M/S. Gvpr Engineering Limited- M/S Hes Infrastructure PVT. LTD. Jv. vs. State Of Rajasthan

Original PDF →
CW/14206/2024HC RajasthanGSTCNR RJHC02075029202417 July 2026Bench: BIPIN GUPTA77 pages
AI SummaryAllowed

Facts

The petitioner, M/s GVPR Engineering Limited-M/s HES Infrastructure Pvt. Ltd. JV, filed a writ petition challenging an order dated 29.06.2024 by the Additional Chief Engineer, Projects, PHED, Bharatpur, which declared their bid non-responsive. The bid was for a project under NIB no. 10/2023-24 floated by the PHED department of Rajasthan. The petitioner's bid was deemed non-responsive due to not meeting the financial criteria concerning credit limit requirements, specifically the FIN-2 certificate submitted. The petitioner's appeal before the First Appellate Authority and subsequent second appeal were dismissed. The High Court had previously directed that further actions, including the issuance of a Letter of Intent, would be subject to the final outcome of this writ petition. A work order was issued on 03.09.2025, also subject to this Court's decision.

Held

The Court held that the petitioner's bid was wrongly declared non-responsive. The Court found that the bid evaluation committee failed to adhere to the spirit of Rule 59(3) of the Rajasthan Transparency in Public Procurement Rules, 2013. While Rule 59(2)(c) defines 'omission' as failure to submit required information, the crucial aspect is whether such omission is 'material'. The committee is mandated to examine if an omission substantially affects the scope, quality, or performance of the procurement, limits the procuring entity's rights or the bidder's obligations, or unfairly affects the competitive position of other bidders. The Court noted that the respondents did not provide any material on record to demonstrate that the bid evaluation committee satisfied itself about these standards before declaring the bid non-responsive. The learned Single Bench had erred by not considering this aspect. Therefore, the order dated 29.06.2024 declaring the petitioner's bid non-responsive was quashed and set aside. The petitioner was declared a responsive bidder. Any subsequent actions, including the approval of respondent No. 4's financial bid, issuance of LOI, or execution of the agreement, were set aside. The respondents were directed to open and consider the petitioner's financial bid, and if found to be the lowest bidder and fulfilling other conditions, award the contract to the petitioner.

Key Issues

1. Whether the petitioner's bid was rightly declared non-responsive for failing to meet the financial criteria, specifically the credit limit requirement as per the tender document (Clause 1.3)? - Petitioner's Argument: The petitioner contended that as a joint venture, the lead partner (GVPR Engineering Limited) fulfilled the entire credit limit requirement of Rs. 192.65 Crores, having an available credit limit of Rs. 384.85 Crores. The other partner (HES Infra Pvt. Ltd.) was only required to satisfy 10% of the requirement, which it did with a Rs. 20 Crores credit facility, as evidenced by a Bank of India certificate. Although not strictly in FIN-2 format, the certificate sufficiently established compliance. The respondents erred by misconstruing the certificate and declaring the bid non-responsive without seeking clarification. - Revenue/State's Argument: The respondents argued that the FIN-2 certificate submitted by the petitioner was not in conformity with the tender document's requirements. The financial position ought to be reflected as on the date the bid was submitted, and the documents submitted on 04.02.2015 did not furnish complete and correct information. Rule 59 of the Rules of 2013 allows a bid evaluation committee to declare a bid non-responsive for omissions, and the petitioner failed to supply full details as required in Form Con 2 and details of unutilized credit balance as on the date of submission. 2. Whether the bid evaluation committee properly examined the petitioner's bid in accordance with the standards prescribed under sub-rule (3) of Rule 59 of the Rajasthan Transparency in Public Procurement Rules, 2013?

Sections Cited

Section 7, Rule 59

AI-generated summary — verify with the full judgment below

Cause title — parties, addresses and appearances
[2026:RJ-JP:27270] HIGH COURT OF JUDICATURE FOR RAJASTHAN BENCH AT JAIPUR S.B. Civil Writ Petition No. 14206/2024 URN: CW / 28734U / 2024 M/s. GVPR Engineering Limited- M/s HES Infrastructure Pvt. Ltd. JV., Through Its Authorised Signatory Mr. Sridhar Reddy, Office At 8-2-293/82/A, Plot No. 739-A, Road No. 37, Jubilee Hills, Hyderabad 33, Telangana, India ----Petitioner Versus 1. State Of Rajasthan, Through The Chief Secretary, Government Of Rajasthan, Jaipur (Raj.) 2. Secretary, Public And Health Engineering Department, Main Secretariat Building, Jaipur Rajasthan 3. Addl. Chief Engineer, Project, Public Health And Engineering Department, Project Division Bharatpur. 4. SPML-JWL JV, Through Its Authorised Signatory Jai Prakash Gupta S/o Dean Dayal Gupta, Having Its Place Of Business At Jindal ITF Centre, 28 Shvaji Marg, New Delhi- 110015 ----Respondents For Petitioner(s) : Mr. R.K. Agrawal, Senior Advocate assisted by Mr. Adhiraj Modi, Mr. Rakshit Jaimini, Mr. Daksh Pareek assisted by Mr. Arjun Singh, Mr. Ashish Kabra, Mr. Moin Khan For Respondent(s) : Mr. Rajendra Prasad, Advocate General assisted by Ms. Dhriti Ladha Ms. Mahi Yadav, Additional Advocate General assisted by Mr. Kuldeep Singh Rathore, AAAG Ms. Chelsi Agrawal, Mr. Rohan Mittal Mr. Swadeep Singh Hora assisted by Ms. Varuni Agrawal, Mr. Manish Lakhawat HON'BLE MR. JUSTICE BIPIN GUPTA

Judgment

[2026:RJ-JP:27270] (2 of 77) [CW-14206/2024] Reportable Date of hearing and conclusion of arguments 29.06.2026 Date on which the judgment was reserved 29.06.2026 Whether the full judgment or only the operative part is pronounced Full Judgment Date of pronouncement 17.07.2026

1.

The present writ petition has been filed with the following prayers: “It is, therefore, most respectfully prayed that this writ petition may kindly be accepted and allowed and be further pleased: (i) To quash and set aside the order dated 29.06.2024 passed by the Additional Chief Engineer, Projects, Public Health and Engineering Department, Project Division Bharatpur declaring the petitioner non- responsive. (ii)To declare the petitioners bid as responsive/eligible for the above stated Tender and for a direction to respondents to receive and consider the Petitioners Bid and act accordingly. (iii) To declare the constitution of First Appellate Authority and Second Appellate Authority bad in the eyes of law. (iv) Any other order which the court deems fit in Justice, Equity and Good Conscience.”

2.

Learned Senior Counsel for the petitioner, vide application No.1/2026 did not press clause No. (iii) of the prayer of the writ petition. Accordingly, this Court, considering the said application, disposed of the same by order dated 29.06.2026. Therefore, now the writ petition is being considered for prayer Nos. (i),(ii) and(iv).

3.

The factual matrix of the writ petition is a Notice Inviting Bids (hereinafter referred to as “NIB”) no. 10/2023-24 was floated by PHED department of State of Rajasthan presently being respondent Nos. 2 and 3 for “Work of EMI at existing intake well act Chamber River, Raw Water Pipe Line from intake to RWR-1 and RWR-2 at Dholpur, Main Raw Water Pumping Stations at RWR-1

[2026:RJ-JP:27270] (3 of 77) [CW-14206/2024] and RWR-2, Water Treatment Plant 135 MLD near RWR-2 and 5.0 MLD at Dholpur, Cluster Pumping Station, Treatment Plant 5.0 MLD at Dholpur, Cluster Pumping Station, CDS, VDS and Rising Mains and FHTC for Dholpur and Saipau Block including allied works including allied works (Package-01A).”

4.

The date for downloading the bid was fixed as 16.09.2023 to 19.10.2023. Online submission time was from 16.09.2023 to 19.10.2023. Deposit of original document date was upto 1:00 PM on 20.10.2023. Date of opening of technical bid was 20.10.2023 at 03:00 PM.

5.

The present petitioner as well as respondent no. 4 and two other companies namely M/S Megha Engineering and Infrastructure Private Limited and M/S NCC Limited also submitted there bids.

6.

Vide order dated 29.06.2024 office of the Additional Chief Engineer (Project) PHED, Bharatpur, the following bidders were declared responsive/non-responsive for opening of financial bids: S.No. Name of Firm Remark 1 M/s Megha Engineering and Infrastructures Limited Responsive 2 M/s JWIL Infra Limited (JV of M/s SPML Infra Ltd. and M/s JWIL Infra Ltd.) Responsive 3 M/s NCC Limited Responsive 4 M/s GVPR Engineers Limited (JV of M/s GVPR Engineers Limited and M/s HES Infra Pvt. Ltd. Non-responsive, as the bidder does not meet financial criteria (PQ criteria) with regard to credit limit requirement.

7.

The petitioner's bid was declared non-responsive vide order dated 29.06.2024 on the ground that it did not satisfy the financial criteria (PQ Criteria), as the FIN-2 certificate submitted

[2026:RJ-JP:27270] (4 of 77) [CW-14206/2024] by the petitioner was not in conformity with the requirements of the tender document. Thereafter, the petitioner challenged the said decision before the learned First Appellate Authority as per the provisions of the Rajasthan Transparency in Public Procurement Act, 2012 (hereinafter referred to as the “RTPP Act, 2012”), which rejected the petitioner's appeal. Aggrieved thereby, the petitioner preferred a second appeal, which was also dismissed. Thereafter, the present writ petition was filed. Till the filing of the present writ petition, no work order had been issued.

8.

Vide order dated 16.10.2024, this Court directed that all further actions, including the issuance of the Letter of Intent (hereinafter referred to as “LOI”), shall remain subject to the final outcome of the present writ petition. The work order dated 03.09.2025 also specifically records that it has been issued subject to the final decision of this Court in the present writ petition in terms of the order dated 16.10.2024. 9. Learned Senior Counsel for the petitioner submitted that, as per the bidding document in cases where a bidder participates through a joint venture, the requirement regarding the credit limit reads as under: No. Factor Requirement Requireme nt in terms of value for fulfillment of eligibility Single Entity All parties combined Each member One member Submiss ion require ments

1.

