Bdr Builders And Developers Private Limited vs. Sh. Shrichand Bijlani

CM(M)/8/2021HC DelhiGSTCNR DLHC01005707202104 June 2021Bench: HON'BLE MS. JUSTICE ASHA MENON12 pages
For Petitioner: Mr. Ravi Gupta, Senior Advocate with Mr. Akhil Sachar, Ms. Sunanda Tulsyan and Mr. Sachin Jain, AdvocatesFor Respondent: Mr. Pradeep Norula and Ms. Ayushi, Advocates
AI SummaryPartly Allowed

Held

The Court held that the direction to rectify remaining defects on the second, third, and terrace floors within three months was justified, and granted an additional three months for defects not entailing removal of load-bearing structures. The Court found the Executing Court's remark that SDMC's compounding of deviations was immaterial to be misplaced, as SDMC is the competent authority. The Court modified the interim orders, vacating the injunction regarding the first floor but maintaining the restraint on the petitioner creating third-party rights in the basement until the Executing Court finally decides the matter. The Court directed the Executing Court to re-examine the modifications to the basement stairs and skylights, considering the SDMC's circulars and compounding of deviations, and also to determine the need for modifications in light of the agreed site plan. The Court did not comment on whether possession was offered or refused, or the quantum of penalty, deeming these issues for the Executing Court to decide.

Facts

The petitioner, BDR Builders and Developers Private Limited, filed a suit against the respondent, Shrichand Bijlani, concerning property at C-11 Nizamuddin East, New Delhi. The suit was settled via a compromise agreement recorded by the court on November 10, 2017, and disposed of on December 23, 2017. The respondent later filed an Execution Petition seeking directions for the petitioner to carry out construction as per the compromise. The petitioner filed objections under Section 47 CPC. The impugned order dated September 5, 2020, directed the petitioner to carry out repairs/modifications within three months and declined to vacate an interim order restraining the petitioner from creating third-party rights in the first floor and basement. The petitioner assailed this order before the High Court.

Key Issues

1. Whether the petitioner has rectified all defects as per the compromise/settlement agreement, particularly concerning the staircase to the basement and modifications to windows and stone cladding? (Mixed question of law and fact, turning on the interpretation of the Compromise/Settlement Agreement and the reports of the Local Commissioners). 2. Whether the respondent is entitled to claim penalty for alleged deviations from the compromise/settlement agreement, and if so, what is the quantum? 3. Whether the interim order restraining the petitioner from creating third-party rights in its share of the property (first floor and basement) is equitable and should continue? Petitioner's arguments: The petitioner contended that minor defects were rectified, and major deviations, like the staircase construction, were in accordance with the Sanctioned Plan by the South Delhi Municipal Corporation (SDMC) and modified Building Bye-Laws, or were compounded by the SDMC. They argued the Execution Petition was filed malafide after the petitioner demanded payment of GST and balance consideration. They also argued that offering possession ended their obligation and the penalty clause could not be enforced. Respondent's arguments: The respondent argued that the construction was not in terms of the Compromise/Settlement Agreement, leading to refusal of possession and entitlement to penalty.

Sections Cited

Section 47, Order XXIII Rule 3

AI-generated summary — verify with the full judgment below

Cause title — parties, addresses and appearances
CM (M) 8/2021 Page 1 of 12 * IN THE HIGH COURT OF DELHI AT NEW DELHI % Reserved on: 31st May, 2021 Pronounced on: 4th June, 2021 + CM (M) 8/2021 BDR BUILDERS AND DEVELOPERS PRIVATE LIMITED .....Petitioner Through: Mr. Ravi Gupta, Senior Advocate with Mr. Akhil Sachar, Ms. Sunanda Tulsyan and Mr. Sachin Jain, Advocates Versus SHRICHAND BIJLANI .....Respondent Through: Mr. Pradeep Norula and Ms. Ayushi, Advocates CORAM: HON'BLE MS. JUSTICE ASHA MENON

J U D G M E N T

[VIA VIDEO CONFERENCING] CM (M) 8/2021, CM APPLN. 278/2021 (by the petitioner u/S 151 CPC for stay)

1.

This petition has been filed by the petitioner under Article 227 of the Constitution of India with the following prayers: “ a) Allow the present Petition and set aside the order dated 05.09.2020 passed by the Court of Shri Sanjay Sharma-II, Additional District Judge-05 (South East), Saket Courts, New Delhi in Execution Petition No.

CM (M) 8/2021

1352 of 2018 titled as Shrichand Bijlani versus BDR Builders and Developers Private Limited; b) Pass any other such ord

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Delhi High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.