Held

The Court held that the municipal authorities ought not to withhold the lawful and just dues of the petitioners. The Court noted that the petitioners were entrusted with work to the extent of Rs. 33,48,398/- including GST and LW cess, and that a certificate dated November 11, 2025, confirmed the satisfactory execution of the work. The Court directed the municipal authorities to forthwith process the petitioners' bills and disburse the just dues as expeditiously as possible, preferably within a period of 6 weeks from the date of communication of the order. The writ petition was disposed of with these directions.

Facts

The petitioners, Biswas Enterprise & anr., filed a writ petition seeking a direction for the disbursement of bills amounting to Rs. 33,48,398/- (including GST and LW cess) against a work order dated July 17, 2025, issued by The Bidhannagar Municipal Corporation (BMC). The petitioners asserted that they had satisfactorily executed the work, as evidenced by a certificate from the Executive Engineer of BMC dated November 11, 2025, and had submitted reminders and representations for payment. The BMC, through its counsel, acknowledged that the work was completed and that the amount due was being processed for disbursement.

Key Issues

1. Whether the Court should direct the respondents to disburse the outstanding bills of the petitioners for work executed under a specific work order, considering the petitioners' claim of satisfactory completion and the respondents' acknowledgment of the work and processing of payment. The petitioners argued that they had executed the work as per the work order dated July 17, 2025, and that a completion certificate was in process. They relied on their representation dated January 10, 2025, to highlight the delay in payment. The respondents (BMC) contended that the petitioner had indeed completed the job and that the process for disbursing the amount due was underway.

Sections Cited

GST

AI-generated summary — verify with the full judgment below

24.03.

2026 Ct. 3 Item No. 04 sayandeep

WPA 2108 of 2026

Biswas Enterprise & anr. Versus The Bidhannagar Municipal Corporation & Ors.

Ms. Sanghamitra Nandy …For the petitioners Mr. Sirsanya Bandyopadhyay Mr. Tirthankar Dey Mr. Arka Kr. Nag …For the BMC

1.

The instant writ petition has been filed, inter alia, praying for a direction upon the respondents to disburse the bills of the petitioners against the work order NIT no. 219/PWD/Road/BMC/ dated 17.07.2025 amounting to Rs.33,48,398/- including GST and LW cess.

2.

Ms. Nandy, learned advocate appearing for the petitioners has not only drawn the attention of this Court to the work order dated 17.07.2025 but also to the certificate issued by the Executive Engineer of the BMC dated 11.11.2025 to impress upon this Court that the petitioners have not only executed the work satisfactorily but a completion certificate is in the process of being issued.

3.

Ms. Nandy submits that although, the petitioners have from time to time issued reminders, the bills raised by the petitioners have not been disbursed. In this context, she has placed reliance on representati

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Calcutta High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.