M/S Continental Chemical Company vs. The State Of Bihar

Original PDF →
CWJC/1927/2024HC PatnaGSTCNR BRHC01009843202411 May 2026Bench: MR. JUSTICE A. ABHISHEK REDDY13 pages
AI SummaryDismissed

Facts

The petitioner, M/s Continental Chemical Company, was allotted an industrial plot (C-18) in Patliputra Industrial Area on August 8, 2005. This allotment was cancelled by the Bihar Industrial Area Development Authority (BIADA) on August 17, 2022, and the subsequent appeal was dismissed on November 21, 2022. The petitioner then filed a writ petition (CWJC No. 16772 of 2022), which led to the High Court setting aside both the cancellation and appeal dismissal orders on December 22, 2022. Possession was restored to the petitioner on January 1, 2023, and commercial production reportedly commenced. However, BIADA, through the Deputy General Manager, issued an order on November 7, 2023, directing the petitioner to vacate the plot, alleging non-commencement of commercial production, without issuing a fresh show-cause notice or providing an opportunity to present evidence. The petitioner claims to have submitted evidence of functioning on November 6 and 14, 2023, but BIADA forcibly took possession and locked the premises, leading to the unit's closure. The plot was subsequently allotted to Respondent No. 7.

Held

The Court held that the respondent-BIADA was not required to pass a fresh order of cancellation before taking possession in cases where the petitioner had given an undertaking to start commercial production within a time fixed by the Court. Relying on a Division Bench judgment in CWJC No. 919 of 2024, the Court clarified that the previous order dated December 22, 2022, which accepted the petitioner's undertaking, stipulated that in case of default, the petitioner would hand over vacant possession to BIADA. The Court found that the petitioner had failed to demonstrate that any manufacturing of allopathic drugs was being undertaken, citing the nature of the product (canto calcium for veterinary purposes) and minimal electricity consumption as evidence. The Court also noted that the GST returns did not substantiate the petitioner's claim of a functional unit. Regarding the principle of natural justice, the Court found that the inspection reports indicated the unit was not functional, and even if one report was ignored, the other supported this conclusion. The Court further observed that the possession was taken on November 23, 2023, and allotted to Respondent No. 7 on December 21, 2023, making it imprudent to restore possession at that stage, given the petitioner's failure to start commercial production as per the undertaking. The Court dismissed the writ petition but directed BIADA to return all articles, machinery, and furniture from the unit as per the inventory.

Key Issues

1. Whether the respondent-BIADA was required to pass a fresh order of cancellation before taking physical possession of the industrial plot, given the petitioner's undertaking to commence commercial production within a stipulated time in the earlier round of litigation before this Court? Petitioner's arguments: The petitioner contended that BIADA acted contrary to the BIADA Act and the previous High Court order by forcibly taking possession without a fresh cancellation order or a show-cause notice. They argued that BIADA should have approached the Court for permission to take action if the undertaking was breached, rather than taking unilateral possession. The petitioner also argued that the inspection reports relied upon by BIADA were flawed, as no prior notice was given, and one inspection date was a holiday. They further argued that allotting the plot to Respondent No. 7, who runs an IT industry, is contrary to BIADA's industrial policy. Respondent-BIADA's arguments: BIADA opposed the maintainability of the writ petition, stating the petitioner had not approached the court with clean hands and the prayer had become infructuous as the property was already allotted to a third party. They argued that the petitioner failed to start commercial production despite ample opportunities and that inspection reports dated October 20, 2023, and November 3, 2023, indicated the unit was not functional, evidenced by minimal electricity consumption. They contended that the petitioner was merely trading in animal feed and not manufacturing allopathic drugs, and GST returns did not substantiate the unit's functionality.

