M/S Beckon Square Hotels And Properties (P) LTD Thru Director Ashish Agarwal vs. State Of U.P. Thru Addl Chief Secy/ Chairman Upsidc Lko And Another

/4587/2022HC AllahabadGSTCNR UPHC02039758202225 July 2022Bench: DEVENDRA KUMAR UPADHYAYA,RAJNISH KUMAR3 pages
For Petitioner: Vishal Dixit, Ashok Kumar, Prajapati, Kamlesh Kumar, Saloni Jaiswal
AI SummaryWithdrawn

Held

The Court noted that the extension order dated 11.12.2009 did not mention any extension fee, which appeared consistent with Clause 25 of the allotment letter, allowing extension up to two years without a fee. The Court observed that the petitioner had not raised a grievance against the demand for extension fee itself, but only against the interest demanded on it. The petitioner's counsel stated that the Chairman of UPSIDA had the power to waive interest but could not show any provision supporting this. The Court expressed serious doubts about the maintainability of the writ petition before the Lucknow Bench if the Chairman lacked such power. Consequently, the petitioner sought to withdraw the petition with liberty to approach another forum. The Court dismissed the petition as withdrawn, granting the petitioner liberty to approach any other forum, including the Allahabad High Court, for redressal of grievances.

Facts

The petitioner, M/s Beckon Square Hotels And Properties (P) Ltd, was allotted an industrial plot in 2005, with the lease executed in 2006 and possession handed over in March 2007. The allotment letter stipulated that production should commence within two years, with extensions permissible. An extension order dated December 11, 2009, granted one year's further time to set up the industry, expiring on December 10, 2010, without any extension fee. A letter in July 2013 indicated the petitioner had previously run the industry, which was then closed. A demand notice dated November 17, 2021, from the Regional Manager of UPSIDA, included demands for lease rent, maintenance charges, interest, GST, time extension fee of Rs. 14,65,078/-, and interest on delayed payment of extension fee amounting to Rs. 23,20,727/-. The petitioner's grievance was primarily against the demand for interest on the delayed payment of time extension fee.

Key Issues

1. Whether the demand for interest on the delayed payment of time extension fee is legally sustainable, considering Clause 25 of the allotment letter and the extension order dated 11.12.2009? (Question of law). Petitioner's arguments: The petitioner contended that the initial extension order dated 11.12.2009 did not impose any extension fee, and Clause 25 of the allotment letter permits extension up to two years from the date of allotment/transfer without any fee. The petitioner also argued that the Chairman of UPSIDA has the power to waive off any amount of interest. Respondent's arguments: The respondent (State of U.P. and UPSIDA) argued for the maintainability of the demand. The judgment does not explicitly record arguments from the respondent regarding the waiver of interest or the interpretation of Clause 25, beyond impliedly supporting the demand raised.

AI-generated summary — verify with the full judgment below

1 Court No. - 2 Case :- WRIT - C No. - 4587 of 2022 Petitioner :- M/S Beckon Square Hotels And Properties (P) Ltd Thru Director Ashish Agarwal Respondent :- State Of U.P. Thru Addl Chief Secy/ Chairman Upsidc Lko And Another Counsel for Petitioner :- Vishal Dixit,Ashok Kumar Prajapati,Kamlesh Kumar,Saloni Jaiswal Counsel for Respondent :- C.S.C.,Manoj Sahu Hon'ble Devendra Kumar Upadhyaya,J.

Hon'ble Rajnish Kumar,J.

Heard learned counsel for the petitioner and Sri Shikhar Anand, learned counsel for U.P. State Industrial Development Authority, Kanpur.

The petitioner is an allottee of industrial plot no. A-1, F-1, Industrial Area Begrajpur, Meerut Road, Muzaffar Nagar. The allotment letter was issued to the petitioner on 06.01.2005 and consequently lease deed was executed on 28.12.2006. After execution of lease, possession of the property was handed over to the petitioner on 22.03.2007. In terms of allotment letter/lease deed, the petitioner was to develop the industry and start production within two years. In terms of Clause 25 of the allotment letter, time extension for setting up the industry/starting production is permissible on payment of certain extension fee, however, "up

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Allahabad High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.