Held
The Court accepted the settlement agreement arrived at between the parties. The agreement stipulated that the second party would pay the first party Rs. 12,00,000/- (exclusive of applicable GST) in full and final settlement. The payment was to be made in installments, with the final installment including any applicable GST. Upon receipt of the entire settlement amount, both parties agreed to withdraw all pending proceedings, including the present appeal. The Court took the settlement agreement on record and disposed of the appeal in terms of this agreement. The reasoning is based on the parties' mutual consent to resolve the dispute amicably, thereby obviating the need for the Court to adjudicate on the merits of the original dispute. The ratio decidendi is that when parties to an appeal reach a lawful settlement, the Court will record it and dispose of the appeal accordingly, promoting the principle of 'buy peace'.
Facts
The appellant, Dezinetree Projects Pvt. Ltd., filed an appeal under Section 96 of the Code of Civil Procedure, 1908, against a judgment dated July 16, 2024, passed by the learned district judge in CS(COMM) 121/2023. The respondents are Spokes Digital Inc and another. The parties informed the Court that they had reached a settlement agreement dated September 19, 2026. The settlement involved the second party, Returnonweb Consulting Services Pvt. Ltd., paying the first party, Dezinetree Projects Pvt. Ltd., a total sum of Rs. 12,00,000/- (exclusive of applicable GST) in full and final settlement of all claims. The agreement also stipulated a payment schedule and the withdrawal of pending proceedings upon receipt of the entire settlement amount.
Key Issues
1. Whether the settlement agreement dated 19.09.2026, entered into between the parties, is valid and binding, and if so, should the appeal be disposed of in terms of this agreement? (Question of law and fact, turning on principles of contract law and civil procedure). Petitioner's Contention: The petitioner, through its counsel, submitted that the matter has been settled as per the agreement dated 19.09.2026. They presented the terms of the settlement, including the settlement amount, payment schedule, mode of payment, and the agreement to withdraw pending proceedings. They sought for the appeal to be disposed of in terms of this settlement. Revenue's Contention: The judgment does not record any specific arguments or contentions from the revenue or the second respondent. The order indicates that counsel for the parties submitted that the matter has been settled.
Sections Cited
Section 96
AI-generated summary — verify with the full judgment below
Cause title — parties, addresses and appearances
O R D E R %
2026
The present Appeal has been filed under Section 96 of the Code of Civil Procedure, 1908 against the impugned judgement dated 16.07.2024 passed by the learned district judge in CS(COMM) 121/2023. 2. Learned counsel for the parties submit that the matter has been settled as per the agreement dated 19.09.2026 in the following terms:
Settlement Amount: The Second Party (Returnonweb Consulting Services Pvt. Ltd.) shall pay to the First Party (Dezinetree Projects Pvt. Ltd.) a total sum of Rs. 12.00,000/- (Rupees Twelve Lakhs only), exclusive of applicable GST. in full and final settlement of all claims. disputes and demands raised or that could have been raised in the Pending Proceedings.
Payment Schedule: The settlement amount referred to in Clause 1 above
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Delhi High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.