Sections Cited

Section 6(2)(a), Section 6(2)(b), Section 6(2)(c)

AI-generated summary — verify with the full judgment below

Cause title — parties, addresses and appearances
IN THE HIGH COURT OF JUDICATURE AT PATNA Civil Writ Jurisdiction Case No.1927 of 2024 ====================================================== M/s Continental Chemical Company, A Partnership firm Constituted Under Indian Partnership Act, having its Office at-First floor, Govinda Complex, Govind Mitra Road, Patna-800004, factory at -31 Industrial Estate, Patna- 800013 through its Partner Indrajeet Kumar Gender Male aged about 47 Years Son of Jagdeep Prasad Verma, Resident of Govinda Complex, Govind Mitra Road, Patna- 800004. ... ... Petitioner/s Versus 1. The State of Bihar through Principal Secretary Department of Industries, Bihar, Patna. 2. The Managing Director, Bihar Industrial Ara Development Authority, Sone Bhavan, Patna, Bihar. 3. The Joint Managing Director, Bihar Industrial Area Development Authority, Udyog Bhavan, East Gandhi Maidan, Patna. 4. Deputy General Manager, Patna Cluster, Industrial Area Development Authority, Udyog Bhavan, East Gandhi Maidan, Patna. 5. The Regional Manager, Bihar Industrial Area Development Authority, Patna Cluster, Patliputra. 6. The Executive Director, Bihar Industrial Area Development Authority, Sone Bhavan, Patna, Bihar. 7. M/s Raisha Solution, Proprietor Archana, resident of Flat- 204, Kamliniranjan Apartment, Phulwari, District- Patna, State- Bihar, 800025. ... ... Respondent/s ====================================================== Appearance : For the Petitioner/s : Mr. Prasoon Kumar, Adv. For Respondent BIADA : Ms. Prakritita Sharma, Adv. For Respondent No. 7 : Mr. Suresh Pd. Singh, Adv. : Ms. Kumari Rashmi, Adv. For the Respondent/s : Mr. Standing Counsel (24) ====================================================== CORAM: HONOURABLE MR. JUSTICE A. ABHISHEK REDDY

ORAL ORDER 28 11-05-2026 Heard the learned counsel for the parties. The present writ petition has been filed for the following relief(s):- “i. To issue writ of mandamus or any other appropriate writ and quash and set aside the order cum notice dated 2/13 07.11.2023 by which the respondent No. 4, namely the Deputy General Manager, Bihar Industrial Area Development Authority, Patna cluster, has directed the petitioner to vacate the plot no. C-18 having an area of 8677 sq ft. at Industrial Area, Patliputra without following the procedure and without providing opportunity as mandated in clause (a), (b), (c) of sub section (2) of section 6 of the Bihar Industrial Area Development Authority Act, 1974 (herein after referred to as BIADA or Act). ii. To hold and declare that taking possession of industrial plot by respondents and locking whereof is violation of order and direction of the Hon'ble High Court in CWJC No. 16772 of 2022 order dated 22.12.2022 as such the petitioner is entitle to get possession of industrial unit. iii. To hold and declare that the taking of possession of land forcefully by the respondent by order dated 07.11.2023 is wholly unreasonable and arbitrary because the petitioner unit is under operation and evidence in support of operation of unit has been submitted to the respondent on 06.11.2023 and again on 14.11.2023 but the respondent without considering the petition forcefully lock the mill premises which resulted closure of the unit. iv. To hold and declare that the respondent had failed to consider the representation and document submitted by petitioner in support of functioning of the industrial unit as such, the respondent has violated the principle of natural justice. v. To issue any other order/orders, direction/directions, writ/writs as your lordship deemed fit and proper.”

3.

It is the case of the petitioner that he has been allotted the subject property by the authority on 08.08.2005. 3/13 That thereafter, the same was cancelled by the respondent- BIADA on 17.08.2022 and though the petitioner has preferred a statutory appeal, the same was also dismissed on 21.11.2022. Thereafter, the petitioner has preferred writ petition in this Hon’ble Court vide CWJC No. 16772 of 2022 and this Court vide order dated 22.12.2022 has set aside both the orders of cancellation dated 17.08.2022 in Memo No. 143 and 21.11.2022 passed in Appeal Case No. 218 of 2022. That consequent to the order passed by this Hon’ble High Court in CWJC No. 16722 of 2022, the possession was restored to the petitioner on 01.01.2023. That after the restoration of the physical possession of the plot to the petitioner, the commercial production of the unit has started and continues to do so. However, the respondent-BIADA without putting the petitioner on any show cause notice or giving the petitioner an opportunity of producing any documents to substantiate that the unit is functioning and is in commercial production has taken physical possession of the subject property.

4.

