Jaya Construction And Company And Anr. vs. The Bidhannagar Municipal Corporation

Original PDF →
WPA/14626/2025HC CalcuttaGSTCNR WBCHCA030002202516 July 2025Bench: HON'BLE JUSTICE GAURANG KANTH3 pages
AI SummaryRemanded

Facts

The petitioner, Jaya Construction & Company, was awarded a work order by the Bidhannagar Municipal Corporation (BMC) on August 22, 2023. The petitioner completed the assigned work within the stipulated time. A completion certificate was issued by the Executive Engineer, PWD, on May 24, 2024, confirming the completion of work under the BMC. The final bill amount was stated as Rs. 2,93,080/- (excluding GST & L.W. Cess) and Rs. 3,49,293/- (including GST & L.W. Cess). Despite the admitted bill amount, the BMC failed to release the payment. The petitioner submitted a representation on March 25, 2025, seeking redressal, but received no response or action from the respondent authority.

Held

The Court directed the respondent corporation to decide the petitioner's representation dated March 25, 2025, strictly in accordance with law. This decision is to be made within a period of four weeks from the date of receipt of a server copy of the order. The respondent corporation must afford the petitioner an opportunity of personal hearing before passing a reasoned and speaking order. The outcome of this consideration is to be communicated to the petitioner within one week thereafter. The Court noted that if the petitioner is aggrieved by the speaking order, they are at liberty to challenge it in accordance with law. The Court also stated that since no affidavit was called for, the allegations made in the writ petition are not deemed to have been admitted. No specific issue regarding GST provisions was decided, as the dispute primarily concerned the payment of contractual dues.

Key Issues

1. Whether the respondent corporation has failed to discharge its contractual obligation to pay admitted dues to the petitioner, thereby necessitating judicial intervention under writ jurisdiction? The petitioner argued that despite the completion of work and the issuance of a completion certificate with an admitted bill amount, the respondent corporation has failed to release the payment. The petitioner further contended that their representation dated March 25, 2025, seeking expeditious settlement of dues, has been ignored by the respondent corporation, which has neither responded nor taken any steps towards payment. The respondent corporation, represented by its learned counsel, submitted that they are willing to decide the petitioner’s representation dated March 25, 2025, within a period of four weeks from the date of receipt of a server copy of the Court's order, after affording the petitioner an opportunity of personal hearing.

AI-generated summary — verify with the full judgment below

Cause title — parties, addresses and appearances
16.07.2025 Sl. No.23 Ct.3/ SG W.P.A. 14626 of 2025 [Jaya Construction & Company & Anr. vs. Bidhannagar Municipal Corpn. & Ors.] Ms. Sanghamitra Nandy … … for the petitioner Mr. Sirsanya Bandopadhyay, Mr. Arka Kumar Nag, Mr. Tirthankar Dey. … … for the BMC 1. Affidavit of service is taken on record. 2. The petitioner has preferred the present writ petition alleging non-payment of admitted contractual dues by the respondent corporation. 3. It is the case of the petitioner that the respondent corporation issued work order dated 22.08.2023 in favour of the petitioner, and he has duly executed the assigned work within the stipulated time period. Thereafter, the Executive Engineer PWD by his Memo No. 86/PWD/ROAD/BMC dated 24.05.2024 issued a completion certificate in favour of the petitioner, stating that the petitioner has completed the work within stipulated period under Bidhannagar Municipal Corporation. In the said certificate final bill amount was mentioned as Rs. 2,93,080/- (excluding GST & L.W. Cess) and Rs. 3,49,293/- (including GST & L.W. Cess). 4. Learned counsel for the petitioner submits that, despite the admitted bill amount, the respondent authority has failed to release the amount due to the petitioner. In such circumstances, the petitioner was constrained to submit a representation dated 25.03.2025, seeking expeditious redressal of the grievance. 2 5. He further contended that despite receiving the said representation, the respondent corporation neither responded to it nor took any steps towards settlement of the admitted dues. 6. Learned counsel for the respondent corporation submits that the respondent is willing to decide the petitioner’s representation dated 25.03.2025 within a period of four weeks from the date of receipt of a server copy of this order after affording an opportunity of personal hearing to the petitioner. 7. In view of the submission made by the learned counsel for the respondent corporation, this Court deems it appropriate to dispose of the present writ petition by directing the respondent corporation to decide the petitioner’s representation dated 25.03.2025 strictly in accordance with law, within a period of four weeks from the date of receipt of a server copy of this order after affording the petitioner an opportunity of personal hearing and by passing a

reasoned and speaking order.

8.

The outcome of the said consideration shall be communicated to the petitioner within one week thereafter.

9.

Needless to mention that if the petitioner is aggrieved by the speaking order, the petitioner will be at liberty to challenge the same in accordance with law.

10.

With the above direction the present writ petition is disposed of.

11.

Since no affidavit has been called for, the allegations made in the writ petition cannot be deemed to have been admitted.

3

12.

Let urgent photostate certificate copy of the order, if applied for, be supplied to the parties on usual undertaking.

(Gaurang Kanth, J.)

Reproduced from the public record of the Calcutta High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.