M/S Creative Projects And Contracts PVT. LTD vs. M/S Suncity Projects PVT LTD

ARB.P./135/2023HC DelhiGSTCNR DLHC01001337202220 March 2024Bench: HON'BLE MR. JUSTICE JASMEET SINGH12 pages
For Petitioner: Mr. Sandeep Sethi, Sr. Advocte, Mr. Anuroop Singhvi, Mr. Ankit Shah, Mr. Aditya Vijay, Mr. Tarun Arora, Mr. Sidhant Singh, AdvocatesFor Respondent: Ms. Malvika Trivedi, Sr Advocate with Mr. Himanshu Satija, Mr. Harsh Saxena, Mr. Shevaaz Khan, Ms. Sujal Gupta, Mr. Siddhant Tyagi, Mr. Shailendra Slaria, Advocates
AI SummaryDismissed

Facts

The petitioner, M/s Creative Projects and Contracts Pvt. Ltd., filed a petition under Section 11(6) of the Arbitration and Conciliation Act, 1996, seeking the appointment of a Sole Arbitrator to adjudicate disputes with the respondent, M/s Suncity Projects Pvt Ltd. The parties had executed three work orders, but only Work Order No. 1 contained an arbitration clause. Disputes arose concerning all three work orders, leading to a Settlement Deed dated December 10, 2021. This deed settled various claims, including payments for Work Orders 1 and 2, a dispute regarding cement supply, and TDS on WCT. Subsequently, the respondent filed a civil suit seeking damages and injunction, which the petitioner challenged via an Order VII Rule 11 application. This application was dismissed, and the dismissal was stayed by the Punjab and Haryana High Court.

Held

The Court held that the Settlement Deed dated December 10, 2021, comprehensively settled all disputes between the parties, including those pertaining to Work Order No. 1. The Court found that the petitioner's claim of fraudulent inducement related to the settlement agreement itself, not the underlying Work Order No. 1. Therefore, the Court concluded that there were no pending disputes under Work Order No. 1 that could be referred to arbitration. The Court reasoned that the scope of Section 11(6) requires a prima facie examination to ensure that the claims are not time-barred or demonstrably non-arbitrable. Citing "Vidya Drolia v. Durga Trading Corpn.", the Court emphasized that while the scope is limited, it is not mechanical and aims to prevent parties from being forced into arbitration for non-arbitrable matters. The Court noted that the petitioner was at liberty to agitate any grievances concerning the settlement agreement in accordance with law. The findings were limited to the present petition and would not affect other disputes in different forums.

Key Issues

1. Whether the disputes arising from Work Order No. 1 are arbitrable, considering the Settlement Deed dated December 10, 2021, and the petitioner's claim of fraudulent inducement in its execution, as per Section 11(6) of the Arbitration and Conciliation Act, 1996. Petitioner's arguments: The petitioner contended that the referral court under Section 11 is only required to examine the existence of an arbitration clause and that the scope is limited to a prima facie determination, citing "Interplay between Arbitration Agreements under the Arbitration & Conciliation Act, 1996 & the Indian Stamp Act, 1899, In re". They argued that the Settlement Deed was fraudulently induced, implying the disputes under Work Order No. 1 were not effectively settled and remained arbitrable. Respondent's arguments: The respondent argued that the Settlement Deed comprehensively settled all disputes, including those under Work Order No. 1, and that payments were made pursuant to this settlement. They asserted that the petitioner's grievance regarding fraudulent inducement pertains to the settlement agreement itself, not the original Work Order No. 1, and that the petitioner is at liberty to pursue such claims separately. They relied on the principle that if there is no subsisting dispute, arbitration cannot be invoked.

Sections Cited

Section 11(6), Section 7, Section 16

AI-generated summary — verify with the full judgment below

Cause title — parties, addresses and appearances
ARB.P. 135/2023 Page 1 of 12 $~4 * IN THE HIGH COURT OF DELHI AT NEW DELHI Date of decision: 20.03.2024 + ARB.P. 135/2023 M/S CREATIVE PROJECTS AND CONTRACTS PVT. LTD ..... Petitioner Through: Mr. Sandeep Sethi, Sr. Advocte, Mr. Anuroop Singhvi, Mr. Ankit Shah, Mr. Aditya Vijay, Mr. Tarun Arora, Mr. Sidhant Singh, Advocates. versus M/S SUNCITY PROJECTS PVT LTD ..... Respondent Through: Ms. Malvika Trivedi, Sr Advocate with Mr. Himanshu Satija, Mr. Harsh Saxena, Mr. Shevaaz Khan, Ms. Sujal Gupta, Mr. Siddhant Tyagi, Mr. Shailendra Slaria, Advocates. CORAM: HON'BLE MR. JUSTICE JASMEET SINGH

O R D E R %

20.03.

2024

1.

This is a petition filed under section 11(6) of the Arbitration and Conciliation Act, 1996 (in short “1996 Act”) seeking appointment of a Sole Arbitrator to adjudicate disputes between the parties.

2.

The petitioner is a private limited company having its registered office at SB-154, 5th floor, Ganga Heights, Bapu Nagar, Tonk Road, Jaipur, Rajasthan. The petitioner is engaged in execution of Civil Engineering Projects with specialization in commercial, resid

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Delhi High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.