Jaya Construction And Company And Anr. vs. The Bidhannagar Municipal Corporation
Original PDF →Facts
The petitioner, Jaya Construction & Company, was awarded a work order by the respondent, Bidhannagar Municipal Corporation (BMC), on 03.10.2024. The petitioner completed the assigned work, and a completion certificate was issued by the Executive Engineer PWD on 05.03.2025. This certificate stated the final bill amount as Rs. 8,31,469/- (excluding GST & L.W. Cess) and Rs. 9,90,945/- (including GST & L.W. Cess). Despite the admitted bill amount, the BMC failed to release the payment. The petitioner submitted a representation on 25.03.2025 seeking redressal, but the BMC neither responded nor took steps towards settlement. Consequently, the petitioner filed a writ petition before the High Court.
Held
The Court held that the respondent corporation should decide the petitioner’s representation dated 25.03.2025 strictly in accordance with law. This decision must be made within a period of four weeks from the date of receipt of a server copy of the Court's order. The respondent is also required to afford the petitioner an opportunity of personal hearing and pass a reasoned and speaking order. The outcome of this consideration shall be communicated to the petitioner within one week thereafter. The Court noted that if the petitioner is aggrieved by the speaking order, they will be at liberty to challenge it in accordance with law. The Court did not delve into the merits of the GST or L.W. Cess amounts, as the primary issue was the non-payment of admitted contractual dues and the lack of response from the respondent.
Key Issues
1. Whether the respondent corporation has failed to act upon the admitted contractual dues of the petitioner, thereby violating their contractual obligations and potentially administrative law principles. This issue turns on the interpretation of the contractual terms and the duty of the respondent to process payments for completed work. Contentions: Petitioner: Argued that the respondent authority has failed to release the admitted bill amount despite the petitioner duly executing the assigned work and receiving a completion certificate. The petitioner also contended that the respondent corporation failed to respond to their representation dated 25.03.2025 or take any steps towards settlement. Respondent: Submitted that they are willing to decide the petitioner’s representation dated 25.03.2025 within a period of four weeks from the date of receipt of a server copy of the order, after affording an opportunity of personal hearing to the petitioner.
AI-generated summary — verify with the full judgment below
Cause title — parties, addresses and appearances
reasoned and speaking order.
The outcome of the said consideration shall be communicated to the petitioner within one week thereafter.
Needless to mention that if the petitioner is aggrieved by the speaking order, the petitioner will be at liberty to challenge the same in accordance with law.
With the above direction the present writ petition is disposed of.
Since no affidavit has been called for, the allegations made in the writ petition cannot be deemed to have been admitted.
3
Let urgent photostate certificate copy of the order, if applied for, be supplied to the parties on usual undertaking.
(Gaurang Kanth, J.)
Reproduced from the public record of the Calcutta High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.