M/S Raj Construction Through Its Power Of Attorney Mr. Rahul vs. Union Finance And Corporate Affairs Minister Thru. Chairmanship And Ors.
Held
The Court did not decide on the merits of the case. Instead, it directed the petitioner to make a fresh, detailed representation to respondent no. 5, the Executive Engineer, Faizabad/Ayodhya Development Authority, within two weeks. This representation should include all grievances, a copy of the writ petition, annexures, and supporting documents. Respondent no. 5 is then mandated to consider and decide this representation in accordance with the law, by a reasoned and speaking order, within two months of receiving the certified copy of the order and the representation. The Court explicitly stated that it had not applied itself to the merits of the case and all questions remain open for the competent authority to decide. No specific findings were made on the issues raised, and no operative directions beyond the consideration of the representation were issued.
Facts
The petitioner, M/s Raj Construction, through its Power of Attorney Mr. Rahul, filed a writ petition seeking a mandamus directing the respondents, specifically the Executive Engineer, Development Authority, District Ayodhya (respondent no. 5), to comply with Letter No. 177/09/2022-T.R.U. issued by the Ministry of Finance, Department of Revenue (Tax Research Unit), Government of India. This letter pertains to the implementation of GST at 18% on all construction works from July 18, 2022. The petitioner also sought a mandamus to release the pending amount of Rs. 11,07,970/- for running bills, which represents the increased total amount due to the GST provision. The petitioner argued that their grievance would be substantially addressed if their representation was considered and decided promptly.
Key Issues
1. Whether the Executive Engineer, Development Authority, District Ayodhya, is legally obligated to comply with Letter No. 177/09/2022-T.R.U. issued by the Ministry of Finance, Department of Revenue (Tax Research Unit), Government of India, regarding the implementation of 18% GST on construction works from July 18, 2022? (Question of law) 2. Whether the petitioner is entitled to the release of the pending amount of Rs. 11,07,970/- for running bills, representing the increased total amount due to the aforementioned GST provision? (Question of mixed law and fact) Petitioner's Contention: The petitioner argued that the Executive Engineer should comply with the Ministry of Finance letter and release the pending amount. They stated that their grievance would be substantially met if their representation was considered and decided in a time-bound manner. Respondent's Contention: The learned Standing Counsel for the State had no objection to the petitioner's request for a time-bound consideration of their representation.
AI-generated summary — verify with the full judgment below
Neutral Citation No. - 2023:AHC-LKO:45458-DB Court No. - 3 Case :- WRIT TAX No. - 157 of 2023 Petitioner :- M/S Raj Construction Through Its Power Of Attorney Mr. Rahul Respondent :- Union Finance And Corporate Affairs Minister Thru. Chairmanship And Ors.
Counsel for Petitioner :- Vijay Bahadur Singh,Manuvendra Singh Counsel for Respondent :- A.S.G.I.,C.S.C.
Hon'ble Vivek Chaudhary,J.
Hon'ble Manish Kumar,J.
Heard learned counsel for petitioner and the learned Standing Counsel for the State.
Present writ petition has been filed by the petitioner with the following main prayers:- "(i) Issue a writ, order or direction in the nature of Mandamus Commanding to the opposite parties, specifically opposite party no. 5 i.e. Executive Engineer Development Authority District Ayodhya to comply with Letter No. 177/09/2022-T.R.U. issued by the Ministry of Finance Department of Revenue (Tax Research Unit)
Government of India regarding the implementation of GST, 18% GST provision has been made on all construction works from 18-07-2022, in the interest of justice. (ii) Issue any other writ, order or direction in the nature of Mandamus commanding to the opposite parties specifically opposite par
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Allahabad High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.