3 Credit Limit Credit Limit (Fund based and non fund based Unutilized and available with the Bidder shall not be Rs. 192.65 Crore Must meet require ment Must meet requirem ent Must meet at least 10% of the require ment Lead partner must meet at least 51% of the requireme nt Letter from Banks Form FIN 2

[2026:RJ-JP:27270] (5 of 77) [CW-14206/2024] less than 15% of the estimated cost of work

9.

1 Learned Senior Counsel for the petitioner submitted that the purpose of prescribing the credit limit was to ensure that in the event the work order is awarded to the successful bidder, such bidder would have sufficient finances to execute the work and complete the project within the stipulated time.

9.

2 Learned counsel further submitted that under the tender conditions, each member of the joint venture was required to satisfy at least 10% of the prescribed financial requirement, whereas the lead partner was required to satisfy at least 51% thereof. He also submitted that considering the estimated project cost of Rs.1,284.30/-Crores, the prescribed credit limit requirement worked out to 15% thereof, i.e., Rs.192.65/- Crores.

9.

3 Learned Senior Counsel for the petitioner further submitted that M/s GVPR Engineering Limited being the lead partner fulfilled the entire prescribed credit limit requirement of more than Rs.192.65/- Crores and in fact, had an available credit limit of Rs.384.85/- Crores as is evident from Annexure-R/5. He also submitted that the other joint venture partner; namely HES Infra Pvt. Ltd. was independently required to satisfy only 10% of the prescribed credit limit requirement. In this regard, the certificate issued by the Bank of India dated 21.05.2024 clearly certified the availability of the requisite credit facility.

9.

4 Learned Senior Counsel for the petitioner submitted that although the said certificate was not strictly in the prescribed FIN-

[2026:RJ-JP:27270] (6 of 77) [CW-14206/2024] 2 format, its contents sufficiently established that HES Infra Pvt. Ltd. had an available credit limit of Rs.20/-Crores, thereby fulfilling the minimum requirement prescribed under the tender conditions.

9.

5 Learned Senior Counsel for the petitioner submitted that by misconstruing the contents of the certificate and merely because it was not in the exact FIN-2 format, respondent Nos. 1 to 3 without affording any opportunity to the petitioner to furnish clarification, wrongly concluded that the petitioner did not possess the requisite available credit limit as on the relevant date. Consequently, the petitioner's bid was declared non-responsive.

9.

6 Learned Senior Counsel for the petitioner further submitted that the alleged defect was purely curable in nature and could have been rectified in accordance with the provisions of the RTPP Act, 2012 and Rule 13 of the Rules of the 2013. He further submitted that the entire tender process demonstrates that respondent No. 4 was declared the successful bidder despite serious deficiencies in its bid. He also submitted that at the stage of issuance of the LOI, the other bidders who had initially been declared responsive had failed to extend the validity of their bids, leaving respondent No. 4 as the sole remaining bidder. Despite this, and in violation of the provisions of the RTPP Act, 2012 and Rule 13 of the Rules of 2013, respondent Nos. 2 & 3 proceeded to issue the LOI in favour of respondent No. 4 in an arbitrary and discriminatory manner.

9.

7 He further submitted that the LOI was thus issued despite the pendency of the present writ petition and the order passed by

[2026:RJ-JP:27270] (7 of 77) [CW-14206/2024] this Court and was made subject to the out come of the writ petition.

9.

8 Learned Senior Counsel for the petitioner also submitted that the FIN-3 document submitted by respondent No. 4 was not in conformity with the bidding document. He further submitted that the Evaluation Committee, in its observations dated 25.04.2024, specifically recorded the deficiencies in respondent No. 4, FIN-3 document.

9.

9 Learned Senior Counsel for the petitioner submitted that by adopting discriminatory practices and applying different standards, respondent Nos. 2 & 3 permitted respondent No. 4 to correct his FIN-3, whereas the petitioner was not afforded any opportunity at any point of time to clarify his FIN-2.

9.

10 Learned Senior Counsel for the petitioner further submitted that despite all these facts having come on record, respondent Nos. 2 & 3, instead of affording the petitioner an opportunity, proceeded to justify the estimated cost by the committee which was excessively high.

9.

11 Learned Senior Counsel for the petitioner submitted that the discrimination on the part of the Bidding Authority and the State is writ large. The petitioner’ joint venture was in a summary manner, declared non-responsive without there being any material deviation that could have been corrected without affecting the substance of the bid. There is a clear violation of the provisions of the RTPP Act, 2012 and the Rules of 2013.

9.

12 Learned Senior Counsel for the petitioner also drew attention of this Court towards the Committee Meeting (Annexure-1) on

[2026:RJ-JP:27270] (8 of 77) [CW-14206/2024] record, which has been filed along with the second stay application. He submitted that there were material deficiencies in the bidding documents of respondent No. 4 (JWIL). The said deficiencies were serious and substantial in nature and were, in fact, incurable. Despite this, respondent No. 4 was granted sufficient opportunity to rectify the deficiencies and was also permitted to correct his FIN-3 after clarifications had been sought by the procuring authority.

9.

13 Learned Senior Counsel for the petitioner further submitted that the approach adopted by the Bidding Authority was contrary to the principles of transparency and fairness. The price bid submitted by respondent No. 4 was substantially higher than the estimated project cost of Rs.1284.30/- Crores. He further submitted that in order to confer an undue advantage upon respondent No. 4, the estimated cost was sought to be justified not on the basis of the PHED BSR, 2021 as stipulated in the NIB, but on the basis of the revised PHED BSR, 2023 and PWD BSR, 2022. He further submitted that, the bid submitted by respondent No. 4 was approximately 15% higher than the NIB cost.

9.

14 Learned Senior Counsel for the petitioner further submitted that even as late as 09.06.2025, the tender had not been finalized and the pre-qualification (PQ) criteria of respondent No. 4 was still under consideration, whereas the petitioner had already been declared non-responsive vide order dated 29.06.2024. He submitted that although two other bidders were declared responsive, they were not considered as they failed to extend the validity of their bids. Consequently, respondent No. 4 remained

[2026:RJ-JP:27270] (9 of 77) [CW-14206/2024] the sole bidder, despite its bid being approximately 15% higher than the NIB cost.

9.

15 Learned Senior Counsel for the petitioner further submitted that in clear violation of the provisions of the RTPP Act, 2012, the Rules of 2013, and the bidding documents, the authorities issued the LOI in favour of respondent No. 4 during the pendency of the present writ petition, notwithstanding the order of this Court that the LOI would remain subject to the final outcome of the writ petition.

9.

16 Learned Senior Counsel for the petitioner submitted that had the procuring authority adopted the same liberal approach towards the petitioner as it did in the case of respondent No. 4, the State exchequer could have been saved an amount of Rs. 211/- Crores i.e. Rs.1438.3077/- Crores - Rs.1226.51/- Crores.

9.

17 Learned Senior Counsel for the petitioner also drew attention of this Court towards the Rule 9, Rule 60, and Rule 61 of the Rules of 2013 in support of his submissions. Therefore, he, prayed that the writ petition be allowed in terms of the prayers as prayed for.

10.

Per contra, learned Advocate General for the State- respondents Nos. 1 to 3 advanced his submissions and also filed written arguments. He drew attention of this Court towards the conditions contained in the NIB, particularly the requirement relating to the credit limit. Further drew attention of this Court towards Chapter-I of the bidding document, containing the instructions to Bidders, specifically required every bidder to carefully read and understand the instructions, forms, terms and

[2026:RJ-JP:27270] (10 of 77) [CW-14206/2024] conditions governing the tender process. He further submitted that the bidding documents clearly stipulated that all information was required to be furnished strictly in the prescribed format.

10.

1 Learned Advocate General for the State-respondents Nos. 1 to 3 further drew attention of this Court towards the terms and conditions governing the preparation of bids as well as the provisions relating to the "Preliminary Examination of Bids" contained in the NIB. He further submitted that the last date for submission of bids, which was originally prescribed, was extended up to 21.05.2024 and the petitioner submitted its bid on the said extended last date. The technical bids were opened on 22.05.2024.

10.

2 Learned Advocate General for the State-respondents Nos. 1 to 3 also referred to the various stages of the bid evaluation process,

namely,

preliminary

examination,

substantial responsiveness evaluation, pre-qualification evaluation and thereafter, financial evaluation. It was fairly admitted that on 22.05.2024, technical bids of all the four participating bidders were opened.

10.

3 Learned Advocate General for the State-respondents Nos. 1 to 3 submitted that the first meeting of the Bid Evaluation Committee was held on 25.06.2024 and minutes were drawn, wherein the petitioners’ bid was found not to satisfy the prescribed financial eligibility criteria as the FIN-2 which has been provided by the petitioner did not specifically disclose the total credit limit available as well as the unutilized credit limit available within three

[2026:RJ-JP:27270] (11 of 77) [CW-14206/2024] months from the date of opening of the pre-qualification bid, as required under the bidding conditions.

10.

4 Learned Advocate General for the State-respondents Nos. 1 to 3 submitted that the certificate issued by the Union Bank of India in favour of the lead partner, M/s GVPR was found to be in conformity with the tender requirements. However, the certificate dated 21.05.2024 issued by the Bank of India in favour of M/s HES Infra Ltd. did not satisfy the prescribed conditions. Consequently, the petitioner's bid was declared non-responsive and the petitioner was informed accordingly vide order dated 29.06.2024.

10.

5 Learned Advocate General for the State-respondents Nos. 1 to 3 submitted that the petitioner challenged the order dated 29.06.2024 by filing a first appeal before the learned First Appellate Authority, which came to be dismissed vide order dated 12.07.2024, affirming the decision of the Bid Evaluation Committee. The petitioner thereafter preferred a second appeal before the learned Second Appellate Authority, which was also dismissed vide order dated 21.08.2024.

10.

6 Learned Advocate General for the State-respondents Nos. 1 to 3 submitted that thereafter, on 03.09.2025, the procuring entity issued the work order in favour of respondent No. 4 and a formal contract was also executed with respondent No. 4.

10.

7 Learned Advocate General in written submissions have raised preliminary objections regarding the maintainability of the present writ petition. It was argued that the writ petition has been filed by a Joint Venture, which is not a legal entity and therefore, the writ

[2026:RJ-JP:27270] (12 of 77) [CW-14206/2024] petition itself is not maintainable. He further submitted that the petitioner is an unregistered partnership firm and, therefore, the writ petition is also barred in view of the provisions of Section 69 of the Indian Partnership Act, 1932 (hereinafter referred to as the “Act of 1932”).

