Govt Of Nct Of Delhi vs. M/S Harbel Singh And Sons
Held
The Court held that the Arbitrator's findings on all preliminary issues were plausible and supported by material and submissions. Regarding Issue No. 1, the Arbitrator correctly held that the claims were within limitation, considering Section 28 of the Indian Contract Act, the Limitation Act, COVID-19 exclusions, and judicial pronouncements. The undertaking on the EOT proforma was rightly deemed not voluntary and given under duress due to withheld amounts. On Issue No. 2, the Arbitrator correctly found that merely signing the final bill did not amount to a final settlement, as amounts were withheld. On Issue No. 3, the Arbitrator correctly concluded that since the agreement contained an EOT clause, time was not the essence, and thus, a notice under Section 55 of the Indian Contract Act was not necessary for claiming compensation under Section 73. The Court found that the Arbitrator meticulously considered all evidence and submissions, and its interpretation of the contract was a plausible view, not amounting to patent illegality or perversity. The Court declined to interfere with the Arbitral Award, upholding the Arbitrator's jurisdiction over contract interpretation and evidence. The declaratory award regarding GST reimbursement was also upheld, as it was based on the contract and the potential liability of the claimant.
Facts
The Government of NCT of Delhi (Petitioner) challenged an Arbitral Award dated April 19, 2024, passed by a Sole Arbitrator. The dispute arose from a construction contract awarded to M/s Harbel Singh and Sons (Respondent) on February 27, 2016. The work was completed with a delay of approximately 14 months, but the Petitioner granted an Extension of Time (EOT) up to October 3, 2017, without levying compensation. The Respondent raised disputes regarding amounts due, which were referred to arbitration. The Petitioner challenged specific claims allowed by the Arbitrator, including those related to substituted items, extra items, and escalation, arguing they were awarded without cogent reasoning and in contravention of the contract. The Arbitrator had also made a declaratory award regarding Goods and Services Tax (GST) on the awarded sums.
Key Issues
1. Whether the Arbitrator erred in holding that the Respondent's claims were within the limitation period, despite the Petitioner's contention that Clause 25 of the Agreement prescribed a 120-day limitation period, and whether the undertaking given by the Respondent on the EOT proforma, surrendering claims, was binding? 2. Whether the Arbitrator correctly concluded that the final bill acceptance by the Claimant did not signify a full and final settlement of all claims? 3. Whether a notice under Section 55 of the Indian Contract Act was necessary to claim compensation under Section 73 of the Indian Contract Act, given the EOT clause in the agreement? Petitioner's Arguments: The Petitioner argued that the Arbitrator's award was contrary to public policy and that frivolous claims were allowed without cogent reasoning. Specifically, it contended that an amount of Rs. 1,13,22,658/- awarded for a substituted item was arbitrary, based on inflated rates, and rewrote the agreement terms. It also argued that Claim No. 2.3 for escalation was awarded despite no provision in the agreement for such compensation. Respondent's Arguments: The Respondent argued that the claims were within limitation, supported by Section 28 of the Contract Act and judicial pronouncements. They contended that the undertaking on the EOT proforma was given under duress due to withheld payments and was therefore not voluntary. They also argued that signing the final bill did not constitute a final settlement. Regarding Section 55 of the Contract Act, they relied on judgments to argue that notice was not required when time was not the essence of the contract.
Sections Cited
Section 34, Section 12, Section 12(5), Section 28, Section 55, Section 73, Section 31(7)(a), Section 28(1)
AI-generated summary — verify with the full judgment below
Cause title — parties, addresses and appearances
JUDGMENT
The present petition under Section 34 of the Arbitration and Conciliation Act, 1996 has been filed by the Petitioner challenging the Impugned Arbitral Award dated 19.04.2024 passed by the learned Sole Arbitrator.
Shorn of unnecessary details, the facts leading to the filing of present petition are as under:- a. The Petitioner floated a Tender for Construction of Additional classrooms in existing premises under jurisdiction under EO Zone-24 of DDE (South) (Priority-I) SH: C/o SPS type Classroom
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Delhi High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.