Union Of INDIA vs. M/S Sh. S.S. Chauhan And Sons

/2720/2025HC RajasthanGSTCNR RJHC02050546202528 August 2025Bench: SANJEEV PRAKASH SHARMA,SANJEET PUROHIT17 pages
AI SummaryDismissed

Held

The Court held that the grounds raised by the appellant did not fall within the scope and ambit of Section 34 read with Section 37 of the Arbitration & Conciliation Act, 1996. The Court found no patent illegality or violation of public policy in the arbitral award. It affirmed the Arbitrator's factual findings regarding hindrances and delays attributable to the appellant, stating that such findings, based on appreciation of evidence, cannot be interfered with. The Court also held that the Arbitrator's quantification of claims, including loss of opportunity, profit, and overhead charges, was done holistically and using the pro rata assessment as per the Hudson formula, which is approved by the Supreme Court. The issues regarding the delay in issuing the layout plan and the 500 M GSB were also considered factual and not open for interference. The Court concluded that the appellant failed to demonstrate any misconduct by the Arbitrator or misinterpretation of contract clauses. The Commercial Court's concurrence with the Arbitrator's findings was also noted. The appeal was dismissed.

Facts

The Union of India (appellant) appeals a Commercial Court's dismissal of its Section 34 application, which sought to set aside an arbitral award in favour of M/s S.S. Chauhan and Sons (respondent). The dispute arose from a contract for construction work awarded to the respondent in 2016. The respondent claimed delays and hindrances, including issues with drawings, approach roads, river sand availability, and delayed payments, which impacted work completion. The appellant terminated the contract in 2018. The respondent raised claims, which were initially considered by a Disputes Redressal Committee. Subsequently, the Chief Engineer levied compensation. The respondent invoked arbitration, and the Sole Arbitrator partially allowed the claims, awarding Rs.92,03,080/- plus GST and future interest, finding delays attributable to the appellant. The Commercial Court upheld the award, and the appellant filed this appeal.

Key Issues

1. Whether the arbitral award suffers from patent illegality or violation of public policy of Indian law, as contemplated under Section 34 of the Arbitration & Conciliation Act, 1996, warranting interference under Section 37 of the Act? Appellant's Arguments: The appellant contended that the Arbitrator committed misconduct by re-appreciating evidence and interfering with factual findings, particularly regarding the quantification of claims like loss of opportunity, profit, and overhead charges. They argued that the Arbitrator erred in interpreting contract clauses and that the award was based on no evidence or misinterpretation. The appellant also questioned the Arbitrator's findings on delay and the closure of the approach road. Respondent's Arguments: The respondent argued that the Arbitrator's findings on delays, hindrances, and the appellant's role in causing them were based on a holistic consideration of evidence and contract terms. They contended that the Arbitrator correctly applied the Hudson formula for calculating damages and that the grounds raised by the appellant do not fall within the limited scope of Section 34 or Section 37 of the Act.

Sections Cited

Section 37, Section 34

AI-generated summary — verify with the full judgment below

Cause title — parties, addresses and appearances
[2025:RJ-JP:33375-DB] HIGH COURT OF JUDICATURE FOR RAJASTHAN BENCH AT JAIPUR D.B. Civil (Commercial) Miscellaneous Appeal No. 2720/2025 Union of India, through Executive Engineer, Jaipur Central Division-I, CPWD, Kendriya Sadan, Block-A, Room Number-110, Sector-10, Vidhya Nagar, Jaipur, Jaipur-302039. ----Appellant/ Non-Claimant Versus M/s Sh. S.S. Chauhan and Sons, G-140/9, Sangam Vihar, New Delhi-110062. E-Mail- Ashok9999741479@gmail.com. ----Respondent/ Claimant For Appellant(s) : Mr. Ashish Kumar For Respondent(s) : Mr. Sarvesh Jain HON'BLE MR. JUSTICE SANJEEV PRAKASH SHARMA HON'BLE MR. JUSTICE SANJEET PUROHIT

Order Reportable RESERVED ON:- 19/08/2025 PRONOUNCED ON:- 28/08/2025 Per, HON’BLE MR. SANJEET PUROHIT, J:

1.

The present Appeal under Section 37 of the Arbitration & Conciliation Act, 1996 (for brevity “Act of 1996”) is filed being aggrieved of the judgment dated 17.03.2025 passed by the learned Judge, Commercial Court No.3, Jaipur Metropolitan-II, whereby the Objection Application No.81/2024 filed by the appellant/non-claimant preferred under Section 34 of the Act of 1996 has been dismissed and the award dated 15.11.2022 passed by the learned Sole Arbitrator in fa

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Rajasthan High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.