10.

8 Learned Advocate General for the State-respondents Nos. 1 to 3 submitted that the petitioner has challenged only the order dated 29.06.2024 and has failed to challenge the subsequent orders passed by the learned First Appellate Authority dated 12.07.2024 and the learned Second Appellate Authority dated 21.08.2024. Therefore, by virtue of the doctrine of merger, the original order stood merged with the appellate orders and, in the absence of any challenge thereto, the writ petition is liable to be dismissed.

10.

9 Learned Advocate General for the State-respondents Nos. 1 to 3 submitted that the petitioner has made incorrect pleadings by alleging that the order dated 21.08.2024 is an order, whereas in fact it was merely the English translated version of the original order passed in Hindi. He further submitted that this material fact has neither been disclosed in the pleadings nor in the supporting affidavit, thereby violating the Rule 22 of the Rajasthan High Court Rules, 1952 and therefore, the writ petition deserves to be dismissed.

10.

10 Learned Advocate General for the State-respondents Nos. 1 to 3 submitted that no relief can be granted in respect of an order which has not been specifically challenged. Since the petitioner has not amended the writ petition to challenge the subsequent

[2026:RJ-JP:27270] (13 of 77) [CW-14206/2024] appellate orders, no relief can be granted against those orders in the present proceedings.

10.

11 Learned Advocate General for the State-respondents Nos. 1 to 3 submitted that a pure question of law can be raised at any stage of the proceedings and that the preliminary objections relating to the maintainability of the writ petition deserve to be decided at the threshold.

10.

12 Learned Advocate General for the State-respondents Nos. 1 to 3 submitted that the controversy involved in the present case is squarely covered by the judgment rendered in Project Director, RUID & Others v. M/s Rama Infra & Others (D.B. Special Appeal (Writ) No. 804/2018) decided on 29.03.2019. He further submitted that the scope of judicial review in contractual and tender matters is extremely limited and that on the date of submission of the bid, the petitioner was admittedly ineligible. The respondents were under no statutory obligation to seek any clarification or negotiate with a bidder whose bid had been found to be non-responsive.

10.

13 Learned Advocate General for the State-respondents Nos. 1 to 3 drew attention of this Court towards Section 5 & 7 of the Act, 2012 and Rule 59, 60 and 61 of the Rules of 2013.

10.

14 Lastly, he further submitted that while exercising juri iction under Article 226 of the Constitution of India, this Court cannot travel beyond the statutory framework governing the tender process. He further submitted that equitable considerations cannot override the express provisions of the statute or the terms

[2026:RJ-JP:27270] (14 of 77) [CW-14206/2024] and conditions of the tender document. Therefore, he prayed that the writ petition be dismissed.

11.

Learned counsel for the respondent No. 4 supported the submissions advanced by the learned Advocate General. In addition thereto, he submitted that respondent No. 4 has filed an application under Section 379 of BNSS, 2023 alleging that the petitioner has placed on record a fabricated and forged document, namely, the purported order of the learned Second Appellate Authority.

11.

1 Learned counsel for the respondent No. 4 argued that the writ petition has, in any case, become infructuous inasmuch as the LOI has already been issued, the contract has been awarded and executed, and the petitioner has failed to suitably amend the writ petition so as to challenge the subsequent developments.

11.

2 Learned counsel for the respondent No. 4 submited that pursuant to the award of the contract, respondent No. 4 has mobilized substantial machinery, manpower, financial resources and furnished the requisite bank guarantees. A significant portion of the work has already been executed and an investment of crores has been made. He further submitted that any interference at this stage would not only seriously prejudice the successful bidder but would also adversely affect the execution of a Major Public Water Supply Project undertaken in public interest.

11.

3 Learned counsel for the respondent No. 4 drew attention of this Court towards Section 2(34) of the RTPP Act, 2012 defining a "responsive bid", as well as Section 60(4) of the said Act. He also

[2026:RJ-JP:27270] (15 of 77) [CW-14206/2024] referred to Clauses 1.12 & 11.2 read with Clauses 5.1, 20.1 and 21.1 of the bidding documents.

11.

4 Learned counsel for the respondent No. 4 argued that FIN-2 certificate furnished by the petitioner's Joint Venture partner, M/s HES Infra Pvt. Ltd., did not disclose the availability of the requisite credit limit as on the date of submission of the bid, which constituted a breach of the mandatory conditions of the tender document. Consequently, the petitioner's bid was rightly declared non-responsive.

11.

5 Learned counsel for the respondent No. 4 further argued that the petitioner has filed a false affidavit before this Court and, therefore, the writ petition deserves to be dismissed in limine.

11.

6 Learned counsel for the respondent No. 4 further submitted that the original order dated 29.06.2024 stood merged with the appellate orders dated 12.07.2024 and 21.08.2024. Since the petitioner has not challenged the subsequent appellate orders, the present writ petition is not maintainable and is liable to be dismissed on this ground alone.

11.

7 Learned counsel for the respondent No. 4 further argued that while exercising juri iction under Article 226 of the Constitution of India, this Court ought not to interfere in matters relating to tender evaluation except in cases of arbitrariness, malafides or violation of statutory provisions, none of which is made out in the present case.

11.

8 Learned counsel for respondent no. 4 pointed out that as on March, 2026, works valuing approximately Rs.188.20/-Crores (inclusive of GST) had already been completed and further

[2026:RJ-JP:27270] (16 of 77) [CW-14206/2024] purchase orders worth approximately Rs.433/-Crores had also been issued. Therefore, he submitted that the deficiency in the FIN-2 certificate furnished by the petitioner's Joint Venture was of such a fundamental nature that it could neither be clarified nor rectified after submission of the bid. Accordingly, the decision of the Bid Evaluation Committee in declaring the petitioner's bid non- responsive was fully justified. Therefore, he prayed that the writ petition be dismissed.

12.

In rejoinder the learned Senior Counsel for the petitioner submitted that the filing of the English translated copy of the order dated 21.08.2024 of the learned Second Appellate Authority, instead of the original Hindi version, was only a bonafide procedural irregularity. The translation was a true and correct translation generated through Google Lens, the original Hindi order has since been placed on record by both the respondents and the petitioner, and its authenticity was never disputed in the reply; therefore, the objection raised during arguments is merely an afterthought.

12.

1 Learned counsel in rejoinder further submitted that the objection regarding maintainability of the writ petition at the stage of arguments under Section 69 of the Act of 1932 is misconceived and beyond the pleadings. It was submitted that the petitioner participated in the tender as a Joint Venture, which was expressly permissible under the tender conditions and accepted by the respondents throughout the tender process. Section 69 of the Act of 1932 applies only to suits for enforcement of contractual rights and has no application to proceedings under Article 226 of the

[2026:RJ-JP:27270] (17 of 77) [CW-14206/2024] Constitution. It was also submitted that the writ petition specifically challenges the legality of the orders passed by the procuring authorities under the RTPP Act, 2012 and that the constitutional juri iction of this Court cannot be curtailed by technical objections regarding the form of challenge.

12.

2 Learned Senior Counsel also opposed the respondents' application under Section 379 read with Section 215 of the BNSS, 2023, contending that no case of forgery, falsehood or perjury is made out and that the application is frivolous, malafide and intended only to prejudice the petitioner during the pendency of the writ petition.

13.

Learned Senior Counsel for the petitioner placed reliance on the judgments: - (i) Uday Shankar Triyar vs. Ram Kalewar Prasad [2026:RJ-JP:27270] (18 of 77) [CW-14206/2024] (ix) Assn of Registration Plates vs. Union of India (xv) Comptroller and Auditor-General of India, Gian Petition No. 8541/2025 decided on 26.02.2026. (xvii) M/s. Geo Miller Co. Pvt. Ltd. vs. State of Rajasthan and Anr. reported in AIR 2016 RAJ 130. (xviii) The Porject Director and others vs. M/s. Ramky Infrastructure Ltd., in D.B. Special Appela (Writ) 804/2018 and connected matters.

14.

Learned Advocate General for the State-respondents Nos. 1 to 3 placed reliance on the following judgments: (i) Deputy Commissioner of Sales Tax, (Law) BOR (Taxes), Ernakulam vs. M/s Kelukutty reported in (1985) 4 SCC 35. (ii) Ethiopian Artilines vs. Ganesh Narain Saboo reported in (2011) 8 SCC 539. (iii) Shanti vs. T.D. Vishwanathan & Anr. reported in (2019) 11 SCC 419. [2026:RJ-JP:27270] (19 of 77) [CW-14206/2024] (iv) State of Orissa & Anr. vs Mamta Mohanty reported (Pandey) & Ors. reported in (2024) 20 SCC 23. (vi) ADM (City) Agra vs. Prabhakar Chaturvedi & Anr. reported in (1996) 2 SCC 12. (vii) State of W.B. & Anr. vs. West Bengal Registration Copywriters Ass. & Anr. reported in (2009) 14 SCC 132. (viii) Yeshwant Deorao vs. Walchand Ramchand (xi) Project Director, RUIDP & Ors. vs. M/s Ramky Infrastructure Ltd. & Ors. (DBSAW o. 804/2018) India & Anr. reported in (2020) 16 SCC 489. (xiii) Michigan Rubber (India) Ltd. vs. State of (xv) N.G. Projects Ltd. vs. M.s Vinod Kumar Jain & Electric Supply & Transport Undertaking (BEST) & Ors. (Civil Appeal No. 3887 of 2023). (xvii) KSRTC vs. Ashrafulla Khan & Ors. reported in (2002) 2 SCC 560. (xviii) Council of ISCE vs. Isha Mittal & Anr. reported in (2000) 7 SCC 521. 15. Learned counsel for the respondent no. 4 placed reliance on the following judgments:-

[2026:RJ-JP:27270] (20 of 77) [CW-14206/2024] (i) Madras High Court Advocates’ Association vs. Dr. A.S. Anand, Hon’ble The CJI and anothers reported in (2001) 3 SCC 19. (ii) Aman Singh vs Union of India reported in (2011) 7 (xii) Centsal Coalfields Ltd. and anothers vs. SLL-SML (Joint Venture Consortium) and Ors. reported in (2016) 8 SCC 622. (xiii) [2026:RJ-JP:27270] (21 of 77) [CW-14206/2024] (xiv) Sorath Builders vs. Shreejikrupa Buildcon Ltd. (xvi) State of Jharkhand and others vs. CWE-SOMA Consortium reported in (2016) 14 SCC 172. (xvii) Giepl-Hsepl JV vs The Additional Chief Engineer and others in S.B. Civil Writ Petition 8466/2018. (xviii) Dilip Buildcon Ltd. vs. State of Rajasthan and others reported in MANU/RH/1612/2019. 16. Heard all the parties and perused the material available on record.

