National Highways Authority Of INDIA vs. Ashoka Buildcon LTD.

O.M.P. (COMM)/294/2019HC DelhiGSTCNR DLHC01031893201913 September 2023Bench: CASES PERTAINING TO SPECIAL BENCHES54 pages
For Petitioner: Ms. Madhu Sweta and Ms. Raveena Dewan, AdvocatesFor Respondent: Mr. Jay Salva, Sr. Advocate with Mr. Rajpal Singh, Advocate
AI SummaryDismissed

Facts

The National Highways Authority of India (NHAI), the petitioner, invited proposals for the construction of a Project Highway. Ashoka Buildcon Ltd. (ABL), the respondent, submitted a bid which was accepted, and a Contract Agreement was executed on August 1, 2016. A dispute arose, and ABL invoked arbitration on July 31, 2017. The Arbitral Tribunal (AT) was constituted on September 26, 2017. ABL filed its Statement of Claims, followed by NHAI's Statement of Defence and ABL's rejoinder. On March 25, 2019, the AT passed an award directing NHAI to pay ABL a sum of Rs. 3628.79 lakhs plus GST as per actual. NHAI filed a petition under Section 34 of the Arbitration and Conciliation Act, 1996, seeking to set aside this arbitral award.

Held

The Court held that the scope of interference with an Arbitral Award under Section 34 of the Arbitration and Conciliation Act, 1996, is limited and narrow, and the Court should not sit in appeal. The petitioner failed to demonstrate patent illegality or error apparent on the face of the award that would shock the conscience of the Court. The Arbitral Tribunal considered all relevant material, and its award was well-reasoned and not in contravention of the fundamental policy of Indian law. Specifically, the Court found no reason to interfere with the findings of the learned Arbitrator regarding claims No. 4, 5, and 6, which were challenged. The Court upheld these claims as awarded by the Tribunal. The petitioner failed to corroborate with evidence how the Arbitrator had erred in adjudicating the dispute. Therefore, the Court found no cogent reasons to entertain the petition and set aside the impugned award.

Key Issues

1. Whether the Arbitral Tribunal erred in allowing the respondent's claim for delay by omitting applicable provisions of the Contract Agreement, specifically Clauses 4.1.4, 8.3, and 10.5, and whether the appointed date was mutually independent of the handing over of the Right of Way (ROW)? The petitioner argued that the Tribunal failed to consider these clauses, that the appointed date was consequent to ROW handover, and that the ROW was handed over as per the agreement. The petitioner contended that damages should have been calculated as per Article 4 of the Contract Agreement, specifically Clause 4.1.4, and that Clause 4.1.5 stipulated that damages under Clause 8.3 were full and final. The petitioner also argued that the Tribunal failed to consider the Non-Obstante Clause limiting aggregate damages to 1% of the contract price. 2. Whether the Arbitral Tribunal's award of overhead charges, idle charges, and demobilization charges was perverse and lacked reasoning? The petitioner submitted that the respondent's allegations lacked support and evidence. 3. Whether the Arbitral Tribunal erred in awarding costs of arbitration and interest against Clause 26.3 (iv) and 26.3.1(vi) of the Contract Agreement, which stipulated that each party bears its own costs and that aggregate damages were limited? The petitioner argued that the Tribunal went against the contract in awarding pre- and pendente lite interest and that the award of interest on the entire award was against applicable law and the contract. The petitioner relied on ONGC v. Wig Brothers Builders and Engineers Private Limited (2010) 13 SCC 377.

Sections Cited

Section 34, Clause 4.1.4, Clause 8.3, Clause 10.5, Clause 4.1.5, Clause 26.3 (iv), Clause 26.3.1(vi)

AI-generated summary — verify with the full judgment below

Cause title — parties, addresses and appearances
O.M.P. (COMM) 294/2019 Page 1 of 54 * IN THE HIGH COURT OF DELHI AT NEW DELHI % Pronounced on: 13th September, 2023 + O.M.P. (COMM) 294/2019 & I.A. 764/2020 NATIONAL HIGHWAYS AUTHORITY OF INDIA ..... Petitioner Through: Ms. Madhu Sweta and Ms. Raveena Dewan, Advocates versus ASHOKA BUILDCON LTD. ..... Respondent Through: Mr. Jay Salva, Sr. Advocate with Mr. Rajpal Singh, Advocate CORAM: HON’BLE MR. JUSTICE CHANDRA DHARI SINGH

J U D G M E N T

CHANDRA DHARI SINGH, J.

1.

The instant petition under section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter The Act) has been filed on behalf of the petitioner seeking the following reliefs: “a) To quash and set aside the arbitral award dated 25.03.2019 passed by the Arbitral Tribunal, and/or (b) To pass such other order or direction as deemed fit and proper in the facts and circumstances of the present case.”

FACTUAL MATRIX

2.

The petitioner, National Highways Authority of India (NHAI), is an autonomous body constituted under the National Highways Authority of India Act, 198

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Delhi High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.