The Board Of Major Port Authority For The Shama Prasad Mookerjee Port, Kolkata And Anr. vs. Haryana Micro And Small Eneterprises Facilitation Council (Hmsefc), Panchkula And Ors.
Facts
The petitioners, the Board of Major Port Authority for the Syama Prasad Mookerjee Port, Kolkata, issued an e-tender for architectural services. Respondent No. 4 submitted a bid and was awarded a work order on April 21, 2022, for Rs. 12,50,000 plus applicable GST. Respondent No. 4 submitted a first R.A. Bill for Rs. 2,95,000, which was paid. However, Respondent No. 4 allegedly failed to submit all required deliverables as per the tender document. Despite several communications and a show cause notice, the petitioners found the reply unsatisfactory and issued a termination order on March 25, 2025. Respondent No. 4 did not challenge this termination order but instead filed an application before the Haryana Micro and Small Enterprises Facilitation Council (HMSEFC) under Section 18(1) of the MSMED Act, 2006, claiming Rs. 18,40,800.
Held
The Court held that the Micro and Small Enterprises Facilitation Council (MSMED Council) is not the appropriate forum to decide issues related to the termination of a contract. The petitioners had not challenged the termination order before any court of law. The Court found that the respondent supplier had not completed the work as per the scope, had not supplied any goods to the petitioners, and had not raised any claim or final R.A. bill for dues payable prior to filing the application before the MSMED Council. Consequently, the Court concluded that the proceedings initiated by the respondent before the MSMED Council under Section 18(1) of the MSMED Act, 2006, were not maintainable. The Court set aside and quashed the proceedings before the MSMED Council. The writ petition was allowed.
Key Issues
1. Whether the Haryana Micro and Small Enterprises Facilitation Council (HMSEFC) has the jurisdiction to entertain a reference under Section 18(1) of the MSMED Act, 2006, when the petitioner has terminated the contract and the termination order has not been challenged by the respondent supplier? (Section 18(1) of MSMED Act, 2006). The petitioner argued that the HMSEFC lacks jurisdiction because the contract was terminated and the termination order was not challenged. They contended that there are no amounts due and payable to the respondent, and thus, the application under Section 18(1) is not maintainable. The respondent did not appear to present their arguments. 2. Whether any amount is due and payable by the petitioners to the respondent supplier under the contract or the MSMED Act, 2006, considering the alleged non-completion of work and the termination of the contract? (Sections 15, 17, and 18 of MSMED Act, 2006). The petitioner argued that no amount is due as the respondent failed to complete the work and did not submit any final R.A. bills prior to the show cause notice. The respondent did not appear to present their arguments.
Sections Cited
Section 18(1), Section 17, Section 16, Section 15, Section 2(d), Section 2(f), Section 2(n)
AI-generated summary — verify with the full judgment below
IN THE HIGH COURT AT CALCUTTA (Constitutional Writ Juri iction) APPELLATE SIDE
Present: The Hon’ble Justice Krishna Rao
W.P.A. No. 26463 of 2025
The Board of Major Port Authority for the Syama Prasad Mookerjee Port, Kolkata & Anr. Vs. Haryana Micro and Small Enterprises Facilitation Council (HMSEFC), Panchkula & Ors.
Mr. Kishore Datta, Sr. Adv. Mr. Ashok Kumar Jena
....For the petitioners.
Hearing Concluded On : 22.09.2026 Judgment Delivered On : 05.10.2026 Judgment Uploaded On : 05.10.2026 Krishna Rao, J.:
The petitioners have filed the present writ petition challenging the juri iction of the Haryana Micro and Small Enterprises Facilitation
2
Council (hereinafter referred to as “HMSEFC”) to make the reference and in issuing the letter dated 3rd July, 2025 by the respondent no.3 on behalf of the respondent no.2 by invoking Section 18(1) of the MSMED Act, 2006. 2. The petitioners floated an E-tender notice on 18th August, 2021 for engagement of architect for comprehensive architectural services towards interior and exterior modification of Jawahar Tower Complex and its allied areas at Haldia
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Calcutta High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.