Himani Refrigeration And Co. vs. The State Of Bihar
Original PDF →Facts
The petitioner, Himani Refrigeration and Co., a Class-III contractor, participated in a tender process initiated by the Building Construction Department for the SITC of VRV/VRF & Cassette Air Conditioning System. The petitioner's bid was found to be the lowest (L1 bidder) by the Divisional Tender Committee on October 16, 2023, and this recommendation was approved by the Circle Tender Committee on October 26, 2023, which directed the issuance of a work order. However, an objection was raised by other bidders regarding the validity of the petitioner's character certificate, which expired on September 26, 2023, while the tender submission deadline was October 10, 2023. Consequently, the Superintending Engineer, vide a letter dated December 12, 2023, cancelled the work order issued to the petitioner and issued a fresh work order to Sri Upendra Kumar Sinha. The petitioner filed a writ petition seeking the issuance of a work order and to restrain coercive steps, later amending it to challenge the cancellation and allotment to Sinha.
Held
The Court held that the petitioner's tender was liable to be rejected because Clause 27 of the NIT clearly stipulated the requirement of a valid character certificate, along with other documents, for bid submission. The petitioner's submitted character certificate was valid only up to September 26, 2023, which was prior to the tender submission deadline (October 10, 2023) and the bid opening date (October 12, 2023). The Court found the petitioner's reliance on the departmental letter to be misplaced, as the NIT was issued by the Electric Works Division No.1, Patna, and the terms of the NIT itself were not questioned. The Court distinguished the Supreme Court's decision in Rashmi Metaliks Ltd., noting that in this case, the character certificate was a clearly stipulated requirement in Clause 27 of the NIT, and no valid character certificate was produced even at the stage of the writ petition. The Court also observed that the application for a fresh certificate was made just one day before the tender submission deadline and no such certificate was produced. The Court concluded that the cancellation of the work order and the subsequent allotment to another bidder were justified based on the undisputed facts and the NIT's provisions. The writ petition was found to be without merit.
Key Issues
1. Whether the petitioner's tender was liable to be rejected for failing to submit a valid character certificate as per Clause 27 of the Notice Inviting Tender (NIT)? 2. Whether the petitioner's reliance on a departmental letter exempting character certificates from mandatory submission was applicable in this case? 3. Whether the Supreme Court's decision in Rashmi Metaliks Ltd. & Anr. Vs. Kolkata Metropolitan Development Authority & Ors. aids the petitioner's case? Petitioner's arguments: The petitioner contended that the character certificate was not an essential document required for a bid to be considered responsive, citing a letter dated February 17, 2022, from the Building Construction Department. They also relied on the Supreme Court's decision in Rashmi Metaliks Ltd., arguing that a minor discrepancy should not lead to disqualification without an opportunity for rectification. The petitioner argued that they had applied for a fresh certificate before the submission deadline. Revenue/State's arguments: The respondents argued that Clause 27 of the NIT explicitly required a valid character certificate, and the petitioner failed to provide one. They contended that the departmental letter cited by the petitioner was not applicable as the NIT was issued by a different division, and the terms of the NIT were not challenged. They also pointed out that the work order had already been cancelled, a fresh agreement executed with another bidder, and the work was nearing completion.
Sections Cited
Section 27
AI-generated summary — verify with the full judgment below
Cause title — parties, addresses and appearances
ORAL JUDGMENT (Per: HONOURABLE MR. JUSTICE HARISH KUMAR) Date : 28-03-2024 Heard learned counsel for the petitioner as well as 2/10 learned counsel representing the respondents.
The petitioner, a Class-III contractor, registered with Building Construction Department, has filed the present writ petition seeking a direction upon the respondents to issue work order in respect of SITC of VRV/VRF & Cassette Air Conditioning System in Labour Resources Department, A-Block and B-Block at 2nd Floor, Niyojan Bhawan, Bailey Road, Patna. The Divisional Tender Committee has recommended the lowest rate of bid offered by the petitioner in its meeting dated 26.10.2023. Further prayer has been made for issuance of status quo or restrain the respondent no.6 from taking any coercive steps during the pendency of the writ petition.
The short facts as gleaned from the records are that the petitioner was found eligible in response to the Extra Emergency Notice Inviting Tender (hereinafter referred to as ‘the NIT’) No. 22 of 2023-24 dated 21.09.2023 for the work in respect of SITC of VRV/VRF & Cassette Air Conditioning System in Labour Resources Department, A-Block and B-Block at 2nd Floor, in Niyojan Bhawan, Bailey Road, Patna wherein it has submitted tender.