Learned counsel appearing on behalf of the petitioner has submitted that the act of the respondent authority in forcibly taking over the physical possession of the unit without cancelling the allotment made to the petitioner is 4/13 contrary to the provisions of the BIADA Act and also the judgment of this Hon’ble Court passed in CWJC No. 16772 of 2022 dated 22.12.2022. Learned counsel has submitted that the authority without cancelling the allotment has forcibly taken the possession of the subject property solely on the ground that this Court in the earlier round of litigation has granted permission to the respondent-BIADA to take over the possession of the subject property in case the commercial production has not started. Learned counsel has submitted that even for the sake of argument if there was any violation of the terms and conditions of the undertaking given by the petitioner before this Hon’ble Court in the earlier round of litigation, the respondent-BIADA was expected to approach this Hon’ble Court and apprise this Court by way of filing the petition or filing a contempt. However, they could not have taken forcible physical possession of the subject property without approaching this Court or passing an order of cancellation after putting the petitioner notice. Learned counsel has submitted that earlier order of cancellation passed by the Deputy General Manager and also the order passed by the Principal Secretary in the Appeal Case No. 218 of 2022 were both quashed and set aside by this Hon’ble Court. Therefore, there was no occasion for the 5/13 respondent-BIADA to take physical possession of the subject property without any show cause notice. Learned counsel has submitted that had the petitioner been put on prior notice and given an opportunity of filing his explanation, he could have produced documentary evidence to prove that the unit was functioning and in commercial production of allopathic drugs. Further, learned counsel has submitted that the reliance placed by the respondent authority on the two inspection reports are both made to suit their needs, as no prior notice was given to the petitioner prior to the date of inspection. That one of the dates of inspection on i.e., 20.10.2023 was a holiday and the unit was closed on that particular date. Learned counsel has submitted that without cancelling the allotment made to the petitioner, the authority ought not to have taken physical possession of the subject property forcibly and allotted the same to the respondent No. 7 herein. Further, handing over of the possession of the subject property to the respondent No. 7 who is running an IT Industry is contrary to the BIADA own industrial policy and therefore, the same is liable to be set aside. Learned counsel has stated that the petitioner has invested crores of rupees and made the unit functional one and, therefore, the abrupt taking of the physical possession by the respondent-BIADA is contrary to the 6/13 principles of natural justice and equity and also the provisions of the BIADA Act. Learned counsel has therefore, prayed this Hon’ble Court to allow the present writ petition and restore the possession back to the respondent-BIADA.

5.

Per contra, the learned counsel appearing on behalf of the respondent-BIADA has vehemently opposed the very maintainability of the present writ petition. Learned counsel has submitted that the petitioner has not approached this Hon’ble Court with clean hands and further, the prayer sought for in the present writ petition has become infructuous as the respodent-BIADA has taken physical possession of the subject property and allotted it to a third party i.e., respondent No. 7 herein. Learned counsel has submitted that the petitioner in spite of being given ample opportunity, has failed to start commercial production and no effort was made by the petitioner to start production within a time granted by this Hon’ble Court in the earlier round of litigation. Learned counsel has submitted that the petitioner himself has voluntarily given an undertaking before this Court that he will start the commercial production and keep the unit running, but, he has failed to do so. Learned counsel has submitted that the petitioner was put on notice in the Month of April 2023 (Annexure-R/7) and further, the 7/13 inspections have taken place in the Months of October, November and December, 2023 and on physical inspection, it was found that the petitioner has violated undertaking given to this Hon’ble Court. Further, it is stated that the petitioner had to make the unit fully functional for sanctioned products i.e., allopathic drugs but the petitioner has not filed any scrap of paper to substantiate that he is in commercial production of the sanctioned products. That the documents filed by the petitioner reveal that the petitioner is not manufacturing any allopathic drugs but he is only trading in some chemicals which are mainly used for veterinary purposes. Learned counsel submits that in the earlier round of litigation, the respondent-BIADA was authorized to take over the physical possession of the subject property in case the petitioner failed to commence the commercial production as per his own undertaking and the petitioner having failed to hand over the physical possession of the subject property, the respondent authority had to necessarily take the physical possession of the unit. Further, learned counsel has submitted that the documents filed by the petitioner namely the tax receipts, invoices and also the electricity bills reveal that the petitioner’s unit is not in commercial production but the petitioner is only indulging in trading. That the GST returns 8/13 filed by the petitioner clearly establish the fact that there is no commercial activity present and so also the electricity bills filed by the petitioner reveal that there is no manufacturing process that is being conducted by the petitioner as the monthly bills bare minimum. The negligible consumption of electricity of the unit clearly points out to the fact that there is no manufacturing process that is being undertaken by the petitioner. Learned counsel has submitted that the petitioner is habitual offender and in fact, in the earlier round of litigation also, this Hon’ble Court on the basis of undertaking given by the petitioner had given an opportunity to the petitioner to commence commercial production but he has failed to do so. That the principles of natural justice and equity have been complied with, by the authority before taking possession. That the petitioner was put on notice on 03.11.2023 and he has submitted his reply on 06.11.2023 and, thereafter, on finding that the documents and the reply filed by the petitioner to the show cause notice was not substantiated by any proof of any production, a speaking order dated 14.11.2023 was passed. Further, the contention of the petitioner that the IT Parks are not permitted under the BIADA policy is totally misconceived as the Government of Bihar under the new Industrial Incentive Promotion Policy is now permitting 9/13 allotment of land to the service sector specifically IT Parks etc. Learned counsel has submitted that a third party has already been allotted the subject property and therefore, the equities as claimed by the petitioner are not available to him and prayed for dismissing the present writ petition.

