M/S Ram Gopal Agrawal vs. Union Of INDIA Through Northern Railway Moradabad

ARB.P./1154/2023HC DelhiGSTCNR DLHC01044042202331 July 2024Bench: HON'BLE MR. JUSTICE C.HARI SHANKAR15 pages
For Petitioner: Mr. Sahil Garg, Ms. Samiksha Jain and Ms. Mithil Malhotra, AdvsFor Respondent: Mr. Farman Ali, CSPC with Ms. Usha Jamnal and Mr. Krishan Kumar, Advs. Mr. Ashok Deo and Mr. Chandra Shekhar, Advs
AI SummaryAllowed

Facts

The petitioner, M/s Ram Gopal Agrawal, was awarded three construction contracts by the respondent, Union of India through Northern Railway Moradabad, in 2017 and 2020. These contracts were governed by General Conditions of Contract (GCC) of 2014 and 2018, both of which provided for dispute resolution through arbitration. The petitioner claimed outstanding payments under various heads, including escalation, price variation, and GST. After unsuccessful attempts at settlement, the petitioner issued a notice under Section 21 of the Arbitration and Conciliation Act, 1996, seeking the appointment of a sole arbitrator. The respondent contested the petitioner's claims. As no consensus was reached, the petitioner filed a petition before the High Court seeking the appointment of an arbitrator.

Held

The Court held that its primary role under Section 11(6) of the Arbitration and Conciliation Act, 1996, is to ascertain the existence of a valid arbitration agreement between the parties. Following the Supreme Court's decision in SBI General Insurance Co Ltd v. Krish Spinning, the Court emphasized that other contentious issues should be left to the Arbitral Tribunal to maintain arbitral autonomy. The Court found that the GCCs provided for arbitration and that the parties had entered into contracts containing such clauses. Therefore, the Court appointed Mr. J Sai Deepak, an advocate, as the sole arbitrator to adjudicate the disputes. The arbitration proceedings would be conducted under the aegis of the Delhi International Arbitration Centre (DIAC) and would abide by its rules. All contentions of fact and law, including maintainability, were left open for adjudication before the learned arbitrator.

Key Issues

1. Whether the disputes arising from the construction contracts are arbitrable under the relevant General Conditions of Contract (GCC) and the Arbitration and Conciliation Act, 1996? Petitioner's contention: The petitioner argued that the disputes are interconnected and should be referred to a common arbitrator for expeditious disposal and cost reduction, as envisaged by the GCC and the 1996 Act. They relied on the principle that courts should satisfy themselves about the existence of an arbitration agreement and relegate other controversial issues to the Arbitral Tribunal, citing SBI General Insurance Co Ltd v. Krish Spinning. Respondent's contention: The respondent initially contested the petitioner's claims but did not oppose the reference of all matters to a common arbitrator, reserving their right to raise objections before the arbitrator. They acknowledged a slight difference in the arbitration clauses between the two GCCs.

Sections Cited

Section 21, Section 11(6), Section 12(2)

AI-generated summary — verify with the full judgment below

Cause title — parties, addresses and appearances
ARB. P. 1154/2023 Page 1 of 15 $~52 * IN THE HIGH COURT OF DELHI AT NEW DELHI + ARB.P. 1154/2023 M/S RAM GOPAL AGRAWAL .....Petitioner Through: Mr. Sahil Garg, Ms. Samiksha Jain and Ms. Mithil Malhotra, Advs. versus UNION OF INDIA THROUGH NORTHERN RAILWAY MORADABAD .....Respondent Through: Mr. Farman Ali, CSPC with Ms. Usha Jamnal and Mr. Krishan Kumar, Advs. Mr. Ashok Deo and Mr. Chandra Shekhar, Advs. CORAM: HON'BLE MR. JUSTICE C.HARI SHANKAR

JUDGMENT (ORAL) % 31.07.2024 ARB.P. 1154/2023

1.

The petitioner was awarded three contracts by the respondents for carrying out construction activities on 28 November 2017, 22 December 2017 and 10 September 2020. The contracts dated 28 November 2017 and 22 December 2017 were governed by General Conditions of Contract1, whereas the contract dated 10 September 2020 was governed by GCC of 20182. 2. There is no dispute that both the GCCs of 2014 and 2018 envisage resolution of disputes between the parties by arbitration, though Mr. Farman Ali, learned Counsel for the respondent submits 1 GCC 2 GCC of 2018 KUMAR Signi

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Delhi High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.