Sai Infra Equipments Private Limited vs. Gannon Dunkerly And Company Limited
Facts
Sai Infra Equipments Private Limited (Applicant) filed an Arbitration Application seeking the appointment of an arbitrator to adjudicate disputes arising from a Work Order dated February 25, 2020, issued by Gannon Dunkerly & Company Limited (Respondent). The Applicant, a hirer of construction equipment, deployed a batching plant and other machinery to the Respondent's project at Udangudi. The Applicant sought clarifications and amendments to the work order, including incorporating the Tamil Nadu GST number, but deployed the equipment at the Respondent's request. The Respondent allegedly failed to make timely payments, leading the Applicant to stop raising invoices for the minimum guarantee quantity (MGQ) amounting to Rs. 1,84,98,823/- to avoid immediate GST payment. The Applicant claimed Rs. 2,21,47,902.16 as of November 16, 2021, towards rental charges. The Respondent terminated the work order on December 21, 2021, citing the Applicant's failure to adhere to contract terms, including delays in plant erection and stopping concrete supply. The Respondent also claimed a refund of Rs. 14,63,695/- for excess advance payments and alleged that the Applicant's breaches led to BHEL terminating the Respondent's contract, imposing penalties of Rs. 55,59,55,000/-.
Held
The Court found that Clause 28 of the Work Order dated February 25, 2020, explicitly contains an arbitration clause, stating that arbitration shall be as per the Indian Arbitration and Conciliation Act, 1996, with Hyderabad as the venue and governed by the laws of India. The Respondent did not dispute the existence of this clause in their counter affidavit or during arguments. The Court acknowledged that disputes have arisen between the parties concerning the Work Order. Therefore, the Court held that an arbitrable dispute exists and is required to be referred to arbitration in terms of Clause 28 of the Work Order. Consequently, the Court allowed the Arbitration Application and appointed Smt. Justice T. Rajani, a retired High Court Judge, as the sole Arbitrator to resolve the disputes between the Applicant and the Respondent. Both parties were directed to appear before the Arbitrator on December 6, 2023. The cost of arbitration was to be borne equally by both parties. No issue was expressly left undecided.
Key Issues
1. Whether an arbitrable dispute exists between the Applicant and the Respondent concerning the Work Order dated February 25, 2020, and connected issues, as contemplated by Clause 28 of the said Work Order, thereby warranting the appointment of an arbitrator under Section 11(5) and (6) of the Arbitration and Conciliation Act, 1996? Contentions: Applicant: Argued that Clause 28 of the Work Order clearly provides for arbitration and that a legal notice was issued invoking this clause. The Applicant reiterated its claims for outstanding rental charges, interest, and compensation for financial losses due to the Respondent's alleged defaults. Respondent: Denied the Applicant's averments, stating that the Applicant breached the contract by delaying plant erection and stopping concrete supply, which led to the termination of the Respondent's contract with BHEL and imposition of substantial penalties. The Respondent claimed the Applicant was liable to reimburse them for these penalties and excess advance payments.
Sections Cited
Section 11(5), Section 11(6)
AI-generated summary — verify with the full judgment below
I 132s5 l IN THE HIGH COURT FOR THE STATE OF TELANGANA AT HYDERABAD FRIDAY, THE TWENTIETH DAY OF OCTOBER TWO THOUSAND AND TWENTY THREE PRESENT THE HON'BLE SRI JUSTICE N.V. SHRAVAN KUMAR ARBITRATION APPLICATION No: 1 60 ot 2022 t Between: AND I Sai Infra Equipments Private Limited, having its corporate office at No. 1 Sai Avenue, Green Glen Layout ORR, Bellandur, Bangalore - 560103 Represented by its Managing Director K. llango .APPLICANT Gannon Dunkerly & Company Limited, A company registered under the Companies Act, 2013 Represented by its Managing Director Manoj Kumar Singh Having its Office at #6-3-1111116, Nishath Bagh Begumpet, (Somajiguda Circle)
Hyderabad - 500016. ...RESPONDENT Arbitration Application filed Under Section 11 (5) and (6) of the Arbitration and Conciliation Act 1996 read with Scheme for Appointment of Arbitrator, 2002, praying that this Hon'ble Court may be pleased to: To appoint an arbitrator to adjudicate the claims and disputes between the Applicant and Respondent in respect to Work Order dated 25-02-2020 and connected disputes; and To award costs of Application.
Counsel for the Petitioner: SRI N. SAMEENA Counsel for the Respondent: SRI S. RAM BABU The Cour
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Telangana High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.