17.

Before adverting to the writ petition on merits, this Court deems it appropriate to first consider certain objections raised by the respondents, although such objections were not specifically pleaded in their reply.

18.

One of the principal objections jointly raised by all the respondents is that the petitioner has not challenged the subsequent developments that occurred during the pendency of the present writ petition, namely, the issuance of the LOI, the work order, the execution of the agreement, and the substantial progress of the work. It was further contended that respondent No. 4 has made substantial investments pursuant thereto, and therefore, this Court ought not to entertain the writ petition at this stage.

18.

1 This Court finds that immediately after the impugned order dated 29.06.2024 was passed, the petitioner approached the competent authorities for redressal of its grievances. Thereafter,

[2026:RJ-JP:27270] (22 of 77) [CW-14206/2024] the present writ petition was instituted on 29.08.2024. The Co- ordinate Bench of this Court, vide an interim order dated 16.10.2024, passed the following directions:

“1. It has been stated that petitioner in joint venture (JV) with partner-M/s HES Infra Pvt. Ltd., participated in NIB No.10/2023-2024 and in the preliminary examination, the petitioner's bid was passed by the Bid Evaluation Committee. However, on the next stage of evaluation i.e. a substantial evaluation, petitioner's bid was declared non-responsive with the remark "as bidder does not meet the financial criteria (PQ criteria) with regard to credit limit requirement" vide office order dated 29.06.2024 released from the Office of Additional Chief Engineer, (Project), Public Health And Engineering Department, Project Division Bharatpur.

2.

Learned senior counsel appearing on behalf of petitioner argued that deficiency in respect of credit limit requirement of petitioner has been observed in respect of joint venture (JV) partner-M/s HES Infra Pvt. Ltd. and the certificate dated 21.05.2024 issued by the Bank of India has not been accepted merely for technical reason that same is not issued in form of prescribed and proper format.

3.

Learned Senior Counsel for petitioner vehemently argued that such defect is curable and the procuring authority in exercise of its powers with the aid of Rule 59, 60 and 61 of the Rajasthan Transparency in Public Procurement Rules, 2013 could have asked to submit a fresh certificate in proper format, since same does not amount to material deviation, rather pertains to clarification of the conditions of tendered document.

4.

Learned Senior Counsel submits that declaring the petitioner's bid as non-responsive on such technical ground is violative to the aim and object of Rajasthan Transparency in Public Procurement Act, 2012. The First

[2026:RJ-JP:27270] (23 of 77) [CW-14206/2024] Appellate Authority and Second Appellate Authority, being the superior officers of the respondent- department, has dismissed the appeals filed by the petitioner in a mechanical manner, hence, the order dated 29.06.2024 be quashed and petitioner be held responsive/eligible to participate in the financial bid.

5.

Learned Senior Counsel argued that since the decision making process of respondent-authorities suffers from infirmity as much as the order impugned suffers from vice of arbitrariness and stands in clear-cut violation of Article 14 of the Constitution of India, therefore, in such peculiar facts and circumstances, the writ juri iction has been invoked against the arbitrariness of the respondents-authorities in ousting the petitioner to participate in financial bid, which resulted against the public interest.

6.

Per contra, counsel for respondent No.4 who has been impleaded as party being another participant to NIB and being declared as L-1 bidder, argued that after declaring the petitioner as non-responsive bidder vide order dated 29.06.2024, the financial bid has been opened on 04.07.2024, wherein respondent No.4 has been declared as L-1 bidder and only Letter of Intent (LOI) is to be issued in his favour.

7.

Learned counsel appearing for respondent No.4 argued that the certificate dated 21.05.2024 issued by Bank of India in favour of M/s HES Infra Pvt. Ltd., joint venture partner of petitioner to participate in the bid, is in form of an advice and a conditional certificate to provide credit limit subject to grant of tender contract which does not meet the requisite criteria of cash credit limit as stipulated in Clause 1.3 of "eligibility criteria for credit limit" of the tendered document. Hence, the bid of petitioner has rightly been rejected.

8.

Learned counsel for respondent No.4 submits that since respondent No.4 has been declared as L1 bidder,

[2026:RJ-JP:27270] (24 of 77) [CW-14206/2024] at this juncture no interference by the High Court in writ juri iction be made in the present writ petition pertaining to challenging the process of Government tender.

9.

Heard. Considered.

10.

Let notice to respondents No.1 to 3 of writ petition as also of stay application be issued. In addition, copy of writ petition may be served in the Office of Additional Advocate General, Ms. Mahi Yadav for PHED (Public Health and Engineering Department).

11.

List the matter on 05.11.2024. 12.Having considered the facts and circumstances obtaining in the present case, it is hereby observed that issuance of LOI in favour of respondent No.4 shall remain subject to order(s) passed in the instant petition.” (Emphasis Supplied)

18.

2 This Court finds that, as on the date of the interim order dated 16.10.2024, the tender evaluation process had not attained finality. The bid of respondent No. 4 had neither attained finality nor had respondent No. 4 been finally declared to be a responsive bidder. The record reveals that certain queries raised by the tendering authority remained pending consideration, and the determination of the responsiveness of respondent No. 4 was contingent upon the satisfactory resolution thereof. It was in these circumstances, when the evaluation process itself remained incomplete, and the Co-ordinate Bench of this Court, being satisfied that the petitioner had made out a prima facie case, issued notice in the writ petition and directed that any LOI/Work Order issued in favour of respondent No. 4 would remain subject to the final outcome of the present writ petition.

[2026:RJ-JP:27270] (25 of 77) [CW-14206/2024]

18.

3 It is an admitted position that none of the respondents sought any review, modification, clarification, or vacation of the aforesaid interim order, and the same continued to operate throughout the pendency of the proceedings. Subsequently, the LOI/Work Order came to be issued only on 03.09.2025, nearly eleven months after the passing of the interim order dated 16.10.2024. Significantly, the LOI/Work Order itself expressly records that it has been issued subject to the final outcome of the present writ petition, thereby giving effect to and acting in conformity with the directions contained in the interim order.

18.

4 In view thereof, any rights or obligations arising from the said LOI/Work Order are necessarily conditional and remain subject to the final adjudication of the present writ petition. Having accepted the interim order and consciously acted in accordance therewith, the respondents cannot now be permitted to contend that the subsequent issuance of the LOI/Work Order has rendered the writ petition infructuous or has otherwise affected its maintainability. Such a contention is inconsistent with their own conduct and is liable to be rejected.

18.

5 This Court also notes that the respondents issued the LOI nearly 11 months after the interim order dated 16.10.2024. During this interregnum, respondents Nos. 1 to 3 had ample opportunity to seek clarifications from the petitioner, and in fact, queries had been raised to the respondent No.

4.

However, despite waiting for almost one year before finally declaring respondent No. 4 as responsive, the respondents failed to extend a similar

[2026:RJ-JP:27270] (26 of 77) [CW-14206/2024] opportunity to the petitioner to clarify the alleged deficiencies in its bid.

18.

6 In view of the foregoing discussion, the preliminary objection raised by the respondents regarding the maintainability of the writ petition on account of subsequent developments is liable to be rejected. The subsequent issuance of the LOI/Work Order, having been expressly made subject to the final outcome of the present writ petition, did not give rise to any independent or distinct cause of action requiring the petitioner to institute a separate challenge or amend the reliefs already sought. The validity of the consequential actions taken by the respondents remains wholly dependent upon the legality of the impugned tender process, which is the principal issue under consideration in the present proceedings.

18.

7 This Court is further of the considered opinion that the issuance of the LOI/Work Order during the pendency of the writ petition constituted merely a consequential step undertaken in conformity with the interim order of this Court and did not alter the nature or scope of the controversy. Accepting the respondents' contention would lead to the anomalous consequence of requiring a litigant to repeatedly amend pleadings or institute fresh proceedings upon every consequential administrative action taken during the pendency of the litigation, notwithstanding that such actions are expressly made subject to the final adjudication of the Court. Such an approach would unnecessarily multiply proceedings, undermine the principle of judicial economy, and elevate procedural form over substantive justice. Accordingly, the

[2026:RJ-JP:27270] (27 of 77) [CW-14206/2024] subsequent issuance of the LOI/Work Order neither affects the maintainability of the writ petition nor renders the present proceedings infructuous.

18.

8 This Court is further guided by the equitable principle embodied in the Latin maxim pendente lite nihil innovetur, meaning thereby that during the pendency of litigation, the subject matter of the dispute should not be altered to the prejudice of the rights of the parties awaiting adjudication by the Court. The maxim is founded upon the broader principle that judicial proceedings should not be rendered ineffective or frustrated by unilateral acts undertaken while the dispute remains sub judice. Although the respondents were not restrained from proceeding with the tender process, the Co-ordinate Bench of this Court had categorically directed that any LOI/Work Order issued in favour of respondent No. 4 would remain subject to the final outcome of the present writ petition. The subsequent issuance of the LOI in conformity with that order was, therefore, necessarily provisional and incapable of conferring any absolute or indefeasible rights upon respondent No. 4.

18.

9 Accordingly, the respondents cannot contend that the execution of the LOI or the consequential agreement has created a fait accompli or rendered the present writ petition infructuous. To accept such a contention would permit a party to defeat the efficacy of pending judicial proceedings by taking consequential administrative steps during their pendency, notwithstanding that such steps were expressly made subject to the ultimate decision of the Court. Such a course would not only undermine the

[2026:RJ-JP:27270] (28 of 77) [CW-14206/2024] authority of judicial orders but would also be contrary to the salutary principle underlying the maxim pendente lite nihil innovetur, which seeks to preserve the efficacy of the judicial process until the rights of the parties are finally determined.

