M/S Greenbilt Industries Private Limited vs. M/S A B Dinesh Concrete Private Limited
Held
The Court held that the MOU dated February 9, 2022, was circulated via email and was not executed by the parties. The agreement dated April 3, 2023, between the directors was not an arbitration agreement between the companies. The Court found no evidence of a valid arbitration agreement between the petitioner and the respondent. The termination of the arbitral proceeding by the petitioner's nominee was noted. The Court concluded that the High Court at Calcutta lacked jurisdiction to act as a referral court as the cause of action did not arise within its territorial limits. The judgments relied upon by the petitioner were deemed inapplicable. Therefore, the application for the appointment of an arbitrator was dismissed. The petitioner was, however, permitted to proceed in accordance with law before the appropriate forum.
Facts
The petitioner, M/s Greenbilt Industries Private Limited, sought the appointment of an arbitrator to resolve disputes arising from the respondent's, M/s A B Dinesh Concrete Private Limited, alleged acquisition of the petitioner's ACC block manufacturing unit. An oral agreement was reached in October 2020 for the respondent to take over the plant for Rs. 21 crores, with an advance of Rs. 3 crores, forfeitable upon default. The respondent was permitted to run the plant during an interregnum, paying occupational charges. A written agreement dated December 7, 2020, was signed, and physical possession was handed over on December 10, 2020, with a partial advance payment. A Memorandum of Understanding (MOU) dated February 9, 2022, was circulated via email, containing an arbitration clause. The petitioner alleged the respondent failed to pay the balance advance, consideration, and occupational charges, and abandoned the plant by the end of 2020. The parties' directors mutually agreed on April 3, 2023, to invoke arbitration, nominating their respective arbitrators. The petitioner's nominated arbitrator terminated the proceeding on April 20, 2023, due to the respondent's and its arbitrator's absence. The petitioner then issued a demand letter and a notice under Section 15(2) of the Arbitration and Conciliation Act, 1996, for a substitute arbitrator, which the respondent contested, denying the existence of an arbitration agreement.
Key Issues
1. Whether Clause 12.3 of the MOU dated February 9, 2022, constitutes a valid and binding arbitration agreement between the parties, as contemplated by Section 7(4)(b) of the Arbitration and Conciliation Act, 1996? The petitioner argued that the exchange of the MOU via email constituted valid execution of an arbitration agreement, and even if the MOU were invalidated, the arbitration clause remained a separate and independent agreement. The petitioner further contended that the respondent's email dated February 1, 2024, admitting the MOU's existence, albeit alleging misrepresentation and fraud, indicated a subsisting arbitrable dispute. The respondent argued that the MOU had not been executed and that the petitioner had committed fraud and misled the respondent, resulting in financial loss. The respondent also disputed the jurisdiction of the High Court at Calcutta to entertain the application, asserting that the cause of action did not arise within its jurisdiction.
Sections Cited
Section 7(4)(b), Section 15(2)
AI-generated summary — verify with the full judgment below
IN THE HIGH COURT AT CALCUTTA (Commercial Division) ORIGINAL SIDE
Present: Hon’ble Justice Shampa Sarkar
AP (COM) 421 of 2024
M/S GREENBILT INDUSTRIES PRIVATE LIMITED VS M/S A B DINESH CONCRETE PRIVATE LIMITED
For the petitioner :
Mr. Kumarjit Banerjee, Adv. Ms. Sanchari Chakraborty, Adv.
For the respondent :
Mr.Sourav Kumar Mukherjee, Adv. Ms. Falguni Jana, Adv. Ms. Sahana Pal, Adv. Mr. SouhardyaMitra, Adv.
Hearing concluded on: 15.01.2025 Judgment on: 27.03.2025
Shampa Sarkar, J.:-
This is an application for appointment of a learned Arbitrator for settlement of disputes which allegedly arose out of a transaction for acquisition of the petitioner’s ACC block manufacturing unit, by the respondent. The petitioner contended that this Court must appoint an arbitrator, in view of the termination of the arbitration proceeding by Sri Prabir Gupta, petitioner’s nominee, on April 20, 2023. 2. According to the petitioner, the respondent wanted to take over the entire ACC block manufacturing plant situated at Karga
2
village, post office Jamgaon (M), District Durg (CG), which was approximately 25
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Calcutta High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.