The NIT stipulated the date for downloading the bid document in between 29.09.2023 to 10.10.2023 and the last 3/10 date for uploading the document was 10.10.2023 and the date for pre-bid meeting was fixed on 03.10.2023 in the office of the respondent no.
The date of opening of the Tender document was fixed on 12.10.2023. 5. It is contended on behalf of the petitioner that the Technical and Financial Bid were opened on 16.10.2023 by the Divisional Tender Committee and after having found the petitioner as L1 bidder, the Divisional Tender Committee recommended the name of the petitioner’s firm for Award of contract to the Circle Tender Committee. Subsequent thereupon, Circle Tender Committee in its proceeding dated 26.10.2023 approved the aforenoted recommendation and on finding petitioner’s firm tender to be responsive, directed the respondent no.6 to issue work order in favour of the petitioner’s firm. The copy of the proceeding dated 26.10.2023 is produced as Annexure-P/2. 6. Adverting to the aforesaid facts, Mr. Sanjeev Ranjan, learned Advocate further submitted that while considering the bid of the petitioner, the Circle Tender Committee in its proceeding dated 26.10.2023 has clearly stated that the character certificate of the petitioner is valid up to 26.09.2023 and the petitioner has filed certified copy of 4/10 application dated 09.10.2023 for issuance of fresh character certificate from the office of the Superintendent of Police, which was pending at that point of time. Learned counsel for the petitioner has also placed reliance on letter no. 1094 dated 17.02.2022 issued by the Building Construction Department prescribing the list of documents, which are required to be uploaded mandatorily in respect of tender documents involving contract of an amount of less than Rs.2,00,00,000/- (Two crores). Referring to the aforesaid letter, he submits that the character certificate is not an essential document, which was required to be filed by a bidder for the bid to be found responsive.
Reliance has also been placed on a decision rendered by the Apex Court in the case of Rashmi Metaliks Ltd. & Anr. Vs. Kolkata Metropolitan Development Authority & Ors., reported in (2013) 10 SCC 95. 8. In response to the averments made in the writ petition, a counter affidavit has been filed on behalf of respondent nos. 4, 5 and 6. 9. The facts narrated hereinabove on behalf of the petitioner to the extent that the bid submitted by the petitioner was found to be lowest and accordingly the work order was 5/10 issued in favour of the petitioner vide letter no. 2140 dated 26.10.2023, has been admitted by the respondent. But it is further contended that soon after issuance of the aforenoted letter, an objection was filed from Shreyas Enterprises and Upendra Kumar Sinha for verification of the tender documents, as the character certificate submitted by the petitioner was valid only up to 26.09.2023 and under Clause 27 of the NIT, the petitioner failed to upload a valid character certificate. Taking note of the objection received from the other contesting bidders, a request was made by the Electrical Executive Engineer vide its letter no. 2079 dated 11.11.2023 to the Superintending Engineer, Electric Work Circle, South Bihar to reconsider the comparative reports/statements and do needful in accordance with law.
In response thereto, it was directed to submit a comparative report with recommendation after making proper enquiry. The entire facts was again placed before the Superintending Engineer, Electric Work Circle, South Bihar and taking note of the said irregularity, the Superintending Engineer, Electric Work Circle, South Bihar vide its letter 2555 dated 12.12.2023 was pleased to cancel the previous work order no. 2140 dated 26.10.2023 issued in favour of the petitioner and a fresh work order was issued in favour of Sri Upendra Kumar 6/10 Sinha.
Learned Government Advocate further contended that in view of the letter dated 12.12.2023, a fresh agreement stands executed with Sri Upendra Kumar Sinha on 19.12.2023 and now the work is almost at the verge of completion.
Having heard the learned Advocate for the respective parties and after careful perusal of the materials, prima facie, this Court finds that the counter affidavit was duly sworn and filed on 21.02.2024 stating all the facts that the work order in favour of one Upendra Kumar Sinha was already issued after executing a fresh agreement in his favour on 12.12.2023 itself.
