspondence and requests for documents, as evidenced by their letter dated 18.10.2025, indicated that a "breaking point" had not been reached. Therefore, the Court deemed it fit to appoint an Arbitrator to adjudicate the dispute, explicitly leaving the question of limitation open for the Arbitrator to decide. Regarding the claims for GST reimbursement and loss of overheads, the Court did not make a definitive finding on their entitlement but rather directed that these issues, including the question of limitation, be resolved by the appointed Arbitrator. The Court allowed the petition and appointed Mr. Deven Khanna, Advocate, as the Arbitrator to adjudicate the dispute between the parties. The operative direction was the appointment of the Arbitrator, with the question of limitation and the merits of the claims to be decided by the Arbitrator.

Facts

The petitioner, M/s National Construction Company India, filed a petition under Section 11(6) of the Arbitration and Conciliation Act, 1996, seeking the appointment of an Arbitrator. The dispute arose from a contract for the construction of a bridge, awarded on 31.05.2016, with a completion date of 30.04.2021. An extension of 46 months and 15 days was granted. The petitioner raised issues regarding escalation and the imposition of Goods and Services Tax (GST) at 12% on construction works from 01.07.2017. A legal notice dated 23.09.2025 was sent, seeking appointment of Dispute Review Experts. The respondents replied on 18.10.2025, stating GST reimbursement was subject to proof of deposit with the GST Department. A subsequent legal notice dated 06.11.2025 demanded payment of GST amounting to Rs.26,91,258/- and loss of overheads of Rs.1,00,71,900/-. The respondents contended the claims were time-barred, as the work was completed on 30.04.2021 and final payments were accepted without protest. The last payment was made on 07.10.2022.

Key Issues

1. Whether the petition for the appointment of an Arbitrator is maintainable in light of the respondents' plea that the claims are barred by limitation, given the work was completed on 30.04.2021 and final payments accepted without protest, as argued by the respondents, relying on Bharat Sanchar Nigam Limited vs. M/s Nortel Networks India Private Limited? 2. Whether the petitioner is entitled to claim GST reimbursement and loss of overheads, and if so, under what conditions, considering the respondents' contention that GST reimbursement requires proof of deposit with the GST Department and that claims for idling charges and overheads pertain strictly to the execution period (2016-2021)? The petitioner argued that the respondents were engaged in correspondence and kept asking for documents, including GST returns, as evidenced by letters dated 14.09.2021, 13.11.2022, and others collectively at Annexure P-7, indicating ongoing engagement and thus, the bar of limitation does not apply, especially since the last payment was released on 07.10.2022. The respondents argued that the petitioner failed to submit the required statutory documents for GST reimbursement and that the claim for loss of overheads was denied.

Sections Cited

Section 11(6), Section 11(8), Central Goods and Services Tax Act, 2017

AI-generated summary — verify with the full judgment below

( 2026:HHC:49847 )

IN THE HIGH COURT OF HIMACHAL PRADESH, SHIMLA

Arb. Case No.40 of 2026

Decided on: 06.11.2026 M/s National Construction Company India .....Petitioner

Versus The State of Himachal Pradesh …..Respondents and another Coram: The Hon'ble Mr. Justice G.S. Sandhawalia, Chief Justice. Whether approved for reporting? For the petitioner: Mr. Suneet Goel, Senior Advocate with Mr. Vishwas Kaushal, Advocate. For the respondents: Mr. Navlesh Verma, Additional Advocate General. G.S. Sandhawalia, Chief Justice. The present petition has been filed by the petitioner under Section 11(6) of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as ‘the Act’), seeking the appointment of an Arbitrator.

2.

The work in question pertained to the construction of a 40-meter span pre-stressed concrete (PSC) double-lane bridge over Khaddar Nalla on the Sainj-Nerwa-Feduj Road at R.D. 62/300 (SH: C/o PSC bridge along with both side approaches) for an amount of Rs. 2,59,98,575/-. Pursuant to the Letter of Award dated 31.05.2016

2 (Annexure P-1), an agreement (Annexure P-2) was exe

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Himachal Pradesh High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.