Suresh Chandra Dash vs. State Of Odisha
Held
The Court held that while writ jurisdiction should generally be exercised with restraint in contractual matters, as reiterated by the Supreme Court in Tata Motors Limited vs. The Brihan Mumbai Electric Supply & Transport Undertaking (BEST) and Others, this restraint does not preclude the Court from directing the competent authority to examine a claim that has already been processed and approved by departmental authorities. The Court acknowledged the Petitioner's assertion that the work was completed and the price adjustment/escalation was computed and approved by Opposite Party No.4. The Court found it necessary for the competent authority to examine whether the computed amount is presently payable and if any further contractual or statutory requirements remain. Therefore, the Court directed Opposite Party No.4, the Superintending Engineer (R&B) Division, Sonepur, to consider the Petitioner's claim for price adjustment/price escalation under Clause 31 of the agreement, including the already computed and approved calculation. The authority is to examine any remaining requirements for disbursement and, if found payable, take consequential steps for its release within four weeks, communicating a reasoned decision to the Petitioner. The Court explicitly stated it was not expressing any opinion on the entitlement or quantum of the Petitioner's claim.
Facts
The Petitioner, Suresh Chandra Dash, entered into an agreement on 21.12.2020 with the Opposite Parties for the construction of an Academic Building for Sonepur College, with an agreement value of ₹3,03,05,065/- excluding GST. The work was completed by 20.09.2021, and a completion certificate was issued. The Petitioner's grievance is the non-disbursement of the price adjustment/price escalation amount payable under Clause 31 of the agreement. The Superintending Engineer, R&B Division, Sonepur (Opposite Party No.4), had computed and approved this amount on 10.02.2022, but it has not been released. The Petitioner contends that this is a contractual claim for an already computed and approved amount, not a fresh or disputed claim.
Key Issues
1. Whether the High Court, exercising writ jurisdiction, should intervene in a contractual dispute concerning the disbursement of an already computed and approved price adjustment/escalation amount, particularly when the Petitioner is not seeking adjudication of a fresh or disputed contractual claim? (Mixed question of law and fact, turning on the principles of judicial review in contractual matters and the scope of Article 226 of the Constitution of India). Petitioner's argument: The Petitioner is not seeking to adjudicate a new or disputed contractual claim. Instead, the Petitioner seeks the disbursement of a price adjustment/escalation amount that has already been computed and approved by the competent departmental authority (Opposite Party No.4) as per Clause 31 of the agreement. The Petitioner argues that despite completion of work and approval of the escalation amount, they have been deprived of the benefit without justifiable reason. Revenue/State's argument: The judgment records no specific arguments from the Opposite Parties regarding the Petitioner's claim. However, the Court's reasoning references the principles laid down by the Supreme Court in cases like Tata Motors Limited vs. The Brihan Mumbai Electric Supply & Transport Undertaking (BEST) and Others, which generally advocate for restraint by writ courts in contractual matters unless gross or palpable errors are pointed out or overwhelming public interest requires interference.
Sections Cited
Clause 31
AI-generated summary — verify with the full judgment below
Cause title — parties, addresses and appearances
2026
1. Heard learned counsel for both the Parties.
The Petitioner had entered into an agreement dated 21.12.2020 with the Opposite Parties for the work of construction of an Academic Building for Sonepur College at Sonepur in the District of Subarnapur for the year 2020-21 under World Bank Assistance OPHEE Phase-I. The agreement value was ₹3,03,05,065/-, excluding GST, with the stipulated date of completion being 20.11.2021. The work was, however, completed by the Petitioner on 20.09.2021 and a completion certificate was issued in his favour.
The grievance of the Peti
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.