After receipt of the copy of the counter affidavit two interlocutory applications, bearing I.A. No. 1 of 2024 and I.A. No. 2 of 2024, have been filed seeking quashing of the order dated 11.11.2023 issued under the signature of respondent no.8 whereby the Tender Committee on reconsideration of comparative statements of the tender document submitted by the petitioner had found the tender of the petitioner to be non- responsive, as the petitioner had failed to upload the valid character certificate with the tender document. The petitioner 7/10 further sought quashing of letter dated 12.12.2023 whereby the work order issued to the petitioner had been cancelled and simultaneously, the work, in question, has been allotted to one Upendra Kumar Sinha; in such circumstances, the petitioner also prayed to implead Sri Upendra Kumar Sinha as party respondent in the present writ petition.
Now coming to the merit of the case in hand, Clause 27 of the NIT clearly stipulates that a bidder will have to produce Electrical License, up-to-date GST certificate, Pan Card, valid Character Certificate, self attested valid Character Certificate along with the bid documents.
Admittedly, the Character certificate submitted by the petitioner was valid up to 26.09.2023, thus, the date on which the bid document was uploaded i.e. in between 29.09.2023 to 10.10.2023, as also the date fixed for pre-bid meeting i.e. on 03.10.2023 and the date of opening of tender document fixed on 12.10.2023, the character certificate submitted by the petitioner was not a valid one, which fact is uncontroverted. Corresponding to such circumstances, the NIT, especially Clause 32 and 33 thereof clearly prescribes that during verification, if any document is found to be incorrect, the department shall be at liberty to take action and the competent 8/10 authority shall be at liberty to reject and cancel the tender.
Further the petitioner’ case is that he had applied for a fresh character certificate on 09.10.2023. In addition to the fact that no such fresh certificate has been produced, the application was just one day before 10.10.2023; which was the closure date of tender submission.
It is trite that, where on the admitted or undisputed facts, only one conclusion is possible and under the law only one consequence is permissible, then opportunity to show cause is not necessary, where facts are undisputed and the affected person could not put forth any valid defence even when opportunity is given by the Court/authority. In such circumstances, the Court may not insist on the observance of the principles of natural justice because it would be futile to order their observance and will be reduced to an empty formality
So far the reliance placed by the petitioner on a letter issued by the Building Construction Department that the character certificate shall not fall under the category of mandatory documents and filing of the same is not essential; it is wholly misplaced, as the NIT has been issued by the Electric Works Division No.1, Patna and moreover the terms of the NIT especially Clause 27 has never been questioned by the writ 9/10 petitioner. All the more, character certificate of a bidder has always been treated as vital document.
Now we come to the decision cited by the petitioner in the case of Rashmi Metaliks (supra) whereby the Hon’ble Supreme Court has held that the disqualification of the Appellant-company on the ground of it having failed to submit its latest Income Tax Return along with its bid is not sufficient reason for disregarding its offer/bid. The Hon’ble Supreme Court while considering the aforesaid issue found that in the Income Tax Return for the Assessment Year 2011-2012, the gross income of the Appellant-company was Rs.15,34,05,627, although, for the succeeding Assessment Year 2012-2013, the income tax was NIL, but substantial tax had been deposited. The Hon’ble Supreme Court further observed that the Income Tax Return would have assumed the character of an essential term if one of the qualifications was either the gross income or the net income on which tax was attracted. In many cases this is a salutary stipulation, since it is indicative of the commercial standing and reliability of the tendering entity. However, the feature being absent, the Apex Court found that the filing of the latest Income Tax Return was a collateral term, and accordingly the Tendering Authority ought to have brought this discrepancy 10/10 to the notice of the Appellant- company and if even thereafter no rectification had been carried out, the position may have been appreciably different. In view of the aforesaid premise, the Apex Court set aside the impugned judgment.
It would be worth noting here that in the present case Clause 27 of the NIT clearly stipulates the requirement of filing of valid character certificate and its consequence. Moreover, as we noticed, there is no character certificate produced even at this stage, despite an application said to have been made on 09.10.2023 which, even if produced would be inconsequential since in tendering the last date is sacrosanct due to the competition between the various tenderers.
In the aforesaid facts, circumstances and the position obtaining in law, the writ petition sans any merit, is fit to be dismissed.
uday/- (K. Vinod Chandran, CJ) (Harish Kumar, J) AFR/NAFR NAFR CAV DATE NA Uploading Date 03.04.2024 Transmission Date NA
Reproduced from the public record of the Patna High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.