Suresh Chandra Dash vs. State Of Odisha

WP(C)/27482/2026HC OrissaGSTCNR ODHC01065153202630 September 2026Bench: MR. JUSTICE HARISH TANDON (CJ),MR. JUSTICE CHITTARANJAN DASH4 pages
AI SummaryRemanded

Held

The Court held that while writ courts ordinarily refrain from interfering in contractual matters and tender awards, as reiterated by the Supreme Court in Tata Motors Limited vs. The Brihan Mumbai Electric Supply & Transport Undertaking (BEST) and Others, this restraint does not preclude the Court from directing the competent authority to examine a claim that has already been processed and acknowledged by departmental authorities under the terms of the contract. The Court noted that the Petitioner asserted completion of work and that price adjustment/escalation had been computed and approved by Opposite Party No.4. Therefore, the Court directed Opposite Party No.4, the Superintending Engineer (R&B) Division, Sonepur, to consider the Petitioner's claim for price adjustment/price escalation under Clause 31 of the agreement, including the calculation already made and approved. The authority is to examine whether any further requirements remain for disbursement and, if payable, take consequential steps. This exercise is to be completed within four weeks from the order's communication, with a reasoned decision to be communicated to the Petitioner forthwith. The Court explicitly stated it was not expressing any opinion on the entitlement or quantum of the claim.

Facts

The Petitioner, Suresh Chandra Dash, entered into an agreement on December 21, 2020, with the Opposite Parties for the construction of an academic building for AES College at Tarva, Subarnapur district, for ₹2,20,63,745 (excluding GST). The work was to be completed by September 20, 2021, and the Petitioner claims to have finished it within the stipulated period, obtaining a completion certificate. The Petitioner's grievance is the non-disbursement of the amount towards price adjustment/price escalation, computed and approved by the Superintending Engineer, R&B Division, Sonepur (Opposite Party No.4) on February 10, 2022, amounting to ₹20,36,627.97. The Petitioner contends this claim arises directly from Clause 31 of the agreement and is not a fresh or disputed contractual claim.

Key Issues

1. Whether the High Court, in its writ jurisdiction, should entertain a dispute arising from a contractual transaction concerning the release of price adjustment/escalation amounts already computed and approved by a departmental authority under Clause 31 of the agreement? Petitioner's Argument: The Petitioner argued that the claim arises directly from Clause 31 of the agreement and that they are not seeking adjudication of any fresh or disputed contractual claim, but rather the release of an amount that has already been computed and approved by the departmental authority. They are seeking enforcement of a contractual obligation that has been acknowledged by the respondent. Revenue/State's Argument: The judgment does not record any specific arguments made by the Opposite Parties (State of Odisha & others) regarding the Petitioner's claim. However, the Court's reliance on Supreme Court judgments concerning writ jurisdiction in contractual matters suggests an implicit argument that such matters are generally outside the purview of writ petitions.

Sections Cited

Clause 31

AI-generated summary — verify with the full judgment below

Cause title — parties, addresses and appearances
Page 1 of 4 IN THE HIGH COURT OF ORISSA AT CUTTACK WP(C) No.27482 of 2026 CNR No. ODHC010651532026 Suresh Chandra Dash …. Petitioner Mr. S. Agarwal, Advocate -Versus- State of Odisha & others …. Opp. Parties Mr. S. Rath, AGA CORAM: HON’BLE THE CHIEF JUSTICE AND HON’BLE MR. JUSTICE CHITTARANJAN DASH Order No.
30.09.

2026

02.

1. Heard learned counsel for both the Parties.

2.

The Petitioner had entered into an agreement dated 21.12.2020 with the Opposite Parties for the work of “Construction of Academic Building for AES College at Tarva in the District of Subarnapur under World Bank Assistance OPHEE Phase-I for the year 2020-21”. The agreement value was ₹2,20,63,745/-, excluding GST, with the stipulated date of completion being 20.09.2021. The Petitioner claims to have completed the work within the stipulated period and a completion certificate was thereafter issued.

3.

The grievance of the P

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.