Kashish Developers Limited vs. The State Of Bihar
Held
The Court held that the impugned order dated July 2, 2020, rescinding the agreement, is void and quashed. The primary reason for this decision was the non-compliance with the principles of natural justice and Clause 14 of the contract, which stipulated issuance of a written notice to the contractor before cancellation. The Court found that no show cause notice was issued to the petitioner prior to the rescission. Additionally, the Court found the order to be bad in law because the Executive Engineer, the competent authority, appeared to have acted on departmental directions from the Chief Engineer and Superintending Engineer, rather than exercising his independent judgment. The Court relied on the Apex Court's decision in Gordhandas Bhanji. Regarding the petitioner's request for a 12-month extension to complete the work, the Court granted liberty to the petitioner to file a representation with the respondents. This representation is to be considered sympathetically, taking into account the COVID-19 lockdown and relevant judgments, and disposed of within four weeks of its filing.
Facts
Kashish Developers Limited (the petitioner) entered into an agreement with the Executive Engineer, Building Construction Department, Bihar, Patna, for the construction of Vidhayak Awasan (MLA Parisar). The work was to commence on May 2, 2017, with a completion deadline of May 2, 2019. The petitioner claims the work was hampered by various issues including encroachment, tree removal, lack of drawings, underground utilities, demonetization, sand supply ban, GST implementation, COVID-19 pandemic, irregular payments, and drawing changes. Despite requests for outstanding dues and time extension, the agreement was rescinded by an office order dated July 2, 2020, issued by the Executive Engineer. The petitioner sought to set aside this order and requested a 12-month extension to complete the remaining work.
Key Issues
1. Whether the rescission of the agreement by the Executive Engineer, without issuing a show cause notice to the petitioner, violates the principles of natural justice and Clause 14 of the contract, rendering the order illegal and void? 2. Whether the Executive Engineer, in rescinding the contract, failed to apply his independent mind and exercised his judgment based on departmental directions rather than his own assessment? Petitioner's Arguments: - The rescission order is illegal and void for non-compliance with Clause 14 of the contract, which mandates a written notice prior to cancellation, and for violating the principles of natural justice, which are inherent in Article 14 of the Constitution. - Substantial work has been completed, and the petitioner undertakes to finish the remaining work within twelve months. - Relied on judgments in Kems Services Pvt. Ltd. vs. South Bihar Power Distribution Company Ltd. & Ors. and B.K. Enterprises, Dhanpura, Ara v. State of Bihar to support the court's power to direct completion within a stipulated time and the importance of considering financial consequences. - The Executive Engineer acted on departmental directions and did not apply his independent mind. Revenue/State's Arguments: - Not recorded in the judgment.
Sections Cited
Section 14 of the Contract (referred to as Clause 14)
AI-generated summary — verify with the full judgment below
IN THE HIGH COURT OF JUDICATURE AT PATNA Civil Writ Jurisdiction Case No.7234 of 2020 ====================================================== Kashish Developers Limited Registered Office at-87 Old AG Colony, Kadru, Ranchi, Jharkhand-834002, Local Address at-201, Kamla Sadan Apartment, Punai Chak, District-Patna, through its Director Mukesh Kumar, aged about 45 years, Gender-Male, Son of Sri Mukut Prasad Rao, Resident of 171, Mushahari, Bijbaniya, P.S.-Lauriya, West Champaran, District-West Champaran. ... ... Petitioner/s Versus
The State of Bihar through the Principal Secretary-cum-Commissioner, Building Construction Department, Government of Bihar, Patna.
The Engineer-in-Chief-cum-Additional
Commissioner-cum-Special Secretary, Building Construction Department, Government of Bihar, Patna.
The Chief Engineer, Building Construction Department, Government of Bihar, Patna.
The Superintending Engineer Construction Division No. 2, Building Construction Department, Bihar, Patna.
The Executive Engineer, Construction Division No. 2, Building Construction Department, Bihar, Patna. ... ... Respondent/s ===========================================
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Patna High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.