M/S Nirman Construction And Anr vs. Union Of INDIA And Ors.
Held
The Court held that the act of the respondent authorities in invoking the Bank Guarantee was arbitrary and illegal. The Court found that the petitioners had completed the work on December 31, 2023, and the respondents had taken possession of the completed work. No communication regarding any defects was made to the petitioners after completion. The guarantee period of one year also expired on December 31, 2024, without any complaints. The respondents attempted to invoke the Bank Guarantee after more than two years and three months, which was deemed unjustified. The Court noted that the respondents' claim of excess payment was not supported by documents showing any notice issued for recovery. The Court also found that the completion certificate was withdrawn by an email dated May 15, 2024, without stating any reasons, and no subsequent communication regarding defects was made. The Court distinguished the judgments relied upon by the respondents. The Court set aside and quashed the letter dated March 23, 2026, directing the bank to encash the guarantee. The ratio decidendi is that a bank guarantee cannot be arbitrarily invoked after the work is completed, the defect liability period has expired without complaint, and no proper notice for alleged excess payment or defects has been issued.
Facts
The petitioners, M/s. Nirman Constructions & Anr., filed a writ petition seeking to restrain respondent no. 2 from encashing a Bank Guarantee of Rs. 7,16,346/-. The petitioners were awarded a work order on December 15, 2022, for modification/rebuilding of houses. They submitted a Performance Bank Guarantee of Rs. 7,16,346/- on February 2, 2023. A completion certificate was issued on May 2, 2024, stating the work was completed on December 31, 2023. The final bill was paid on January 20, 2024. However, the retention money of Rs. 20,22,950/- remained unreleased. On March 23, 2026, the respondents requested the bank to encash the Bank Guarantee. The petitioners argued that the work was completed satisfactorily, the guarantee period had expired without complaints, and the bank guarantee invocation was unjustified and without notice. The respondents contended the writ petition was not maintainable, the completion certificate was revoked, and an excess payment was made to the petitioners.
Key Issues
1. Whether the invocation of the Bank Guarantee by the respondents is arbitrary and illegal, considering the completion of the work and the expiry of the defect liability period? (Question of law and fact, turning on the interpretation of contract terms and the effect of the completion certificate). Petitioner's arguments: The petitioners argued that they had executed and completed the work to the satisfaction of the respondents, as evidenced by the completion certificate issued on May 2, 2024. They contended that the defect liability period, which was one year from the completion date of December 31, 2023, had expired on December 31, 2024, without any complaints. They further argued that the respondents' action to encash the bank guarantee on March 23, 2026, was without any prior notice or justification, especially since the final bill had been paid and retention money was still held. They also pointed out that the email communication regarding measurement sheets was sent to an incorrect email address. Respondents' arguments: The respondents argued that the writ petition was not maintainable due to suppression of facts and that a beneficiary is entitled to invoke a bank guarantee. They claimed the completion certificate was revoked by an email on May 15, 2024, and that an excess payment of Rs. 30,43,383.94 (excluding GST) was made to the petitioners based on measurement sheets, making a total recoverable amount of Rs. 35,91,192.94. They relied on judgments in Ansal Engineering Projects Limited vs. Tehri Hydro Development Corporation Limited & Anr. and Standard Chartered Bank vs. Heavy Engineering Corporation Limited & Anr. to assert that a bank guarantee is an independent contract and cannot be interfered with unless fraud or special equity exists. They also mentioned the petitioners were habitual defaulters and had been blacklisted.
Sections Cited
Section 73, Section 129, Rule 86A
AI-generated summary — verify with the full judgment below
IN THE HIGH COURT AT CALCUTTA (Constitutional Writ Jurisdiction) APPELLATE SIDE
Present: The Hon’ble Justice Krishna Rao
WPA No. 7814 of 2026
M/s. Nirman Constructions & Anr. Versus The Union of India and Others
Mr. Sayan Chattopadhyay
Ms. Suprava Jana Ms. Sushama Hansda
.....For the petitioners.
Mr. Sauvik Nandy, Sr. Adv. Mr. Dyutimoy Paul .....For the respondent nos. 2 & 3. Hearing Concluded On : 31.03.2026 Judgment on : 02.04.2026 Krishna Rao, J.:
The petitioners have filed the present writ petition praying for a direction restraining the respondent no. 2 from encashing the Bank Guarantee dated 2nd February, 2023 for an amount of Rs. 7,16,346/-.
2
The respondents have issued Letter of Acceptance to the petitioners on 7th December, 2022 for modification/rebuilding of houses including plastering of walls, painting, tiling works in toilets and kitchen in Category-3 and above houses in DSP Township. In terms of the Letter of Acceptance, the respondents have issued the work order to the pet
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Calcutta High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.