Trans Engineers INDIA Private Limited vs. Otsuka Chemicals (INDIA) Private Limited
Facts
The petitioner, Trans Engineers India Private Limited, was engaged by the respondent, Otsuka Chemicals (India) Private Limited, for the expansion of its plant, referred to as the "Lion project." Two purchase orders dated September 16, 2016, totaling Rs. 71 crores, were issued, followed by an agreement dated January 20, 2017, for the supply, erection, manufacture, and commissioning of equipment and materials. Disputes arose concerning the petitioner's claim for additional works performed at the respondent's instance. The petitioner raised 26 proforma invoices for these additional works, which the respondent refused to pay, leading to arbitration. The petitioner claimed Rs. 28,37,09,384/- for additional works, plus statutory dues, costs, and interest. The respondent filed counter-claims for liquidated damages, pending and remedial work, and price difference.
Held
The Court held that the impugned arbitral award is unsustainable and is therefore set aside. The Court found that the arbitral tribunal erred in its assessment of the petitioner's claim for additional works. The tribunal's finding that equipment claimed as "extra" was reflected in the P&IDs dated July 26, 2016, or the offer dated August 30, 2016 (based on P&IDs dated August 20, 2016), was flawed, particularly as the P&IDs dated August 20, 2016, were not on record. The Court noted that the P&IDs dated August 20, 2016, though a basis for the offer, were consciously not made the basis for the purchase orders dated September 16, 2016, which were issued based on the P&IDs dated July 26, 2016. The award also failed to properly consider that the P&IDs were subject to continuous revisions, which the petitioner was bound to abide by, and that such revisions entailed entitlement for additional payment. The Court found that the award acknowledged the execution of "additional work" but erroneously concluded the petitioner failed to prove it was "major" or to establish its price. The Court concluded that the award vitiates the arbitral award in its entirety by omitting to assess the claim based on the correct contractual framework.
Key Issues
1. Whether the arbitral tribunal erred in holding that the petitioner was not entitled to recover amounts for additional works performed, by incorrectly determining the contractual basis for assessing such claims? (Section 34 of the Arbitration and Conciliation Act, 1996). The petitioner argued that the arbitral award failed to consider the correct contractual framework, specifically the P&IDs dated July 26, 2016, as the baseline for assessing additional work, and that the tribunal's reliance on P&IDs dated August 20, 2016, and the offer dated August 30, 2016, was erroneous, especially since the P&IDs dated August 20, 2016, were not even on record. The petitioner contended that the award acknowledged "additional work" and that the respondent never denied its execution until arbitration was invoked. The respondent argued that the P&IDs dated August 20, 2016, and the offer dated August 30, 2016, were part of the contract, and that the petitioner failed to prove the additional work was "major" or to establish its price.
Sections Cited
Section 34
AI-generated summary — verify with the full judgment below
O.M.P. (COMM) 310/2022
$~J-1 * IN THE HIGH COURT OF DELHI AT NEW DELHI Judgment pronounced on:22.07.2024 + O.M.P. (COMM) 310/2022, IA Nos.11536/2022 & 1013/2023
TRANS ENGINEERS INDIA PRIVATE LIMITED ..... Petitioner Through: Mr. Arvind Nigam, Sr. Advocate along with Ms. Binsy Susan, Ms. Neha Sharma, Ms. Palak Kaushal, Ms. Ayushi Thakur, Mr. Amogh Srivastava, Mr. Vishal Habloni and Mr. Arijeet Shukla, Advocates.
versus
OTSUKA CHEMICALS (INDIA) PRIVATE LIMITED.. Respondent Through: Mr. Jayant Mehta, Sr. Advocate along with Mr. Amit Dhingra, Mr. Rohit Mahajan, Ms. Anu Shrivastava, Mr. Akshat Aggarwal, Ms. Kesang T. Doma and Mr. Udit Dediya, Advocates.
CORAM:
HON'BLE MR. JUSTICE SACHIN DATTA
By way of the present petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the “A&C Act”), the petitioner seeks to assail the arbitral award dated 07.03.2022 (hereinafter referred to as the “impugned award”)passed by the learned sole arbitrator. JUDGMENT
The respondent is stated to have engaged
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Delhi High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.