M/S Ashutosh Enterprises vs. The Union Of INDIA
Held
The Court held that the contract was frustrated due to force majeure events, specifically the Covid-19 pandemic and the consequential nationwide lockdown. The Court found that the petitioner could not be held solely responsible for the non-commencement of the parking stand work, which was beyond their control. The Court reasoned that the nationwide lockdown and suspension of train services made the contract impracticable and useless from the perspective of its object and purpose, attracting Section 56 of the Contract Act, 1872. The Court relied on the Supreme Court's interpretation in Satyabrata Ghose and Delhi Development Authority cases, which held that 'impossible' in Section 56 includes impracticability arising from supervening circumstances not contemplated by the parties. The Court also found that the Ministry of Finance's Office Memorandum dated 19.02.2020, which included pandemics under force majeure and allowed termination without financial repercussions for delays exceeding 90 days, was applicable. The Court noted that the Ministry of Railways itself had acknowledged force majeure in similar situations. Consequently, the Court quashed the impugned order dated 01.02.2021 and directed the refund of the forfeited security amounts and license fees paid by the petitioner within three months.
Facts
M/s Ashutosh Enterprises, a proprietary concern, sought to quash an order dated 01.02.2021 by the Senior Divisional Commercial Manager, NF Railway, Katihar, which terminated their contract and forfeited securities and license fees. The petitioner had been awarded a parking stand contract at New Jalpaiguri Station. Following the Letter of Acceptance dated 28.02.2020, the petitioner deposited license fees and GST. However, a nationwide lockdown was announced on 24.03.2020 due to the Covid-19 pandemic, suspending all transport services, including rail. The petitioner contended that the contract became impossible to perform due to force majeure. Despite this, the Railways insisted on contract commencement and fee payment, leading to the petitioner invoking the force majeure clause on 26.10.2020 and requesting a refund of deposits. The impugned order was issued thereafter.
Key Issues
1. Whether the contract for the parking stand at New Jalpaiguri Station was frustrated due to force majeure events, specifically the nationwide lockdown and suspension of train services caused by the Covid-19 pandemic, thereby entitling the petitioner to termination without financial repercussions, as per Clause 26 of the tender document and Office Memorandum dated 19.02.2020? The petitioner argued that the nationwide lockdown, commencing on 24.03.2020, and the subsequent suspension and regulation of train services rendered the contract impossible to perform. They relied on Clause 26 of the tender document, which allowed for contract closure if performance was prevented for over three months, and the Office Memorandum dated 19.02.2020, which included pandemics in the force majeure clause and permitted contract termination without financial repercussions if performance was delayed for over 90 days. They also invoked Section 56 of the Contract Act, 1872, citing the Supreme Court's interpretation in Satyabrata Ghose and Delhi Development Authority cases regarding impossibility and impracticability of performance. The respondent Railways contended that the petitioner was declared the successful bidder and was bound by the terms and conditions of the tender. They argued that the Office Memorandum issued by the Ministry of Finance was not applicable. They also asserted that similar decisions taken by the Ministry of Railways, which allowed invocation of force majeure in other contracts due to restricted train services and minimal footfalls, were not binding on this specific case.
Sections Cited
Section 56
AI-generated summary — verify with the full judgment below
IN THE HIGH COURT OF JUDICATURE AT PATNA Civil Writ Jurisdiction Case No.6322 of 2023 ====================================================== M/s Ashutosh Enterprises, a Proprietary concern having its place of business at Shop No. 14, Jupiter Apartment, Dolphin Garden, Poonam Sagar Complex, Mira Road, East, Thane, P.S. Thane, District Thane (Maharashtra) through its Proprietor Sandeep Bholanath Shukla, Male, Aged about 35 years, Son of Sri Bholanath Shukla, Resident of B101, Jupiter Apartment, Dolphin Garden, Poonam Sagar Complex, Mira Road, East, Thane, P.S. Thane, District Thane (Maharashtra). ... ... Petitioner/s Versus
The Union of India Ministry of Railways through the Senior Divisional Commercial Manager, NF Railway, Katihar.
The Senior Divisional Commercial Manager, NF Railway, Katihar.
The Divisional Commercial Manager, NF Railway, Katihar.
The Secretary, Ministry of Home Affairs, Government of India, New Delhi.
The Secretary, Department of Expenditure, Ministry of Finance, Procurement Policy Division, Government of India, New Delhi. ... ... Respondent/s ====================================================== Appearance : For the Petitioner/s : Mr. Umesh P
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Patna High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.