Punia Construction vs. Union Of INDIA/Northern Railway

ARB.P./1569/2024HC DelhiGSTCNR DLHC01067816202422 November 2024Bench: HON'BLE MR. JUSTICE SACHIN DATTA11 pages
For Petitioner: Mr. Himanssu Upadhyay and Ms. Ruby Sharma, AdvsFor Respondent: Ms. Irammajid, CGSC and Mohd Suboor, Advs
AI SummaryAllowed

Facts

The petitioner, Punia Construction, entered into an agreement with Northern Railway on March 31, 2021, for the construction of a road over bridge and allied works. The petitioner claims to have faced significant hindrances during execution, leading to delays and losses. The work, initially scheduled for completion by May 2021, was completed on September 20, 2023. The petitioner intended to raise several claims, including machinery rent, engineering staff costs during the extended period, U-shape retaining wall construction, head office expenses, design alteration expenses, GST neutralization, and other contractual claims. The contract contained an arbitration clause. The petitioner filed a petition under Section 11 of the Arbitration and Conciliation Act, 1996, seeking the appointment of an Arbitral Tribunal to adjudicate these disputes.

Held

The Court held that the appointment procedure envisaged in Clause 64 of the conditions of contract, which involves appointment from a panel maintained by the Railways, is no longer a valid procedure for appointing an arbitral tribunal under Section 11 of the Arbitration and Conciliation Act, 1996. The Court reasoned that the appointment of an independent arbitral tribunal is incumbent upon the Court at this stage. Furthermore, the Court found that the technical nature of the dispute and the requirement for domain expertise do not justify restricting the choice of arbitrators to the Railways' panel or serving officers. The Court relied on its previous decision in M/s. M.V. Omni Projects (India) Ltd v. Union of India, where an independent sole arbitrator was appointed in similar circumstances. Consequently, the Court appointed Mr. R. K. Aggarwal, Retd. Spl. DG, CPWD, as the Sole Arbitrator to adjudicate the disputes. The respondent is permitted to raise objections regarding jurisdiction and arbitrability, including pre-arbitral procedure adherence, before the arbitrator. All claims and counter-claims are to be decided on their merits by the arbitrator. The Court explicitly stated that its order does not express any opinion on the merits of the case.

Key Issues

1. Whether the appointment procedure envisaged in Clause 64 of the conditions of contract, which contemplates appointment from a panel maintained by the Railways, is a valid procedure for appointing an arbitral tribunal under Section 11 of the Arbitration and Conciliation Act, 1996? (Question of law) 2. Whether the technical nature of the dispute and the need for domain expertise necessitate restricting the choice of arbitrators to the panel maintained by the Railways or to serving officers of the Railways? (Question of law) The petitioner argued that the arbitration agreement is not disputed and that the Court should appoint an independent arbitral tribunal. They relied on the principle that at the stage of Section 11, the Court's scope of enquiry is limited to the prima facie existence of an arbitration agreement, citing SBI General Insurance Co. and In Re: Interplay. The petitioner also referred to a previous judgment of this Court in M/s. M.V. Omni Projects (India) Ltd v. Union of India, where an independent sole arbitrator was appointed despite a similar arbitration clause. The respondent (Union of India/Northern Railway) did not record any specific arguments against the appointment of an arbitrator in the judgment.

Sections Cited

Section 11, Section 12

AI-generated summary — verify with the full judgment below

$~21 * IN THE HIGH COURT OF DELHI AT NEW DELHI %

Date of Decision: 22.11.2024

+ PUNIA CONSTRUCTION

.....Petitioner Through: Mr. Himanssu Upadhyay and Ms. Ruby Sharma, Advs.

versus

UNION OF INDIA/NORTHERN RAILWAY .....Respondent Through: Ms. Irammajid, CGSC and Mohd Suboor, Advs.

CORAM:

HON'BLE MR. JUSTICE SACHIN DATTA

1.

The present petition under Section 11 of the Arbitration and Conciliation Act, 1996 (hereinafter ‘the A&C Act’) seeks constitution of an Arbitral Tribunal to adjudicate the disputes between the parties. SACHIN DATTA, J. (ORAL)

2.

The disputes between the parties have arisen in the context of an agreement dated 31.03.2021 for “Construction of 2 lane Road Over Bridge 1x52.926 metre centre to centre of bearing (overall length 55.834 metre) with steel composite girder at skew angle 65 12’00” including construction of approaches using reinforced earthwall, roads, retaining / boundary wall, diversion of road and other allied works at km 68.110 on crossing Hansi- Tosham Road (SH-12) on Roh

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Delhi High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.