Tmeic Industrial Systems INDIA Private Limited vs. Kansal Pumps Private Limited
Facts
The applicant, TMEIC Industrial Systems India Private Limited, filed an application under Section 11(4) & (6) of the Arbitration and Conciliation Act, 1996, seeking the appointment of an arbitrator. The dispute arose from two tax invoices dated January 19, 2021, and March 20, 2021, for equipment supplied to the respondent, Kansal Pumps Private Limited, under purchase orders dated January 31, 2020, and February 05, 2021. The applicant claimed a total outstanding amount of Rs. 47,17,357/-. The respondent contended that the equipment was not in good condition, installation and commissioning were incomplete, and there was no valid arbitration agreement. The respondent also raised an issue regarding the incorrect filing of a purchase order signed by a sister concern instead of the respondent.
Held
The Court held that its jurisdiction under Section 11(6) of the Arbitration and Conciliation Act, 1996, is limited to examining the existence of an arbitration agreement and the presence of disputes. The Court noted that there was no dispute about a contract existing between the parties and that equipment had been supplied. The applicant's assertion that the respondent retained the original project terms and conditions, and only a signed soft copy was forwarded, was accepted for the purpose of this application. The Court found that Clause 17(b) of the project terms and conditions clearly stipulated for arbitration. The genuineness of the document and the respondent's claims regarding the quality of goods and incomplete services were matters to be decided by the arbitrator, not by the High Court at this stage. Therefore, the Court allowed the application and appointed an arbitrator.
Key Issues
1. Whether a valid arbitration agreement exists between the applicant and the respondent, as contemplated under Section 11(6) of the Arbitration and Conciliation Act, 1996, considering the respondent's contention that the filed document was not signed by them and was an agreement with a sister concern? 2. Whether the disputes arising from the non-payment of dues for the supplied equipment are arbitrable, given the respondent's claims regarding the quality of goods and incomplete services? Petitioner's Arguments: The petitioner argued that a contract existed, equipment was supplied, and an arbitration notice was issued. They asserted that the respondent retained the original project terms and conditions, and a signed soft copy was forwarded. The genuineness of the document, they contended, was for the arbitrator to decide. They relied on Clause 17(b) of the project terms and conditions, which provides for arbitration. Respondent's Arguments: The respondent argued that the equipment was not in good condition, installation and commissioning were incomplete, and their clients demanded refunds. They further contended that there was no arbitration agreement between the parties, as the document filed by the applicant was not signed by the respondent and was an agreement with M/s Kansal Power Private Limited, a sister concern. They acknowledged inadvertently filing a document signed by the sister concern instead of the respondent.
Sections Cited
Section 11(4), Section 11(6), Clause 17(b)
AI-generated summary — verify with the full judgment below
IN THE HIGH COURT FOR THE STATE OF TELANGANA ATHYDERABAD '" WEDNE AY, TFIE TWENW FIRST DAY OF FEARUARY TWO THOUSAND AND TWENTY FOUR N APPLICATION l,lo: 44 2023 [ 3183 ] ...Appellant ...Respondent PRESENT THE HON'BLE SRI JUST]CE B. VIJAYSEN REDDY ITRATI Between: Also at AND TMEIC lndustrial Svslems Inrlia private Limited, A Company registered under the Companies Act 19-56 havino. its. of,C." ,i''Ff.it.'til tE: Vasanthanarasaoura B8ir':lil#:',; r?:r,ii3ii;{S:r"d"dr' Mids';' *lii "nl"o,'' r,iii,i'i;i;i'"#; The Millennia Tower A. l0th Floor, No. 1 & 2 Murphy Road, Halasuru, Benoaluru B3:lT,e%iFT,?nJ'#f lg,lrjgl:##t+1*#"!1,"..*ri*k"fl nc"#:,y Also at; No. 105. 1"t Floor. BpTp park Centra Sector _ 30, Gurgoan _122001 (Represented by its Company Su"i"trrv aio-LJj.iilLli""r Mr. Uday parhak)
Kansal Pumps Private Limited, A pmpany incorporated uDder the Companies Ai:.'i,1%[1'lg 3,Ttri::"1*"p9tr,il,:ti#ll;d;'&i#po,na, BedH Einds" i'?i?'"9,[i',{"",i.'"",lliH{IHiff [,|*S,i,",ff ff H*::)^uthorizedsisnatory Arbitration Apprication Under. section I 1 (4) & (6) of the Arbitration and Conciliation Act, for the reasons stated in tne jclrori"nying affidavit, praying that this Hon'ble Court may be
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Telangana High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.