Mohammed Ilyasuddin vs. The State Of Telangana

WP/5225/2025HC TelanganaGSTCNR HBHC01010537202520 February 2025Bench: SUREPALLI NANDA13 pages
AI SummaryPartly Allowed

Facts

The petitioner, Mohammed Ilyasuddin, a consumer of electricity for his business, received a provisional assessment notice dated January 30, 2025, from the 4th respondent (Assistant Divisional Engineer) under Section 135 of the Electricity Act, 2003. The notice alleged theft of electricity and demanded Rs. 2,07,728/-. The petitioner contended that the inspection date mentioned in the notice (October 28, 2024) was impossible as the tampered meter was allegedly taken by the department on July 8, 2024. Aggrieved, the petitioner submitted a representation on February 10, 2025, to the 4th respondent, requesting withdrawal of the notice and expressing willingness to pay the compounding fee under protest, which was paid on February 18, 2025. As the representation remained unaddressed, the petitioner filed a writ petition seeking a direction to dispose of the representation and to refrain from coercive steps, including power disconnection, without due process.

Held

The Court directed the respondents not to disconnect the petitioner's electricity service connection bearing SC.No.A3002537. The petitioner was directed to deposit 50% of the amount indicated in the provisional assessment notice, totaling Rs. 1,03,864/-, within four weeks from the date of receiving a copy of the order. Upon such deposit, the respondents were directed to refer the subject issue to the Special Court as mandated under Section 154(5) of the Electricity Act, 2003, for passing appropriate orders within four weeks thereafter. The respondents were also restrained from taking any coercive steps against the petitioner for recovery of the un-assessed amount until the civil liability is determined by the appropriate Court under Section 154(5) of the Electricity Act, 2003. The Court noted the submissions of both parties and the contents of the provisional assessment notice and Section 154(5) of the Electricity Act, 2003.

Key Issues

1. Whether the provisional assessment notice dated January 30, 2025, issued under Section 135 of the Electricity Act, 2003, is vitiated by factual inconsistencies regarding the inspection date and meter seizure, thus warranting its withdrawal or modification? Petitioner's arguments: The petitioner argued that the provisional assessment notice is flawed due to contradictory dates regarding the inspection and seizure of the meter, suggesting a false implication. The petitioner also highlighted that the service connection had not been disconnected despite the notice stating so and sought protection of their interest until the deposit of 50% of the assessed amount. The petitioner relied on their representation dated February 10, 2025, for consideration. Respondents' arguments: The respondents, through their learned standing counsel, contended that the provisional assessment notice clearly indicates the demand of Rs. 2,07,728/- based on assessment rules and clause 10 of the General Terms and Conditions of Supply, pending determination of civil liability under Section 154(5) of the Electricity Act, 2003. Therefore, the petitioner is obligated to pay 50% of the assessed amount for further action by the respondent under Section 154(5) of the Act, and the relief sought by the petitioner cannot be granted at this stage.

Sections Cited

Section 135, Section 154(5)

AI-generated summary — verify with the full judgment below

l32s2l HIGH COURT FOR THE STATE OF TELANGANA AT HYDERABAD (Special Original Juri iction) THUR AY,THE TWENTIETH DAY OF FEBRUARY TWO THOUSAND AND TWENW FIVE PRESENT THE HONOURABLE MRS JUSTICE SUREPALLI NANDA WRIT PETITION NO: 5225 OF 2025 Between: AND Mohammed llyasUddin, S/o Mohammed Maslihuddin, Aged about 52 years, Occ.Business, Rl/o H.No.10-5-29/1, Masab Tahk, Hyderadad -500028. ...PETTTTONER( '1 . The stale of Telangana, The Principal Secretary Energy, Telangana Secretariat, Hyderabad -500 06e

2.

The Chairman and Managing Director, The Southern Power Distribution Company of Telangana Ltd., Having its office at Door No.6-1-50, 5th Floor, Mint Compound, Hyderabad, Telangana State - 500 063. 3. TheAddl. Assistant Engineer, Assessments, 1st Floor, 33/'l'l KV CM Camp Office $ub Station, Punjagufta, Hyderabad - 500 082. 4. The Assistant Divisional Engineer, Mehdipatnam, TGSPDCL, Hyderabad. ...RESPONDENTS Petition under Article 226 ol the ConStitution of lndia praying that in the circumstances stated in the affidavit filed therewith, the High Court may be pleased to issue a Writ, order or direction more particularly in the nature of Writ of Mandamus directing the Respondent Officials

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Telangana High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.