18.

10 In view of the foregoing discussion, this Court has no hesitation in holding that the objection raised by the respondents regarding the petitioner's alleged failure to challenge the subsequent developments is wholly misconceived, legally untenable, and devoid of any merit. The subsequent events neither render the writ petition infructuous nor affect its maintainability. The objection is accordingly rejected.

19.

Another objection raised by respondent No. 4 is that the documents annexed with the writ petition are not duly supported by a proper affidavit and, therefore, the writ petition is liable to be rejected.

19.

1 This Court finds that the writ petition was filed on 29.08.2024. Significantly, no such objection was raised by any of the respondents in their respective replies. The objection has been raised for the first time during the course of final arguments.

19.

2 Learned counsel for the respondent No. 4 filed an application under Section 379 of the BNSS, 2023 praying that a false evidence has been filed and, therefore, seeking initiation of criminal proceedings against the petitioner.

19.

3 This Court finds that during the hearing, it was noticed that the order of the learned Second Appellate Authority placed on record was not the original order. Learned Advocate General submitted that the original order of the learned Second Appellate

[2026:RJ-JP:27270] (29 of 77) [CW-14206/2024] Authority had been passed in Hindi, whereas the document annexed with the writ petition was its English translation. Both parties were heard at length on the issue regarding the effect of the English translation being placed on record when the original order was already available.

19.

4 This Court has perused the record. The affidavit filed by the petitioner in support of the documents annexed with the writ petition, particularly at page Nos. 165 and 166, contains paragraph 2, which reads as under: “That the annexed document Annex.1 to are true and exact photo copies/downloaded copies/certified copies of their originals.”

19.

5 A perusal of the said affidavit reveals that when the writ petition was initially filed, the affidavit in support of the documents was not happily or appropriately worded. However, if the affidavit was defective or not in the prescribed form, the same ought to have been objected by the Registry at the time of scrutiny. This Court finds that no such objection was ever raised by the Registry, thereafter the writ petition came to be registered and notices were duly issued to the respondents.

19.

6 The objection has surfaced only at the stage of final arguments. In the opinion of this Court, even assuming that the affidavit was deficient or not in the proper format, such deficiency would, at best, constitute a curable defect. It is well settled that where the Court finds that where an affidavit supporting annexed documents is incomplete or not in the prescribed format, the defect can always be rectified by permitting the filing of a proper affidavit.

[2026:RJ-JP:27270] (30 of 77) [CW-14206/2024]

19.

7 The record further reveals that Learned Senior Counsel for the petitioner has, in fact, filed a duly corrected affidavit on 26.05.2026, wherein paragraph No.2 specifically states as under:

“2. THAT the Annexure-1 to 6 and 8 to the writ petition are true and correct photocopy of the original. Annexure-7 is collectively the true and correct photocopy of the memo of second appeal and the English translation of the order dated 21.08.2024 of the second appellate authority, as delivered by the Google Lens and is actual translation of the original order in Hindi language.”

19.

8 A bare perusal of the affidavits referred to in paragraph 19.4 reveals that no affidavit was filed with respect to the annexure generated through Google Lens, i.e., the order of the learned Second Appellate Authority. The affidavit was filed only in respect of Annexure-1.

19.

9 This Court further finds that the corrected affidavit, as referred to in paragraph 19.7 of this order, has been filed, which clearly demonstrates that Annexure-7 consisted of the photocopy of the memo of the second appeal along with the English translation of the order dated 21.08.2024 passed by the learned Second Appellate Authority.

19.

10 In view of the above, this Court finds no merit in the contention advanced by learned counsel for respondent No. 4 seeking initiation of criminal proceedings under Section 379 of the BNSS, 2023. the omission in original affidavit was a curable procedural defect, which has since been rectified by filing the corrected affidavit. No material has been placed on record to

[2026:RJ-JP:27270] (31 of 77) [CW-14206/2024] establish any deliberate falsehood or intention to mislead the Court.

19.

11 Consequently, the objection raised by respondent No. 4 is devoid of merit and is, accordingly, rejected.

20.

Learned counsel for the respondents have also raised a preliminary objection that the writ petition is liable to be dismissed on the ground that although the petitioner has challenged the original order dated 29.06.2024, the orders passed by the learned First Appellate Authority and the learned Second Appellate Authority have not been assailed. It was submitted that the doctrine of merger would apply and therefore, in the absence of a challenge to the appellate orders, the writ petition is not maintainable.

20.

1 This Court has considered the aforesaid objection and finds no merit therein. The doctrine of merger is primarily applicable in cases where a decree or order of a subordinate Court merges into the decree or order passed by the superior forum. The object of the doctrine is to determine the limitation for execution of a decree and to identify the operative decree or order for purposes of limitation. The said doctrine cannot be mechanically extended to every administrative or quasi-judicial proceeding.

20.

2 In the present case, the impugned action whereby the petitioner's bid was declared non-responsive is contained in the order dated 29.06.2024 passed by the Procuring Entity. Although the petitioner thereafter availed the statutory remedies before the learned First Appellate Authority and the learned Second Appellate Authority under the provisions of the RTPP Act, 2012, the original

[2026:RJ-JP:27270] (32 of 77) [CW-14206/2024] decision declaring the petitioner's bid as non-responsive does not cease to exist nor does it merge in the appellate orders in the manner suggested by the respondents.

20.

3 While exercising its extraordinary juri iction under Article 226 of the Constitution of India, this Court is required to examine the legality, validity and propriety of the original administrative action. If the Court finds that the order dated 29.06.2024 is contrary to the provisions of the Act, the Rule, or the terms and conditions of the NIB, it is well within its juri iction to interfere with the said order. Merely because the appellate orders have not been specifically challenged would not, by itself, render the writ petition non-maintainable by invoking the doctrine of merger.

20.

4 The doctrine of merger, in the facts of the present case, cannot be applied so as to defeat the exercise of the constitutional juri iction of this Court under Article 226 of the Constitution. The availability and exhaustion of the statutory appellate remedies do not denude this Court of its power to examine the legality of the original administrative order.

20.

5 Therefore, this preliminary objection raised by the respondents is devoid of merit and deserves to be, and is hereby, rejected.

20.

6 In reaching the above conclusion this court relies on a judgment passed by the Hon'ble Supreme Court in State of U.P. v. Mohd. Nooh (Supra), wherein it was held that the doctrine of merger does not have universal application and an original order continues to remain operative unless modified or set aside in

[2026:RJ-JP:27270] (33 of 77) [CW-14206/2024] appeal or revision. The mere dismissal of an appeal or revision does not obliterate or supersede the original order, except for limited purposes such as computation of limitation. The relevant extracts from the aforesaid judgment, having a bearing on the controversy involved in the present case, are reproduced hereinbelow:

“19. There appear to be two answers to the foregoing contention. As we have already observed an order of dismissal passed on a departmental enquiry by an officer in the department and an order passed by another officer next higher in rank dismissing an appeal therefrom and an order rejecting an application for revision by the head of the department can hardly be equated with any propriety with decrees made in a civil suit under the Code of Civil Procedure by the court of first instance and the decree dismissing the appeal therefrom by an appeal court and the order dismissing the revision petition by a yet higher court, as has been sought to be done by the High Court in this case, because the departmental tribunals of the first instance or on appeal or revision are not regular courts manned by persons trained in law although they may have the trappings of the courts of law. The danger of so doing is evident from what has happened in the very case now before us.

20.

In the next place, while it is true that a decree of a court of first instance may be said to merge in the decree passed on appeal therefrom or even in the order passed in revision, it does so only for certain purposes, namely, for the purposes of computing the period of limitation for execution of the decree as in Batuk Nath v. Munni Dei [Batuk Nath v. Munni Dei, 1914 SCC OnLine PC 14 : (1913-14) 41 IA 104] , or for computing the period of limitation for an application for final decree in a

[2026:RJ-JP:27270] (34 of 77) [CW-14206/2024] mortgage suit as in Jowad Hussain v. Gendan Singh [Jowad Hussain v. Gendan Singh, 1926 SCC OnLine PC 28 : (1925-26) 53 IA 197] . But, as pointed out by Sir Lawrence Jenkins in delivering the judgment of the Privy Council in Juscurn Boid v. Pirthichand Lal [Juscurn Boid v. Pirthichand Lal, 1918 SCC OnLine PC 85 : (1918-19) 46 IA 52 : ILR (1919) 46 Cal 670 at pp. 678-679] , whatever be the theory under other systems of law, under the Indian law and procedure an original decree is not suspended by the presentation of an appeal nor is its operation interrupted where the decree on appeal is merely one of dismissal. There is nothing in the Indian law to warrant the suggestion that the decree or order of the court or tribunal of the first instance becomes final only on the termination of all proceedings by way of appeal or revision. The filing of the appeal or revision may put the decree or order in jeopardy but until it is reversed or modified it remains effective. In that view of the matter the original order of dismissal passed on 20- 4-1948 was not suspended by the presentation of appeal by the respondent nor was its operation interrupted when the Deputy Inspector General of Police simply dismissed the appeal from that order or the Inspector General simply dismissed the application for revision. The original order of dismissal, if there were no inherent infirmities in it, was operative on its own strength and it did not gain any greater efficacy from the subsequent orders of dismissal of the appeal or the revision except for the specific purposes hereinbefore mentioned. That order of dismissal having been passed before the Constitution and rights having accrued to the appellant State and liabilities having attached to the respondent before the Constitution came into force, the subsequent conferment of juri iction and powers on the High Court can have no retrospective operation on such rights and liabilities. Even if the order of dismissal of the

[2026:RJ-JP:27270] (35 of 77) [CW-14206/2024] respondent was a nullity on the ground that it was passed by disregarding the rules of natural justice, the High Court could not properly be asked to exercise its newly acquired juri iction and powers under Article 226 to correct errors, irregularities or illegalities committed by the inferior departmental tribunal before the commencement of the Constitution, for then there will be no limit to its going backward and that will certainly amount to giving the provisions of Article 226 a retroactive operation. This aspect of the matter does not appear to have been pressed in the High Court or adverted to by it. It is only on this ground that we are constrained, not without regret, to accept this appeal.”

21.

