Ashok Kumar Bajoria vs. Oil INDIA Limited
Held
The Court held that the settlement agreement dated January 7, 2020, was a fresh contract that superseded the arbitral award. The terms of the settlement clearly stipulated that payment of Rs. 7,18,87,644/- would amount to a full and final settlement of all claims and disputes under the contract, irrespective of the original award. The Court found that the award holder's contention that the award revived was not accepted because the settlement agreement explicitly stated that all claims would be settled upon payment as per paragraph 1 of the agreement. While the settlement agreement did not explicitly mention GST deductions, the Court noted that the award debtor claimed such deductions were permissible. The Court concluded that the execution case could not be entertained as the award holder sought to execute an award that had been given a go-by. However, the Court found that an additional amount of Rs. 18,27,651/- was payable by the award debtor to the award holder under the settlement agreement. The Court directed this amount to be transmitted to the award holder's bank account within two weeks. The Court also stated that the petitioner was at liberty to pursue remedies for the enforcement of the settlement agreement in an appropriate forum.
Facts
The petitioner, Ashok Kumar Bajoria (award holder), sought execution of an arbitral award dated November 30, 2019, against Oil India Limited (award debtor). The award directed the award debtor to pay Rs. 5,57,18,967/- plus interest. Subsequently, the parties entered into a settlement agreement on January 7, 2020, agreeing that the award debtor would pay Rs. 7,18,87,644/- (principal and awarded interest) in full and final settlement. The award holder claimed to have received Rs. 7,00,59,993/-, alleging a shortfall due to GST deductions made by the award debtor. The award debtor filed an application seeking dismissal of the execution case, asserting that the settlement agreement had been substantially fulfilled. The award holder contended that the settlement failed due to the non-payment of the full agreed amount, leading to the revival of the original award.
Key Issues
1. Whether the arbitral award dated November 30, 2019, revived due to the alleged non-payment of the full amount stipulated in the settlement agreement dated January 7, 2020, thereby allowing the execution of the award? (Question of law). Petitioner's arguments: The petitioner argued that the award had not been superseded by the settlement agreement. They contended that since the full amount agreed upon in the settlement was not paid, the settlement failed, and the original arbitral award should be executed. The petitioner further argued that the award debtor had no right to deduct GST as it was not part of the settlement agreement, and the deduction of over one crore rupees as GST rendered the payment contrary to the agreement. Respondent's arguments: The respondent argued that the settlement agreement constituted a new contract that superseded the award. They contended that the amount paid, despite GST deductions, was in full and final settlement as per the agreement. The respondent also submitted that GST deductions were permissible under law and the contract.
AI-generated summary — verify with the full judgment below
OCD 1 ORDER SHEET IA NO. GA-COM/2/2025 In EC/231/2023 IN THE HIGH COURT AT CALCUTTA COMMERCIAL DIVISION ORIGINAL SIDE
ASHOK KUMAR BAJORIA Vs OIL INDIA LIMITED
BEFORE: The Hon'ble JUSTICE SHAMPA SARKAR Date: 29th August, 2025. Appearance: Mr. Saurabh Bagaria, Adv. Ms. Nilanjana Adhya, Adv. Mr. Anurag Baaria, Adv. …for the petitioner
Mr. Aritra Basu, Adv. Mr. Uttam Kr. Mandal, Adv. Ms. Udita Mandal, Adv. Mr. Vivek Singh, Adv. . . .for the respondent.
The Court:
EC 231 of 2023 is an application for execution of the award dated November 30, 2019. 2. The award holder had filed a claim against the award debtor demanding payment on various heads, arising out of a contract dated April 7, 2009. The scope of the work was with regard to laying of pipe lines below the river Teesta in a Horizontal Directional Drilling Method. The work was to be completed within 12 weeks from the award of the job that is of April 23, 2009. The award holder claimed to have completed the work
2 on November 20, 2010 after a delay of 1 year 7 months. The delay according to the award holder was for unforeseen reasons.
According
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Calcutta High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.