Ms Dhauladhar Builders PVT LTD vs. Ms Sterling And Wilson LTD

CS/51/2017HC Himachal PradeshGSTCNR HPHC01006049201701 January 2019Bench: HON'BLE MR. JUSTICE SURESHWAR THAKUR3 pages
AI SummaryRemanded

Held

The Court held that the joint application filed under Order 23 Rule 3 CPC, being signed by both the contesting litigants and their respective counsel, was valid and in compliance with the procedural requirements. The Court found that the terms of the compromise, including the payment of Rs. 16,16,105/- as full and final settlement and the payment of Rs. 1,53,440/- towards GST, were agreed upon by both parties. Consequently, the Court decreed the suit as compromised. The Court also directed the refund of court fees to the plaintiff and disposed of all pending applications. The judgment explicitly stated that if the defendant breaches the terms of the compromise decree, the suit shall revive.

Facts

This matter concerns Civil Suit No. 51 of 2017 before the Himachal Pradesh High Court, filed by M/s Dhauladhar Builders Pvt. Ltd. (Plaintiff) against M/s Sterling and Wilson Ltd. (Defendant). During the pendency of the suit, both parties jointly filed an application under Order 23 Rule 3 of the Code of Civil Procedure (CPC) for compromise. The application was signed by the litigants and their respective counsel. As per the compromise, the defendant tendered a sum of Rs. 16,16,105/- to the plaintiff, representing a full and final settlement of outstanding amounts. Additionally, the defendant was directed to pay Rs. 1,53,440/- towards GST by cheque within fifteen days of receiving proof of GST deposit.

Key Issues

1. Whether the joint application filed by the parties under Order 23 Rule 3 CPC, duly signed by the litigants and their counsel, is valid for the compromise of the suit? Petitioner/Plaintiff's Arguments: The plaintiff contended that the joint application, properly executed and signed by both parties and their counsel, represents a genuine and binding compromise. They relied on the provisions of Order 23 Rule 3 CPC, which permits suits to be compromised by the parties. Revenue/Defendant's Arguments: The defendant, through their counsel, agreed to the terms of the compromise as presented in the joint application. They acknowledged the payment of Rs. 16,16,105/- as full and final settlement and agreed to the condition of paying Rs. 1,53,440/- towards GST upon proof of deposit. No specific legal arguments were recorded for the defendant other than their consent to the compromise.

Sections Cited

Order 23 Rule 3

AI-generated summary — verify with the full judgment below

IN THE HIGH COURT OF HIMACHAL PRADESH SHIMLA Decided on : 1.1.2019

M/s Dhauladhar Builders Pvt. Ltd. …..Plaintiff. Versus M/s Sterling and Wilson Ltd. ….Defendant. Coram: The Hon’ble Mr. Justice Sureshwar Thakur, Judge. Whether approved for reporting?1 For the plaintiff: Mr. Sumeet Raj Sharma, Advocate. For the defendant: Mr. Neeraj Gupta, Advocate.

Sureshwar Thakur, J (oral)

OMP No. 636 of 2018 The prayer made in the application is allowed.  The application stands disposed of.

During the pendency of the instant suit before this Court, the parties at contest, have, instituted herebefore, a, joint application, cast, under the provisions of Order 23 Rule 3 1 Whether reporters of the local papers may be allowed to see the judgment?

CPC.  The afore application, is, witnessed, and, signatured by the contesting litigant

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.