M/S. Gvpr Engineering Limited- M/S Hes Infrastructure PVT. LTD. Jv. vs. State Of Rajasthan
Held
The Court held that the petitioner's bid was wrongly declared non-responsive. The Court found that the bid evaluation committee failed to adhere to the spirit of Rule 59(3) of the Rajasthan Transparency in Public Procurement Rules, 2013. While Rule 59(2)(c) defines 'omission' as failure to submit required information, the crucial aspect is whether such omission is 'material'. The committee is mandated to examine if an omission substantially affects the scope, quality, or performance of the procurement, limits the procuring entity's rights or the bidder's obligations, or unfairly affects the competitive position of other bidders. The Court noted that the respondents did not provide any material on record to demonstrate that the bid evaluation committee satisfied itself about these standards before declaring the bid non-responsive. The learned Single Bench had erred by not considering this aspect. Therefore, the order dated 29.06.2024 declaring the petitioner's bid non-responsive was quashed and set aside. The petitioner was declared a responsive bidder. Any subsequent actions, including the approval of respondent No. 4's financial bid, issuance of LOI, or execution of the agreement, were set aside. The respondents were directed to open and consider the petitioner's financial bid, and if found to be the lowest bidder and fulfilling other conditions, award the contract to the petitioner.
Facts
The petitioner, M/s GVPR Engineering Limited-M/s HES Infrastructure Pvt. Ltd. JV, filed a writ petition challenging an order dated 29.06.2024 by the Additional Chief Engineer, Projects, PHED, Bharatpur, which declared their bid non-responsive. The bid was for a project under NIB no. 10/2023-24 floated by the PHED department of Rajasthan. The petitioner's bid was deemed non-responsive due to not meeting the financial criteria concerning credit limit requirements, specifically the FIN-2 certificate submitted. The petitioner's appeal before the First Appellate Authority and subsequent second appeal were dismissed. The High Court had previously directed that further actions, including the issuance of a Letter of Intent, would be subject to the final outcome of this writ petition. A work order was issued on 03.09.2025, also subject to this Court's decision.
Key Issues
1. Whether the petitioner's bid was rightly declared non-responsive for failing to meet the financial criteria, specifically the credit limit requirement as per the tender document (Clause 1.3)? - Petitioner's Argument: The petitioner contended that as a joint venture, the lead partner (GVPR Engineering Limited) fulfilled the entire credit limit requirement of Rs. 192.65 Crores, having an available credit limit of Rs. 384.85 Crores. The other partner (HES Infra Pvt. Ltd.) was only required to satisfy 10% of the requirement, which it did with a Rs. 20 Crores credit facility, as evidenced by a Bank of India certificate. Although not strictly in FIN-2 format, the certificate sufficiently established compliance. The respondents erred by misconstruing the certificate and declaring the bid non-responsive without seeking clarification. - Revenue/State's Argument: The respondents argued that the FIN-2 certificate submitted by the petitioner was not in conformity with the tender document's requirements. The financial position ought to be reflected as on the date the bid was submitted, and the documents submitted on 04.02.2015 did not furnish complete and correct information. Rule 59 of the Rules of 2013 allows a bid evaluation committee to declare a bid non-responsive for omissions, and the petitioner failed to supply full details as required in Form Con 2 and details of unutilized credit balance as on the date of submission. 2. Whether the bid evaluation committee properly examined the petitioner's bid in accordance with the standards prescribed under sub-rule (3) of Rule 59 of the Rajasthan Transparency in Public Procurement Rules, 2013?
Sections Cited
Section 7, Rule 59
AI-generated summary — verify with the full judgment below
[2026:RJ-JP:27270] HIGH COURT OF JUDICATURE FOR RAJASTHAN BENCH AT JAIPUR S.B. Civil Writ Petition No. 14206/2024 URN: CW / 28734U / 2024 M/s. GVPR Engineering Limited- M/s HES Infrastructure Pvt. Ltd. JV., Through Its Authorised Signatory Mr. Sridhar Reddy, Office At 8-2-293/82/A, Plot No. 739-A, Road No. 37, Jubilee Hills, Hyderabad 33, Telangana, India ----Petitioner Versus
State Of Rajasthan, Through The Chief Secretary, Government Of Rajasthan, Jaipur (Raj.)
Secretary, Public And Health Engineering Department, Main Secretariat Building, Jaipur Rajasthan
Addl. Chief Engineer, Project, Public Health And Engineering Department, Project Division Bharatpur.
SPML-JWL JV, Through Its Authorised Signatory Jai Prakash Gupta S/o Dean Dayal Gupta, Having Its Place Of Business At Jindal ITF Centre, 28 Shvaji Marg, New Delhi- 110015 ----Respondents For Petitioner(s) : Mr. R.K. Agrawal, Senior Advocate assisted by Mr. Adhiraj Modi, Mr. Rakshit Jaimini, Mr. Daksh Pareek assisted by Mr. Arjun Singh, Mr. Ashish Kabra, Mr. Moin Khan For Respondent(s) : Mr. Rajendra Prasad, Advocate General assisted by Ms. Dhriti Ladha Ms. Mahi Yadav, Additional Advocate General assisted
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Rajasthan High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.