M/S Jai Mata Di Construction Company vs. The State Of Bihar
Held
The Court held that the writ petition is maintainable and not barred by laches. It reasoned that the Petitioner had been making representations to the authorities, and the cause of action for payment of maintenance amount arose only after the work efficiency certificate dated 19.12.2024 was issued. The Court found the Respondents' contention that the Petitioner had not maintained the work from 2014 to 2019 to be without legal basis and contrary to the record, noting that the Security Refunding Form was signed by the Joint Engineer and Assistant Engineer, with endorsements confirming the road's maintenance and recommendation for payment. The Court also referred to Clause 41 of the agreement regarding the release of security deposit after the defect liability period and certification by the Engineer. Consequently, the Court allowed the writ petition and directed the authorities to make the necessary payments for the maintenance work from 2014 to 2019 within eight weeks.
Facts
M/S Jai Mata Di Construction Company (Petitioner) filed a writ petition seeking payment of Rs. 6,02,312.39 (excluding GST) plus GST and interest for maintenance work performed for five years under Agreement No. 04/SBD-04/2013-14, dated 08.05.2013. The contract involved road construction and subsequent maintenance. The Petitioner claims the maintenance amount for the period from 2014 to 2019 has not been paid despite the work being completed and representations made to the authorities. The Respondents (State of Bihar and its officials) opposed the petition, arguing it was barred by laches due to the Petitioner approaching the court in 2025, over six years after the maintenance period ended. They also contended that the Security Refunding Form submitted by the Petitioner was not signed by the Executive Engineer, rendering payment impossible.
Key Issues
1. Whether the writ petition filed by the Petitioner is maintainable on grounds of laches, considering the delay in approaching the Court after the maintenance period concluded in 2019 and the petition was filed in 2025? 2. Whether the Petitioner is entitled to payment for the maintenance work done from 2014 to 2019, as per the terms of the contract and the submitted Security Refunding Form? Petitioner's Arguments: The Petitioner argued that the authorities have not paid the due amounts for maintenance work from 2014 to 2019, despite the contract terms and representations. They contended that the cause of action for payment arose only after the work efficiency certificate dated 19.12.2024 was issued, justifying the filing of the writ petition. They relied on Section 70 of the Contracts Act, 1872, for their claim. Respondents' Arguments: The Respondents argued that the writ petition should be dismissed due to laches, as the Petitioner approached the court after a significant delay of over six years. They also argued that the Security Refunding Form was merely a format and not signed by the Executive Engineer, thus precluding any payment. They did not dispute the completion of the construction work.
Sections Cited
Section 70
AI-generated summary — verify with the full judgment below
IN THE HIGH COURT OF JUDICATURE AT PATNA Civil Writ Jurisdiction Case No.980 of 2025 ====================================================== M/S Jai Mata Di Construction Company a registered partnership firm having its registered office at Professor Colony, Power House Road, P.S. and District- Begusarai through its Authorized Partner namely Sri Sanjeev Kumar (male), aged about 49 years, son of Late Digamber Prasad Singh, resident of Ward No. 8, P.O.-Chandaur, P.S.-Bhagwanpur, District-Begusarai. ... ... Petitioner/s Versus
The State of Bihar through Principal Secretary, Rural Works Department, Government of Bihar, Patna.
The Principal Secretary, Rural Works Department, Government of Bihar, Patna.
The Additional Chief Secretary, Rural Works Department, Government of Bihar, Patna.
The Engineer in Chief, Rural Works Department, Government of Bihar, Patna.
The Superintending Engineer, Rural Works Department, Work Division, Samastipur, Government of Bihar, Samastipur, Bihar.
The Executive Engineer, Rural Works Department, Work Division Teghra, Begusarai, Bihar.
The Assistant Engineer, Rural Works Department, Work Division Teghra, Begusarai, Bihar. ... ... Respond
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Patna High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.