Ms K S Jain Builders vs. Indian Railway Welfare Organization

O.M.P. (COMM)/456/2022HC DelhiGSTCNR DLHC01042394202225 January 2024Bench: HON'BLE MR. JUSTICE SANJEEV NARULA13 pages
For Petitioner: Ms. Minakshi Jyoti, Mr. Dharaveer Singh and Mr. Vikas Singh, Advocates with Mr. Sanjeep Jain, ARFor Respondent: Mr. Sulaiman Mohd. Khan, Ms. Taiba Khan, Mr. Bhanu Malhotra and Mr. Gopeshwar Singh Chandel, Advocates
AI SummaryDismissed

Facts

The Petitioner, MS K S Jain Builders, challenged an arbitral award dated July 7, 2022, rendered by a Sole Arbitrator. The dispute arose from a contract for the construction of a residential complex valued at INR 33,52,66,929/-, awarded on April 12, 2016. The Petitioner claimed the Respondent, Indian Railway Welfare Organization, obstructed work commencement and failed to supply required steel as per Clause 5.3 of the Special Conditions of Contract. The Respondent unilaterally postponed the project on October 28, 2020, citing Covid-19 and recession, and later terminated the contract on February 2, 2021, on grounds of force majeure. The Petitioner initiated arbitration seeking substantial losses, including resource engagement and loss of profits. The Arbitral Tribunal partially allowed Claims No. 4 and 5, awarding INR 45,29,089.00 for Claim No. 4 and INR 86,01,230.00 for Claim No. 5, totaling INR 1,42,34,622.00 with interest.

Held

The Court held that the Petitioner's contention of patent illegality and conflict with the fundamental policy of Indian law is misconceived. The Arbitral Tribunal's application of contractual terms, even if contentious, is within its interpretative authority. The calculation of lost profits is inherently speculative, and the tribunal's decision to award 5% damages, based on its assessment of hypothetical loss of profits and the reduced work value due to project termination, is a plausible view and a finding of fact. The Court emphasized that the threshold for patent illegality is high and involves more than just an erroneous application of law. The Proviso to Section 34(2A) of the Act states that an award shall not be set aside merely on the ground of an erroneous application of the law or by re-appreciation of evidence. The Court cannot re-appreciate evidence or replace the Arbitrator's findings with its own unless there is clear arbitrariness or gross misinterpretation leading to a miscarriage of justice. As no such flaws were found, the petition was dismissed.

Key Issues

1. Whether the Arbitral Tribunal's award on Claim No. 5, concerning loss of profit on undone work, suffers from patent illegality or contravenes the fundamental policy of Indian law, as argued by the Petitioner, by allegedly applying inapplicable contractual terms and awarding an insufficient rate of 5% for damages, contrary to Section 73 of the Indian Contract Act, 1872 and Clause 4.3(iii) of the GCC of IRWO? 2. Whether the Arbitral Tribunal's assessment of damages at 5% for loss of profit is a finding of fact based on the presented material, and if the Petitioner's disagreement with this assessment or reliance on certain circulars warrants judicial interference under Section 34 of the Arbitration and Conciliation Act, 1996? Petitioner's arguments: The award is in conflict with the most basic notions of morality and justice and the fundamental policy of Indian Law. The Arbitrator applied terms of the contract not pleaded by the Respondent, amounting to patent illegality. The Arbitrator's decision on loss of profit is speculative and does not account for admitted contractor's profit rates. Respondent's arguments: The award is faultless, and the Petitioner's grounds do not fall under the permissible criteria of Section 34 of the Arbitration and Conciliation Act, 1996. The Arbitral Tribunal's assessment of damages is a finding of fact and within its powers.

Sections Cited

Section 34, Section 73

AI-generated summary — verify with the full judgment below

O.M.P. (COMM) 456/2022 * IN THE HIGH COURT OF DELHI AT NEW DELHI Reserved on: 19th January, 2024 Pronounced on: 25th January, 2024

+ O.M.P. (COMM) 456/2022

MS K S JAIN BUILDERS

..... Petitioner Through: Ms. Minakshi Jyoti, Mr. Dharaveer Singh and Mr. Vikas Singh, Advocates with Mr. Sanjeep Jain, AR.

versus

INDIAN RAILWAY WELFARE ORGANIZATION ..... Respondent Through: Mr. Sulaiman Mohd. Khan, Ms. Taiba Khan, Mr. Bhanu Malhotra and Mr. Gopeshwar Singh Chandel, Advocates.

CORAM:

HON'BLE MR. JUSTICE SANJEEV NARULA

J U D G M E N T

SANJEEV NARULA, J.

1.

The Petitioner (claimant in arbitration), despite being the successful party in the arbitration, remains discontent with the arbitral award, dated 7th July, 2022, rendered by a Sole Arbitrator. Their challenge is directed towards the findings on two specific claims i.e., Claims No. 4 and 5, that were only partially allo

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Delhi High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.