Jaya Construction And Company And Anr. vs. The Bidhannagar Municipal Corporation

WPA/14632/2025HC CalcuttaGSTCNR WBCHCA030016202516 July 2025Bench: HON'BLE JUSTICE GAURANG KANTH3 pages
AI SummaryRemanded

Held

The Court noted the submission by the learned counsel for the respondent corporation that they are willing to decide the petitioner's representation dated 25.03.2025 within four weeks, after providing a personal hearing. Consequently, the Court disposed of the writ petition by directing the respondent corporation to decide the petitioner's representation strictly in accordance with law within four weeks from the date of receipt of a server copy of the order. This decision must be made after affording the petitioner an opportunity for a personal hearing and by passing a reasoned and speaking order. The outcome of this consideration is to be communicated to the petitioner within one week thereafter. The Court also clarified that if the petitioner is aggrieved by the speaking order, they are at liberty to challenge it in accordance with law. No affidavit was called for, so the allegations in the writ petition were not deemed admitted.

Facts

The petitioner, Jaya Construction & Company, was awarded a work order by the respondent, Bidhannagar Municipal Corporation (BMC), on 03.10.2024. The petitioner completed the assigned work, and a completion certificate was issued by the Executive Engineer PWD on 05.03.2025. This certificate stated the final bill amount as Rs. 8,26,285/- (excluding GST & L.W. Cess) and Rs. 9,84,766/- (including GST & L.W. Cess). Despite the admitted contractual dues, the BMC failed to release the payment. The petitioner submitted a representation on 25.03.2025 seeking redressal, but the respondent corporation neither responded nor took steps to settle the dues.

Key Issues

1. Whether the respondent corporation has failed to discharge its contractual obligation to pay admitted dues to the petitioner, thereby necessitating judicial intervention through a writ petition? Petitioner's Argument: The petitioner argued that despite the completion of work and issuance of a completion certificate with an admitted bill amount, the respondent corporation has failed to release the payment. They further contended that their representation dated 25.03.2025 seeking payment has been ignored by the corporation, leaving them with no recourse but to approach the High Court. Respondent's Argument: The respondent corporation submitted that they are willing to decide the petitioner's representation dated 25.03.2025 within a period of four weeks from the date of receipt of a server copy of the order. They also stated their willingness to afford an opportunity of personal hearing to the petitioner.

AI-generated summary — verify with the full judgment below

16.07.

2025

Sl. No.25 Ct.3/ SG

W.P.A. 14632 of 2025 [Jaya Construction & Company & Anr. vs. Bidhannagar Municipal Corpn. & Ors.]

Ms. Sanghamitra Nandy

… … for the petitioner

Mr. Sirsanya Bandopadhyay,

Mr. Arka Kumar Nag,

Mr. Tirthankar Dey.

… … for the BMC

1.

Affidavit of service is taken on record.

2.

The petitioner has preferred the present writ petition alleging non-payment of admitted contractual dues by the respondent corporation.

3.

It is the case of the petitioner that the respondent corporation issued work order dated 03.10.2024 in favour of the petitioner, and he has duly executed the assigned work within the extended time period. Thereafter, the Executive Engineer PWD by his Memo No. 896/PWD/ROAD/BMC dated 05.03.2025 issued a completion certificate in favour of the petitioner, stating that the petitioner has completed the work within extended period under Bidhannagar Municipal Corporation. In the said certificate final bill amount was mentioned as Rs. 8,26,285/- (excluding GST & L.W. Cess) and Rs. 9,84,766/- (including GST

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Calcutta High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.