Ram Balak Singh Construction PVT. LTD. vs. The State Of Bihar
Facts
The petitioner, Ram Balak Singh Construction Pvt. LTD., filed a writ petition seeking directions for payment of work done under agreement no. 01-F2/13-14 SCP (4515), including a 5-year maintenance period. The petitioner also sought payment considering the increase in GST rate from 12% to 18% and the applicability of GST provisions. Further, they requested payment of the entire amount with penal interest and litigation costs. The petitioner's counsel prayed for the petition to be disposed of in terms similar to a previous judgment in CWJC No. 13024 of 2022 (M/s. Raghoji House of Distribution Vs. The State of Bihar & Ors.). The respondents did not file a response, and the dispute remained unresolved. The Court noted that the dispute could have been resolved under the Bihar State Litigation Policy, 2011.
Held
The Court did not adjudicate the claims on merits, leaving them open for the concerned authority to decide in accordance with the law and principles of natural justice. The petition was disposed of in terms of the judgment in M/s. Raghoji House of Distribution (Supra), with directions that would govern this case mutatis mutandis. Specifically, Respondent No. 6, the Executive Engineer, Rural Works Department, was directed to examine the petitioner's case and ensure an early decision and disbursement of legitimate dues, if any, within two months. Failure to comply would result in a cost of Rs. 5,000/- to be recovered from the officer's personal salary. Respondent No. 3, the Engineer-in-Chief, was directed to ensure an effective grievance redressal mechanism, preferably on a digital platform, and to inform the public about its availability. Failure to comply with these directions would lead to proceedings for deliberate violation and potential stoppage of salary. The Court clarified that all issues on merit, facts, and law were left open for the decision-making authority. Liberty was reserved for parties to initiate fresh action if needed, and Respondent No. 6 was to file an affidavit of compliance within three months.
Key Issues
1. Whether the petitioner is entitled to payment for the work done and successfully completed under agreement no. 01-F2/13-14 SCP (4515), including the maintenance period, and if so, what is the quantum of such payment? 2. Whether the payment should account for the increase in GST rate from 12% to 18% and the applicability of GST provisions to the work done? 3. Whether the petitioner is entitled to penal interest on the outstanding amount from the date it became due until the date of actual payment? 4. Whether the petitioner is entitled to litigation costs? Petitioner's arguments: The petitioner argued that they have completed the work to the satisfaction of the respondent authorities and are entitled to full payment. They also contended that the payment should include the increased GST rate and that they are entitled to penal interest and litigation costs due to the respondents' failure to make timely payments. They relied on the prayer to dispose of the case in terms of the judgment in M/s. Raghoji House of Distribution. Revenue/State's arguments: No specific arguments were recorded for the respondents in the provided text. However, the Court referenced the Bihar State Litigation Policy, 2011, and Section 89 of the Code of Civil Procedure, 1908, suggesting a potential avenue for dispute resolution that the State might have utilized.
Sections Cited
Section 89
AI-generated summary — verify with the full judgment below
IN THE HIGH COURT OF JUDICATURE AT PATNA Civil Writ Juri iction Case No.16083 of 2022 ====================================================== Ram Balak Singh Construction Pvt. LTD., through its Director Santosh Kumar Singh, Male aged about 43 Years S/o-Ram Balak Singh, R/o-Sri Krishna Nagar, Ward no.-23, P.O. and P.S.-Begusarai, District-Begusarai. ... ... Petitioner/s Versus
The State of Bihar through Principal Secretary Rural Works Department, Government of Bihar, Patna.
The Principal Secretary, Rural Works Department, Government of Bihar, Patna.
The Engineer-in-Chief, Rural Works Department, Government of Bihar, Patna.
The Chief Engineer-3, Rural Works Department, Government of Bihar, Patna.
The Superintending Engineer, Rural Works Department, Work Circle, Samastipur.
The Executive Engineer, Rural Works Department, Work Division, Manjhaul, Bakhri. ... ... Respondent/s ====================================================== Appearance : For the Petitioner/s : Mr.Alok Ranjan, Advocate For the Respondent/s : Mr.Ajay ( GA 5 ) ====================================================== CORAM: HONOURABLE THE CHIEF JUSTICE and HONOUR
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Patna High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.