Held

The Court held that the Arbitral Tribunal (AT) was correct in rejecting the petitioner's claim for liquidated damages (LD). The AT rightly found that Clauses 8.7 and 14.15(b) of the GCC were not a genuine pre-estimate of damages, as there was no evidence of mutual estimation by the parties. The AT's view that unilateral adjustment of LD by the petitioner was impermissible was also upheld. The Court found this reasoning consistent with settled legal principles on LD and beyond reproach under Section 34 of the Arbitration & Conciliation Act. Regarding Counter Claim No. 1 for "Loss to Exchequer on account of Car Parking Charges," the AT's rejection was also upheld. The AT correctly noted the lack of evidence to establish any loss of parking charges earnings by the petitioner. The AT also rightly observed that the petitioner, a society, had not established a sufficient link to the Government of Jammu and Kashmir to claim loss to the public exchequer. Furthermore, the AT correctly held that the petitioner could not claim both LD and additional compensation for loss of parking charges, as this would amount to double recovery. The Court found no legal anomaly in the AT's reasoning.

Facts

The petitioner, Jammu & Kashmir Economic Reconstruction Agency, filed a petition under Section 34 of the Arbitration & Conciliation Act, 1996, seeking to set aside parts of an arbitral award dated 13.07.2024. The dispute arose from a contract for the construction of a multi-storied mechanized parking facility in Srinagar. The construction was completed on 30.04.2017, significantly after the stipulated completion date. The respondent, M/s Simplex Projects Limited, filed claims before the Arbitral Tribunal (AT), and the petitioner raised counter-claims. The AT dealt with several claims and counter-claims, including claims for outstanding payments, price adjustment, refund of excess deduction, service tax reimbursement, return of security deposit, and loss due to unrest. The petitioner also claimed liquidated damages (LD) and loss of earnings from parking charges.

Key Issues

1. Whether the Arbitral Tribunal (AT) erred in rejecting the petitioner's claim for liquidated damages (LD) on account of delay, by holding that Clause 8.7 and 14.15(b) of the General Conditions of Contract (GCC) were not a genuine pre-estimate of damages and that unilateral adjustment was impermissible? - Petitioner's argument: Not explicitly recorded. - Revenue/State's argument: The AT correctly interpreted the clauses and the law on LD, finding no evidence of mutual estimation of damages by the parties and that unilateral adjustment was not permissible. The AT's view is consistent with settled legal principles. 2. Whether the AT erred in rejecting the petitioner's Counter Claim No. 1 for "Loss to Exchequer on account of Car Parking Charges"? - Petitioner's argument: The AT wrongly observed that delay in construction of public facilities does not cause loss and that the petitioner, as an agency of the Government, could claim loss to the public exchequer. - Revenue/State's argument: The AT correctly rejected the claim due to lack of evidence of any loss suffered by the petitioner in the form of lost parking charges earnings. The AT also noted the lack of evidence linking the petitioner society to the Government of Jammu and Kashmir to claim loss to the public exchequer. Furthermore, the AT held that the petitioner could not claim both LD and additional compensation for loss of parking charges as it would amount to double recovery.

Sections Cited

Section 34

AI-generated summary — verify with the full judgment below

Cause title — parties, addresses and appearances
O.M.P. (COMM) 60/2025 Page 1 of 17 * IN THE HIGH COURT OF DELHI AT NEW DELHI % Reserved on : 03.02.2025 Pronounced on : 19.05.2025 + O.M.P. (COMM) 60/2025, I.A. Nos. 2873-74/2025 JAMMU & KASHMIR ECONOMIC RECONSTRUCTION AGENCY .....Petitioner Through: Mr. Praveen Chauhan, Mr. Parth Awasthi, Ms. Malvica Satija, Mr. Sarthak Swahney and Mr. Parth Sen, Advocates. versus M/S SIMPLEX PROJECTS LIMITED .....Respondent Through: Mr. S.D. Singh, Mr. K. Prasad, Ms. Swetha Sinha, Mr. Siddharth Singh and Ms. Meenu Singh, Advocates. CORAM: HON'BLE MR. JUSTICE MANOJ KUMAR OHRI

JUDGMENT

1.

The present petition is instituted under Section 34 of the Arbitration & Conciliation Act, 1996 (hereinafter, referred to as the „A&C Act‟) thereby seeking part setting aside of the arbitral award dated 13.07.2024 (hereinafter, „impugned award‟) delivered by the Arbitral Tribunal comprising of Sole Arbitrator (hereinafter, „AT‟) in respect of Issue Nos. 1 and 2 as framed by the AT.

2.

The impugned award came to be delivered in the cont

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Delhi High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.