Rcc Developers vs. Northern Railways
Facts
The petitioner, RCC Developers, filed a petition under Section 11(6) of the Arbitration and Conciliation Act, 1996, seeking the appointment of a Sole Arbitrator to resolve disputes with Northern Railways. Disputes had previously arisen, leading to the appointment of Mr. Justice A.K. Pathak (Retd.) as Sole Arbitrator for claims up to May 31, 2022. Following this, the petitioner continued to provide services as requested by the respondent and completed the work. However, the respondent allegedly failed to release pending payments, take over the work, record completion, issue a completion certificate, and make payments for price variation, contract prolongation, and extra GST. Consequently, the petitioner issued a second demand notice on March 5, 2024, for arbitration of these subsequent disputes, to which the respondent neither responded nor made payments.
Held
The Court held that Mr. A.K. Pathak (Retd.), who was already appointed as the Sole Arbitrator for disputes arising prior to May 31, 2022, would also be appointed as the Sole Arbitrator for the disputes that have arisen thereafter under the same contract. The reasoning was that since an arbitrator was already seized of disputes under the contract, it was logical and efficient to have the same arbitrator adjudicate subsequent disputes under the same agreement. The Court directed that the parties could raise their respective objections before the Arbitrator. The fees of the Arbitrator would be fixed as per the Fourth Schedule of the Act, 1996, or as consented by the parties, subject to the Arbitrator making necessary disclosures under Section 12(1) and not being ineligible under Section 12(5). The arbitration would be conducted under the aegis of the Delhi International Arbitration Centre. The parties were directed to contact the Arbitrator within one week of receiving the order.
Key Issues
1. Whether a new Sole Arbitrator should be appointed to adjudicate disputes arising after May 31, 2022, under Section 11(6) of the Arbitration and Conciliation Act, 1996, given that a Sole Arbitrator was already appointed for earlier disputes under the same contract. Petitioner's Arguments: The petitioner contended that new disputes had arisen after May 31, 2022, concerning pending payments, completion certificates, and other contractual obligations, necessitating a fresh arbitration. They argued that the previous arbitration was limited to claims up to a specific date and did not cover these subsequent issues. The petitioner relied on the principle that each set of disputes arising under a contract can be subject to arbitration if the contract permits. Respondent's Arguments: The respondent did not dispute the existence of an arbitration clause. Their primary contention, implied by their non-response to the demand notice and the court's eventual decision, was likely that the existing arbitration mechanism could encompass all disputes, or they may have argued against the necessity of a new appointment. However, the judgment does not explicitly record detailed arguments from the respondent regarding the appointment of a new arbitrator for subsequent disputes.
Sections Cited
Section 11(6), Section 12(1), Section 12(5)
AI-generated summary — verify with the full judgment below
Cause title — parties, addresses and appearances
O R D E R %
2024
The present petition has been filed under Section 11(6) of the Arbitration and Conciliation Act, 1996 seeking appointment of the Sole Arbitrator to adjudicate upon the disputes which have arisen between the parties.
It is submitted that earlier certain disputes had arisen between the parties due to which the petitioner was constrained to invoke arbitration by way of a Demand Notice dated 22.07.2021 under Clause 64 of the GCC. The respondent in their Reply to the Demand Notice dated 26.08.2021 did not dispute the existence of the Arbitration Clause.
Thereafter, the petitioner then filed the ARB.P. bearing No. 1213/2021 under Section 11(6) of the Arbitration and Conciliation Act, 1996 seeking appointment of the Sole Arb
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Delhi High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.