Another objection raised by respondent Nos. 1 to 3 is with regard to the fact that the writ petition is not maintainable as being barred by Section 69(2) of the Act of 1932. Learned counsel for respondent No. 4 submitted that a reading of the Joint Venture agreement executed between the petitioner and M/s HES Infra Pvt. Ltd. reveals that it provides for sharing of profits and, therefore, answers the definition of a "partnership" under the Act of 1932. It is contended that since the alleged partnership firm is not registered, the present writ petition is barred under Section 69(2) of the Act of 1932 and is, therefore, not maintainable.

21.

1 At the outset, it is noticed that no such objection was raised by any of the respondents in their written reply. The said contention has been raised for the first time during the course of final arguments.

21.

2 This Court further finds that the NIB itself specifically contemplated participation by Joint Ventures and required only that the constituent members execute a Joint Venture agreement

[2026:RJ-JP:27270] (36 of 77) [CW-14206/2024] before participating in the bidding process. At no stage does the NIB stipulate that such Joint Venture agreement must necessarily constitute a registered partnership firm under the Act of 1932. Had such a condition been intended, the procuring entity would have expressly incorporated the same as an essential eligibility condition. No such requirement finds place in the bidding documents.

21.

3 It is also pertinent to note that respondent No. 4 has not placed on record its any Joint Venture agreement to demonstrate that it had constituted a registered partnership firm before participating in the bidding process. Learned Advocate General has failed to produce any document or material to establish that respondent No. 4, namely SPML–JWIL JV, was constituted as a registered partnership firm or that registration under the Act of 1932 was treated as a mandatory requirement under the tender conditions.

21.

4 On the contrary, the agreement executed by the State- respondents with respondent No. 4 clearly reflects that the contract has been awarded to the Joint Venture itself and not to any registered partnership firm. This itself demonstrates that registration under the RTPP Act, 2012 was never treated as a condition precedent for participation in the bidding process.

21.

5 Even otherwise, Section 69(2) of the Act of 1932 has a limited application. The said provision bars the institution of a suit to enforce a right arising out of a contract by or on behalf of an unregistered partnership firm. The present proceedings are not in the nature of a civil suit but are proceedings under Article 226 of

[2026:RJ-JP:27270] (37 of 77) [CW-14206/2024] the Constitution of India invoking the extraordinary writ juri iction of this Court. The statutory bar contained in Section 69(2) of the Act of 1932 is, therefore, not attracted to the present proceedings. Section 69 of the Act of 1932 reads as under:

“69. Effect of non-registration.— (1)No suit to enforce a right arising from a contract or conferred by this Act shall be instituted in any court by or on behalf of any person suing as a partner in a firm against the firm or any person alleged to be or to have been a partner in the firm unless the firm is registered and the person suing is or has been shown in the Register of Firms as a partner in the firm. (2)No suit to enforce a right arising from a contract shall be instituted in any Court by or on behalf of a firm against any third party unless the firm is registered and the persons suing are or have been shown in the Register of Firms as partners in the firm. (3)The provisions of sub-sections (1) and (2) shall apply also to a claim of set-off or other proceeding to enforce a right arising from a contract, but shall not affect,— (a)the enforcement of any right to sue for the dissolution of a firm or for accounts of a dissolved firm, or any right or power to realise the property of a dissolved firm, or (b)the powers of an official assignee, receiver or Court under the Presidency-towns Insolvency Act, 1909 (3 of 1909) or the Provincial Insolvency Act, 1920 (5 of 1920) to realise the property of an insolvent partner. (4)This section shall not apply,— (a)to firms or to partners in firms which have no place of business in the territories to which this Act extends, or whose places of business in the said

[2026:RJ-JP:27270] (38 of 77) [CW-14206/2024] territories, are situated in areas to which, by notification under section 56, this Chapter does not apply, or (b)to any suit or claim of set-off not exceeding one hundred rupees in value which, in the Presidency- towns, is not of a kind specified in section 19 of the Presidency Small Cause Courts Act, 1882 (5 of 1882), or, outside the Presidency-towns, is not of a kind specified in the Second Schedule to the Provincial Small Cause Courts Act, 1887 (9 of 1887), or to any proceeding in execution or other proceeding incidental to or arising from any such suit or claim.”

21.

6 A bare reading of Section 69 of the Act of 1932 makes it clear that the said provision is applicable only to suits arising out of a contract. In other words, it bars the institution of a suit by or on behalf of a partnership firm against a third party unless the partnership firm is duly registered.

21.

7 In the opinion of this Court, the said provision cannot be applied to the present writ petition for more than one reason.

21.

8 Firstly, the State-respondent Nos. 1 to 3, never prescribed in the NIB that a joint venture was required to be registered as a partnership firm. The only condition stipulated in the NIB was that the parties should execute a valid joint venture agreement for carrying out the work jointly.

21.

9 Secondly, the learned Advocate General has failed to place on record any document to demonstrate that, in the case of a joint venture agreement, registration of the joint venture as a partnership firm was a mandatory requirement. Consequently, this Court finds that the said contention is nothing but an afterthought

[2026:RJ-JP:27270] (39 of 77) [CW-14206/2024] on the part of the State-respondent Nos. 1 to3. Accordingly, the argument deserves to be rejected.

21.

10 The view of this court is further fortified by the principles laid down by the Hon'ble Supreme Court in Umesh Goel (Supra). The Apex Court held that the bar under Section 69(3) of the Act of 1932 applies only where the proceedings are intrinsically connected with a suit instituted in a Court by an unregistered firm or its partner. It further clarified that the expression "other proceedings" is confined to proceedings arising out of or incidental to such suits, and does not extend to independent proceedings. The relevant observations and principles enunciated in the aforesaid judgment, which are germane to the adjudication of the present controversy, are reproduced hereinbelow:

“14. As far as the construction of the said sub-section (3) of Section 69 is concerned, we are able to discern the above legal position without any scope of ambiguity. To be more precise, the condition precedent for the operation of ban under sub-section (3) is that the launching of a suit in a court of law should be present and it should be by an unregistered firm or by a person claiming to be partner of an unregistered firm either to a claim for set-off in the said suit or any other proceedings intrinsically connected with the said suit.

15.

In the event of the above ingredients set out under sub-sections (1), (2) and (3) being fulfilled then and then alone the ban prescribed against an unregistered firm under Sections 69(1), (2) and (3) would operate and not otherwise.

16.

Keeping the above outcome of the legal position that can be derived from a reading of sub-sections (1),

[2026:RJ-JP:27270] (40 of 77) [CW-14206/2024] (2) and (3) of Section 69 in mind we can draw further conclusions by making specific reference to clauses (a) and (b) of sub-section (3) as well as the exceptions set out in clauses (a) and (b) of sub-section (4) as well. When under sub-section (3) which also relates to a ban concerning “other proceedings”, the law-makers wanted to specifically exclude from such ban such of those proceedings which are also likely to arise in a suit, but yet the imposition of ban of an unregistered firm need not be imposed. Keeping the said intent of the law- makers in mind, when we read clauses (a) and (b) of sub-section (3), it can be understood that even though such other proceedings may be for the enforcement of any right to sue but yet if it is for the dissolution of a firm or for accounts of a dissolved firm or any right or power to realise the property of a dissolved firm, the same can be worked out by way of a suit in a court or by way of other proceedings in that suit and the same will not be affected by the ban imposed under sub- section (3). Similarly, any steps initiated at the instance of an official assignee, a receiver or court under the Presidency Towns Insolvency Act, 1909 (3 of 1909) or the Provincial Insolvency Act, 1920 (5 of 1920) to realise the property of an insolvent partner in a pending suit of a court also stand excluded from the ban imposed under sub-section (3). The specific exclusions contained in clauses (a) and (b) of sub-section (3), therefore, makes the position clear to the effect that even though such proceedings may fall under the expression “other proceedings” and may be intrinsically connected with a suit in a court, yet the ban would not operate against such proceedings.

17.

When we read sub-section (4), the ban imposed under sub-sections (1), (2) and (3) will have no application to any of those proceedings set out in clauses (a) and (b) of the said sub-section (4). A

[2026:RJ-JP:27270] (41 of 77) [CW-14206/2024] specific reference to clause (b) of sub-section (4) disclose that in the last part of the said sub-clause it is specifically provided that other proceedings incidental to or arising from any suit or claim of set-off not exceeding Rs 100 in value under those specific statute referred to in the said sub-clause can also be launched without any ban being operated as provided under sub- sections (1), (2) and (3). The said part of clause (b) of sub-section (4) thus gives a vivid picture as to the position that the “other proceeding” specified in the said sub-section can only relate to a pending suit in a court and not to any other different proceeding which can be categorised as “other proceedings”. ......

22.

Under the Partnership Act, the expression “court” is not defined. In Section 2(e) of the said Act though it is stated that the expressions used but not defined, the definition in the Contract Act, 1872 can be applied, in the Contract Act also there is no specific definition set out for the expression “court”. However, we find a definition of the “court” in Section 2(1)(e) of the 1996 Act, which reads as under:

“2. Definitions.—(1) In this Part, unless the context otherwise requires— (a)-(d) *** (e) “Court” means the Principal Civil Court of Original Juri iction in a district, and includes the High Court in exercise of its ordinary original civil juri iction, having juri iction to decide the questions forming the subject- matter of the arbitration if the same had been the subject-matter of a suit, but does not include any civil court of a grade inferior to such Principal Civil Court, or any Court of Small Causes;”.

21.

11 Thus the objection is devoid of merits and deserves to be rejected.

[2026:RJ-JP:27270] (42 of 77) [CW-14206/2024]

22.

Now coming to the merits of the writ petition. To decide the writ petition this Court deems appropriate to quote some of the provisions of the NIB relevant for the purpose of the writ petition:- “GENERAL INSTRUCTIONS”

17.

All bids, in which any of the prescribed conditions are not fulfilled or which have been vitiated by errors in calculations, totaling or discrepancies in figures or words or other discrepancies, will be liable to rejection.

18.

No conditional bids shall be accepted and will be rejected summarily forthwith.

23.

The acceptance of the bid rest with the competent authority who does not bind itself to accept the lowest bid, and reserves to itself the authority to reject any or all the bids received without assigning any reason. “CHAPTER 1 INSTRUCTIONS TO BIDDERS (ITB)”

1.

