Gail (INDIA) Limited vs. Petron Engineering Construction Limited (Through Official Liquidator)
Held
The Court held that the Arbitrator was justified in allowing the Respondent's claim for the final bill and that the deduction on account of PRS was unlawful and unjustified. The Court agreed with the Arbitrator's reliance on the E-in-C's final analysis, which concluded that the delays in completing the project were concurrent with delays not solely attributable to the Respondent. The E-in-C's recommendation to grant final extension of time without imposing PRS was accepted by the Arbitrator. The Court found that Clause 27 of the contract could only be invoked if the delay was solely attributable to the Respondent, which was not the case. The Petitioner's argument that the release of the BG implied an intention not to impose PRS was also considered, and the Arbitrator's finding that the Petitioner did not intend to impose PRS was upheld. Regarding interest, the Court held that the Arbitrator had the discretion under Section 31(7) of the Arbitration and Conciliation Act, 1996, to decide the period and rate of interest, and the awarded interest did not shock the conscience of the Court. Therefore, no ground for interference was made out.
Facts
GAIL (India) Limited (Petitioner) filed a petition under Section 34 of the Arbitration and Conciliation Act, 1996, seeking to set aside an arbitral award dated 09.05.2023 and an order dated 19.06.2023 passed by the sole Arbitrator. The Respondent, Petron Engineering Construction Limited (in liquidation), was the Claimant before the Arbitrator. The dispute arose from a Contract Agreement dated 21.05.2012 for the expansion of GAIL's petrochemical complex. The Respondent claimed Extended Stay Compensation (ESC) and other charges. The Petitioner insisted on additional work and denied delays on its part. The Respondent raised claims for its final bill, including escalation, fire-proofing, ESC, and reimbursement of excise duty. The Engineer-in-Charge (E-in-C) provided an analysis of delays, noting concurrent delays and recommending extension of time without levying penalty. The Arbitrator allowed the final bill to an extent, holding deductions on account of penalty unlawful.
Key Issues
1. Whether the Arbitrator was justified in allowing the Respondent's claim for the final bill, specifically regarding the deduction of Penalty for delayed work (PRS) and the award of interest, considering the Petitioner's contention that the delay was solely attributable to the Respondent? Petitioner's arguments: The Petitioner argued that the Respondent was responsible for delays, citing earlier communications from the E-in-C. They contended that the Arbitrator should have considered these initial delays and that the Petitioner had reserved its right to invoke the PRS clause. The Petitioner also argued that the release of the Bank Guarantee (BG) did not necessarily imply an intention not to impose PRS. Respondent's arguments: The Respondent relied on the E-in-C's final analysis, which concluded that delays were concurrent and not solely attributable to the contractor, recommending the grant of final time extension without PRS. They also argued that the Petitioner's failure to plead that PRS was being levied after the contractual completion date was fatal to their claim. The Respondent further contended that the Arbitrator's discretion in awarding interest under Section 31(7) of the Act was not to be interfered with unless it shocked the conscience.
Sections Cited
Section 34, Section 33, Section 31(7), Clause 27
AI-generated summary — verify with the full judgment below
O.M.P. (COMM) 445/2023 and connected matters
$~ * IN THE HIGH COURT OF DELHI AT NEW DELHI %
Date of Decision: 18th August, 2025 + O.M.P. (COMM) 445/2023 and I.A. 21460/2023
GAIL (INDIA) LIMITED
.....Petitioner Through: Mr. Rajshekhar Rao, Senior Advocate with Mr. Debesh Panda, Ms. Meherunissa Anand, Ms. Nivedita Jha and Mr. K. Sri Aditya, Advocates.
versus
PETRON ENGINEERING CONSTRUCTION LIMITED (THROUGH OFFICIAL LIQUIDATOR)
.....Respondent Through: Mr. Sandeep Bajaj, Mr. Soayib Qureshi, Mr. Mayank Biyani and Ms. Anchal Singh, Advocates.
+ O.M.P. (COMM) 447/2023 and I.A. 21465/2023
GAIL (INDIA) LIMITED
.....Petitioner Through: Mr. Rajshekhar Rao, Senior Advocate with Mr. Debesh Panda, Ms. Meherunissa Anand, Ms. Nivedita Jha and Mr. K. Sri Aditya, Advocates.
versus
PETRON ENGINEERING CONSTRUCTION LIMITED (THROUGH OFFICIAL LIQUIDATOR)
.....Respondent Through: Mr. Sandeep Bajaj, Mr. Soayib Qureshi, Mr. Mayank Biyani and Ms. Anchal Singh, Advocates.
+ OMP (ENF.) (COMM.) 258/2023, EX.APPL.(OS) 1721/2023, 1722/2023, 1723/2023 and 1724/2
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Delhi High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.