Held

The Court held that the municipal authorities ought not to withhold the lawful and just dues of the petitioners. It noted that the petitioners were entrusted with executing a job to the extent of Rs. 4,66,593/- (including GST and LW cess) based on a work order, and that a certificate dated 02.02.2023 confirmed the satisfactory execution of the work, specifically the construction of a masonry box drain, to the full satisfaction of the Bidhannagar Municipal Corporation. The Court directed the municipal authorities to forthwith process the petitioners' bills as expeditiously as possible, preferably within six weeks from the date of communication of the order, and to disburse the just dues payable to the petitioners. The writ petition was disposed of with these directions.

Facts

The petitioners, M/s. C. Biswas & Anr., filed a writ petition seeking a direction for the disbursement of bills amounting to Rs. 4,66,593/-, including GST and LW cess, against a work order (NIT no.1136/PWD/BMC/ dated 14.06.2021) issued by the Bidhannagar Municipal Corporation (BMC). The petitioners submitted that they had executed the work satisfactorily, as evidenced by a certificate from the Executive Engineer of the BMC dated 02.02.2023, and had also made representations for payment. The BMC, through its counsel, stated that the petitioners had completed the job and the respondents were in the process of disbursing the due amount.

Key Issues

1. Whether the Bidhannagar Municipal Corporation is legally obligated to disburse the petitioners' bills for work executed under a valid work order, considering the satisfactory completion certificate issued. Petitioner's contention: The petitioners argued that they had executed the work as per the work order dated 14.06.2021 and that a completion certificate was in the process of being issued, as confirmed by the Executive Engineer's certificate dated 02.02.2023. They further contended that despite their representations, the bills raised had not been disbursed. Revenue/State's contention: The Bidhannagar Municipal Corporation, through its counsel, submitted that the petitioners had indeed completed the job and that the respondents were in the process of disbursing the amount due and payable to the petitioners.

AI-generated summary — verify with the full judgment below

11.

12.02.2026. Court No.03. (Pritam)

WPA 29463 of 2025. M/s. C. Biswas & Anr.

-Vs.-

The Bidhannagar Municipal Corporation & Ors.

Ms. Sanghamitra Nandy.

.....for the petitioners.

Mr. Sirsanya Bandyopadhyay,

Mr. Tirthankar Dey,

Mr. Arka Kumar Nag.

.....for the BMC.

1.

The instant writ petition has been filed, inter alia, praying for a direction upon the respondents to disburse the bills of the petitioners against the work order NIT no.1136/PWD/BMC/ dated 14.06.2021 amounting to Rs.4,66,593/- including GST and LW cess.

2.

Ms. Nandy, learned advocate appearing for the petitioners has not only drawn the attention of this Court to the work order dated 14.6.2021 but also to the certificate issued by the Executive Engineer of the BMC dated 2.2.2023 to impress upon this Court that the petitioners have not only executed the work satisfactorily but a completion certificate

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Calcutta High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.