8 The bidders is required to study all instructions, forms, terms and conditions and other details in the bid documents. Failure to furnish information by the bid documents or submission of a bid not substantially responsive to the bid documents in every respect will be at the bidder’s risk and may result in rejection of its bid.

1.

12 Bidders shall submit only unconditional bids. Conditional bids are liable to be rejected summarily. The bid documents show already the specific terms and conditions on which bids are required by the Department. Hence all bids should be in strict conformity with the bid documents and should be fulfilled in wherever necessary, and initiated. Incomplete bid is liable to be rejected. The terms and conditions of the bid documents are firm, as such conditional bids are liable to be rejected. NOTE: The bidder should provide all the prequalification information in the prescribed formats along with

[2026:RJ-JP:27270] (43 of 77) [CW-14206/2024] satisfactory work completion certificates from an officer not below the rank of Executive Engineer or equivalent duly Self Attested/Notary attested.

7.

Omissions, Errors

and clarification; Pre- Tender Meeting

7.

3 Tenderers shall carefully examine the scope of work and specifications and fully inform themselves as to the conditions and matters, which may in any way affect the work or the cost thereof. Should a Tenderer find discrepancies or omissions in the documents or should he be in doubt as to their meaning he should notify the Deptt. in writing not later than one week earlier or present his request in written form during the pre-bid meeting. The Deptt. will respond to any request which is made prior to or during the pre-bid conference. No such request after the pre- bid meeting shall be entertained. Any resulting interpretation or modification of the tender documents shall be issued to all tenderers as an addendum, which will become a part of the tender documents. The tenderers shall acknowledge in writing the receipt of each addendum. No claims except as otherwise expressly provided will afterwards be accepted due to non- understanding or mis-interpretation of the tender documents.

15.

Format and signing of bid

15.

5 All bids, in which any of the prescribed conditions are not fulfilled or which have been vitiated by errors in calculations, totaling or other discrepancies or which contain over-writing in figures or words or corrections not initialed and dated, may be liable to rejection.

16.

Sealing and marking

16.

2 Contents of Cover-1- It should contain following:- 7. Bankers/financial institutions sanction letters for desired fund and non-fund- based credit facilities available (shall be of period with in 3 months from the date of opening of prequalification bid) (From FIN- 2).

8.

An affidavit on Rs. 500 stamp paper illustrating the list of works, its cost and all information in brief of which are in hand for execution for calculation of bidding capacity (Form FIN-3).

10.

Declaration of Historical Contact Non- performance on Rs. 500 stamp (Form FIN- 05).

20.

Schedule-2; Statement having read the tender document.

21.

Schedule 3.1; Undertaking 22. Schedule 3.2; Deviation from technical specification 23. Schedule 3.3; Deviation from condition of contract 24. Summary of financial information prescribed in Schedule 4

F. Bid Opening and Evaluation

[2026:RJ-JP:27270] (44 of 77) [CW-14206/2024]

19.

Opening of bids by department

19.

1 Additional Chief Engineer, Project PHED, Bharatpurorother

duly

authorized Committee will open the bids online on website in the presence of Bidder(s) or their authorized representative(s) who may choose to be present at the time of bid opening. The bids shall be opened in two stages. In first stage, the pre- qualification bid shall be opened and evaluated. The financial Bid by competent authority, shall be opened at a later date, which will be informed to all responsive and pre-qualified bidders.

20.

Preliminary Examination of bids

20.

3 Substantial bid Notwithstanding

the preliminary examination,

the department

will determine

the substantial

bidder. Substantial bids are those which meet the following requirements: Properly digitally signed, Bid Security fees, Bid document cost and Bid processing fee, Responsive to all requirements of the bid documents and the instructions to bidders, Clarification and substantiation required to assess the quality of the offer, No deviations from terms and conditions (vol.- I), scope of work and Specifications (vol.- II), Drawings (vol.-III) and Preamble to Price Schedule and reservations affecting the scope and quality of the work, limiting the rights of the Department. Or the bidder’s obligations, or whose rectification would affect the competitive position of the other substantial bidder.

20.

4 If a bid is not substantially responsive it will be rejected by the Department and will not be used for further evaluation. The financial offers of non responsive bidder will ot be opened. The Department’s determination of a bid’s responsiveness is to be based on the contents of the bid itself without recourse to extrinsic evidence. It is expressly stated that the information contained in the Cover-1 of the bid will be used to define whether a bid is substantial or not. The Bidders and therefore, advised to submit complete bids only.

21.

Evaluation for pre-qualification

21.

3 The Department reserves the right not to consider any deviation that in the sole discretion of the Department is found unacceptable. The Department shall require such deviations to be withdrawn, for the unaccepted deviations. The evaluation subsequently will be made on the rates quoted for such items in original offer.

23.

The questions for consideration before this Court is whether, merely on reading the bank certificate dated 21.05.2024 issued by the Bank of India in favour of one of the joint venture partners,

[2026:RJ-JP:27270] (45 of 77) [CW-14206/2024] namely M/s HES Infra Pvt. Ltd. (the lead partner), it could have been concluded that the petitioner joint venture was not in possession of the requisite credit facility available within three months from the date of opening of the pre-qualification bid.

24.

Further, this Court is required to examine whether, under the RTPP Act, 2012 as well as the Rule of 2013, the procuring authority had the power to seek clarification. This Court is also required to consider whether the respondents exercised their discretion properly by seeking clarification from one party, namely respondent No. 4, while not seeking a similar clarification from the present petitioner, and whether such action amounts to discrimination.

25.

Both the parties have strongly relied upon the NIB. Learned counsel for the respondents submitted that FIN-2 was a mandatory document and ought to have been submitted by the petitioner accurately and in the prescribed format so as to establish, beyond doubt, that each party to the JV possessed the financial capacity of more than 10% of the estimated project cost, which is approximately Rs.19.265/-Crores.

25.

1 This Court finds that, as per the contents of Cover-1 of the NIB, particularly Clause 16.2 of Volume-I at page No.102 of the paper book of the writ petition, Clause 7 & 8 reads as under:

“7. Bankers/financial institutions sanction letters for desired fund & non-fund-based credit facilities available (shall be of period with in 3 months from the date of opening of prequalification bid) (Form FIN-2). 8.An affidavit on Rs 500 stamp paper illustrating the list of works, its cost and all information in brief of which

[2026:RJ-JP:27270] (46 of 77) [CW-14206/2024] are in hand for execution for calculation of bidding capacity (Form FIN-3).”

25.

2 Both the parties admit that these documents were mandatory and were required to be submitted as part of Cover-1 of the bid.

25.

3 This Court further finds that the Evaluation Committee, while considering the bids in its meeting held on 25.06.2024 has recorded as under: “OFFICE OF THE CHIEF ENGINEER (SPECIAL PROJECTS)

PUBLIC

HEALTH

ENGINEERING DEPARTMENT RAJASTHAN F-18, New Building, I Floor, 2, CIVIL LINES-JAIPUR-302006 0141-2220553 email: rj_cesp@nic.in No.:F.724(1A)(Bid)/CE(SP)/PHED/CDBP/JJM/Pkg- 1A/2024-25/407-412 Dated: 25/6/24 MINUTES OF MEETING OF BID EVALUATION COMMITTEE (NIT No. 10/2023-24 of ACE(P) Bharatpur) 1) A meeting of Bid Evaluation Committee of CE(SP), PHED was held on 24.06.2024 at 4.00 PM in chamber of CE(SP) PHED, at Jal Bhawan, Jaipur to discuss and deliberate on technical bids of the work of EMI at existing Intake well at Chambal River. Raw Water pipeline from Intake to RWR-1 and RWR-2 at Dholpur, Main Raw Water Pumping Stations at RWR-1 & RWR-2. WTP 135 MLD Near RWR-02 & 5.0 MLD at Dholpur, Cluster Pumping Station, WTP 5.0 MLD at Dholpur, Cluster Pumping Station, CDS, VDS, and Rising Mains & FHTC for Dholpur & Saipau Block including allied works (Package-01A), put to bidding on percentage rate basis single point responsibility turn-key contract vide NIT No. 10/2023-24 of the office of ACE(P), Bharatpur. Estimated Cost: Rs. 1284.30 Cr, opened online on 22.05.2024 and submitted by ACE(P) Bharatpur vide Rajkaj Ref. no. 8046083 dated 13.06.2024 to the office of CE(SP), Jaipur.

[2026:RJ-JP:27270] (47 of 77) [CW-14206/2024] 2 Following Members of Committee were present in the meeting: - (i) Sh. Sandeep Sharma, Chief Engineer (SP) PHED (ii) Sh. Ramesh Sankhla, FA (JJM) PHED Jaipur (iii) Sh. Vikas Gupta, SE & TA to CE (SP), PHED 3) At the outset of the meeting, following facts of the case were presented by SE&TA to CE(SP) before the Bid Evaluation Committee: - i. Online bids were floated through NIT No. 10/2024-25, issued by the office of Additional Chief Engineer (Project), PHED, Region Bharatpur and uploaded on SPPP on 15.09.2023 and on e- procurement portal on 15.09.2023. The NIT was also published in newspapers through DIPR. ii. Pre-bid meeting for the NIT was held on 27.09.2023. As per the schedule, the technical bids were opened on 22.05.2024. On scrutinizing e- procurement details, 04 bidders submitted their bids: I. M/s Megha Engineering and Infrastructure Ltd. II. M/s NCC Limited. III. M/s SPML-JWIL JV (JV of M/s SPML Infra Ltd. And M/s JWIL infra Ltd.) IV. M/s GVPR-HES JV (JV of M/s GVPR Engineers Limited and M/s HES Infra Pvt. Ltd.) iii. On examining, it was found that four (4) bidders have deposited bid document fee. RISL processing fee and bid security physically. In light of above, the technical bids of the bidders were downloaded and processed by ACE(P) Bharatpur, 4) ACE (P) Bharatpur submitted evaluation statement for prequalification bid to the office of CE (SP) through letter vide Rajkaj Ref. no. 8046083 dated 13.06.2024. Documents submitted by bidder were further scrutinized at CE(SP) office and FA(JJM) office. Findings are listed as below:- l. M/s Megha Engineering and Infrastructure Ltd.

[2026:RJ-JP:27270] (48 of 77) [CW-14206/2024] A. The firm is registered in AA class in PHED Rajasthan. B. Bid document fee and Bid processing fee have been submitted through e-challan. However, it does not have reference of either NIT or the tendered work. C. Bid security has been submitted in the form of Bank Guarantees. D. The bidder meets the requirement of financial Criteria as per bid documents ie. Average Annual Turnover, Net Worth, Credit Limit, Bidding Capacity and financial stability. E. The bidder meets requirement of technical criteria. F. ACE(P) Bharatpur has recommended the bidder as responsive subject to clarification/lacking documents meeting TD requirement. II. M/s NCC Limited. A. The firm is registered in AA class in PHED Rajasthan. B. Bid document fee and Bid processing fee have been submitted through e-challan. C. Bid security has been submitted in the form of Bank Guarantee. D. The bidder meets the requirement of financial Criteria as per bid documents i.e. Average Annual Turnover. Net Worth. Credit Limit. Bidding Capacity and financial stability. E. The bidder meets requirement of technical criteria F. FIN-5 for History of non performing contract, submitted by the bidder, is not as per the prescribed FIN-5 format. G. ACE(P) Bharatpur has recommended the bidder as responsive subject to clarification/lacking documents meeting TD requirement. III. M/s SPML-JWIL JV. A. Both the firms in JV are registered in AA class in PHED Rajasthan.

[2026:RJ-JP:27270] (49 of 77) [CW-14206/2024] B. Bid document fee and Bid processing fee have been submitted through e-challan. C. Bid security of 2% of NIT cost has been submitted in the form of Bank Guarantee. D. The bidder meets the requirement of financial Criteria as per bid documents i.e. Average Annual Turnover, Net Worth, Credit Limit, Bidding Capacity and financial stability. E. The ratio of JV agreement between M/s SPML and M/s JWIL is shown as SPML 51% (Fifty Percent) and JWIL 49% (Forty Nine Percent) having discrepancy in figures and words. Also, in the JV agreement, it is written that SPML shall be the Partner-in-Charge of the JV and JWIL shall be the other member of JV. There is no clear mention of lead partner of JV. Further, requirement for consent of the Department for modification /amendment in JV agreement has not been mentioned. F. M/s JWIL. in its bidding capacity affidavit has mentioned additional line that "This is also certified that other orders under execution by the firm shall not materially affect the bidding capacity of the firm as required in this tender". Clarification in this regard is required from the bidder. Clarification is also required regarding M/s SPML's FIN-3 for bidding capacity wherein a note is given that 'Figures are without considering unbilled and O&M portion. Projects which have financial liability for SPML have been shown above, whereas substantially completed projects and projects wherein SPML is only technical partner is not listed’. G. The bidder meets requirement of technical criteria. H. FIN-5 for History of non performing contract, submitted by M/s JWIL, Is not as per the prescribed FIN-5 format. H. ACE(P) Bharatpur has recommended the bidder as responsive subject to clarification/lacking documents meeting TD requirement.

[2026:RJ-JP:27270] (50 of 77) [CW-14206/2024] IV. M/s GVPR-HES JV. A. M/s GVPR Engineers Ltd., the lead partner, is registered in AA class in PHED Rajasthan and the other partner M/s HES Infra Pvt. Ltd. is registered in AA class in WRD, Rajasthan. B. Bid document fee and Bid processing fee have been submitted through e-challan. C. Bid security of 2% of NIT cost has been submitted in the form of Bank Guarantee. D. PQ requirement for Credit Limit criterion: As per the eligibility criteria for prequalification of bidders regarding credit limit each member of JV must meet at least 10% of the credit limit requirement (Rs. 19.264 Cr out of total requirement of Rs. 192.64 Cr for the bidder in this bid). As per bid document (PQ criteria), the credit limit requirement is as under. "Credit limit (Fund based and non fund based) unutilized and available with the bidder shall not be less than 15% (Rs. 192.64 Cr in this bid) of the estimated cost of work. Further, the certificate of credit limit to be issued by the Bank in FIN-2 for certification of unutilized and available credit limit should be of period within 3 months from date of opening of pre-qualification bid. Bidder's credit limit as per the technical bid: The bidder has submitted certificate of Bank of India dated 21.05.2024 in favour of M/s HES (the other partner of JV bidder), which mentions as under: "We hereby advise that if the contract for the work is awarded to the firm, we shall be able to provide working capital facilities to the extent of Rs. 20 Crore to meet your working capital requirements for executing the contract during the contract period through consortium banking arrangements subject to bank's extent guidelines on the same." The above advice of Bank clearly reveals that the firm does not have unutilized and available credit limit on the date of issue of the same on 21.05.2024 (i.e. before opening of prequalification bid, as per PQ

[2026:RJ-JP:27270] (51 of 77) [CW-14206/2024] criterion). As the certificate is clear regarding non availability of credit limit of Rs. 19.264 Crore with the JV partner, no clarification from the Bank or the bidder is needed. So, the bidder does not meet this criterion. The bidder does not meet the requirement of financial Criteria. E. In form FIN-1 of the lead partner M/s GVPR, total assets and total liabilities are shown as same and liabilities are not matching with CA's certificate. Further, the CA's certificate does not mention name of firm. F. In case of JV partner M/s HES FIN-1 in prescribed format and CA certificate, as required in the bid document, are not found in the technical bid. Further, CA certificate in support of financial stability (FIN-4), as required in bid document, is not found in the technical bid. GST Coruncate does not bear digital signature. G. The bidder meets requirement of technical criteria I. FIN-5 for History of non performing contract, submitted by Ms JWIL, is not as per the prescribed FIN-5 format. J. ACE(P) Bharatpur has recommended the bidder as non-responsive on account of not meeting financial criteria with regard to credit limit requirement, may be decided by BEC. 5) Bid Evaluation Committee deliberated the responsiveness of bidders as follows- Sr. No Name of bidder Status Clarification / Lacking Documents/comments

1.

M/s Megha Engineering and Infrastructure Ltd. Responsive subject to compliance by ACE(P) Bharatpur of the comments made by BEC

1.

As the e-challan for bid document and bid processing fees do not have reference of either NIT or the tendered work, deposition of the required amount against this NIT be verified from the concerned division.

[2026:RJ-JP:27270] (52 of 77) [CW-14206/2024]

2.

M/s NCC Limited. Responsive subject to compliance by ACE(P) Bharatpur of the comments made by BEC

1.

Clarification regarding FIN-5 in prescribed format, as lacking document, be sought.

3.

M/s SPML-JWIL JV Responsive subject to compliance by ACE(P) Bharatpur of the comments made by BEC

1.

Clarification regarding FIN-5 of M/s JWIL in the prescribed format, as lacking document, be sought.

2.

Clarification for lacking in JV agreement, as mentioned at (4) III. E above be sought.

3.

Regarding additional line in the affidavit for bidding capacity given by M/s JWIL and a note in FIN-3 by M/s SPML., as mentioned at (4) III.F above, clarification shall be taken from the bidder that no liability whatsoever exists except mentioned in the bidding capacity. 4 M/s GVPR-HES JV Non-responsive The bidder does not meet financial criteria (PQ criteria) with regard to credit limit requirement, as mentioned at (4) IV. D, above. 6) In view of above and as per recommendation by the ACE (P) Bharatpur, the following decisions were taken: i. Responsiveness of the following bidders be decided by ACE (P) Bharatpur after compliance of the comments of BEC as mentioned above and compliance of point no. 06,7(2).08 and 13 of the checklist (Format-B) and submit compliance before FC:

[2026:RJ-JP:27270] (53 of 77) [CW-14206/2024] (a) M/s Megha Engineering and Infrastructure Ltd. (b) M/s NCC Limited (c)M/S SPML-JWIL JV ii. Following bidder is decided as non-responsive: (a) M/s GVPR-HES JV iii. Before declaring responsiveness of the bidders, following should be ensured by Addl. Chief Engineer (Project), Bharatpur: (a) It should be ensured that all required documents such as JV Agreement, JV Power of Attorney. Power of Attorney, Historical Contract Non- Performance, Affidavit (C), Bidding Capacity (Fin-3), Financial Stability (Fin-4), Bank Guarantee and all documents related to non-judicial stamp etc. are received in original on Stamp Paper. (b) Bank Guarantee submitted by the bidders towards bid security be got verified from issuing bank as per provisions of RTPP Rules 2013. (c) Compliance of Rule 43 of RTPP Rules 2013 regarding appropriate publicity of NIB and compliance of Rule 63(4) of RTPP Rules 2013 if responsive bidders are less than 3 and compliance of Rule 68 of RTPP Rules 2013, if there is single responsive bidder, be ensured. (d) Compliance of section 17 of RTPP Act 2012 and Rule 51(2) of RTPP Rules 2013 regarding publication of corrigendum on SPPP portal and Newspaper be ensured. (e) Compliance of Rule 11 of RTPP Rules 2013 be ensured. (f) It should be ensured that the bidding capacity submitted by the bidder is as per the requirement of bid document. (g) ACE(P) Bharatpur should ensure verification of GST registration certificate of the bidders. (7)ACE (P) Bharatpur is directed to ensure compliance of the comments given by BEC and meeting the bid requirements before proceeding for opening of the price bid of the responsive bidders.

[2026:RJ-JP:27270] (54 of 77) [CW-14206/2024] (8) ACE(P) Bharatpur is directed to keep evidence of publication on record as per rules, specially publication of corrigendum of bids etc. on portal and newspapers. (9) ACE(P) Bharatpur is to ensure that financial bid shall be opened at least 5 days after uploading the decision of ACE(P) Bharatpur on SPPP portal so that a fair amount of time remains available for bidders to appeal, if required. (10) ACE(P) Bharatpur is to ensure submission of rate justification to the office of Secretary 11 RWSSMB, Jaipur through Chief Engineer (SP), 3 days prior to opening of financial bid. (11) ACE(P) Bharatpur to ensure compliance of the directions of FD vide ID No. 102301081 dated 12.04.2023 and directions of NJJM dated 19.02.2024. The meeting ended with a vote of thanks to the Chair. No.: F.724(LA) (Bid)/CE(SP)/THED/CDBP/JJM/Pkg-1A/2024- 251407-412 Dated: 25/06/24

Reproduced from the public record of the Rajasthan High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.