6.

Learned counsel appearing on behalf of the respondent No. 7 i.e., third party in whose favor the subject land has been allotted while adopting the arguments made by the learned counsel for the respondent-BIADA has also opposed the very maintainability of the present writ petition. Learned counsel has stated that the respondent No. 7 has been allotted subject property on 21.12.2023 and thereafter, the respondent No. 7 has undertaken the necessary steps for setting up the IT Park. Learned counsel has submitted that the balance of convenience and equities are in favor of the respondent No. 7 and it would not be prudent for this Court to set aside the impugned order and restore the possession back to the petitioner who admittedly is a habitual offender. Learned counsel has submitted that though the petitioner was initially allotted the land way back in the year 2005, the petitioner till date has not done much manufacturing and the same is evidenced by the monthly electricity bills of the unit. Further, the inspection 10/13 reports dated 20.10.2023 & 03.11.2023 reveal that the unit of the petitioner was not functional and the minimum electricity consumption of the unit clearly points out to the fact that there is no manufacturing process being undertaken as claimed by the petitioner. Learned counsel has therefore, prayed this Hon’ble Court to dismiss the present writ petition.

7.

The only issue before this Court is as to whether the respondent-BIADA in cases were the unit in the earlier round of litigation has given an undertaking that they will start commercial production within the time fixed by the Court is has to pass a fresh order of cancellation or not no longer res integra.

8.

A division Bench of this Court in CWJC No. 919 of 2024 along with its analogous cases dated 29.04.2025 has clarified as under; “12. An issue was raised before the learned Single Judge, where such matters are now being adjudicated, that before taking any precipitate action, the BIADA, under the orders passed by the Division Bench, referred to above, was under an obligation to approach the Court first; seek liberty and only then pass any order.

13.

On such a plea by the petitioner, the learned Single Judge referred the matter to the Division Bench for interpreting the order dated 22.11.2022, referred to above, as it was passed by a Division Bench.

14.

A plain reading of the order makes is very obvious that the undertaking was of the writ petitioner.

15.

The aforenoted undertaking was accepted by the Bench and it was directed that in case of any default by the petitioner, he shall hand over the vacant and peaceful possession of the allotted property to BIADA.

11/13

16.

This fact had to be communicated to the Court by the BIADA so that necessary action could be taken against the writ petitioner for breach of the undertaking given by him before this Court.

17.

Merely because a part of the order has been couched in such a way so as to suggest that before taking any precipitate action, permission of the Court was necessary, it would not become imperative for the BIADA to first approach this Court and only after seeking liberty, take any action.

18.

This would not be a correct reading of the order of the Division Bench.

19.

The Bench vide order dated 22.11.2022, had only clarified the undertaking given by the writ petitioner and in case of any default, meaning thereby that if the unit would not be started within 60 days or would not be made fully functional or operational within six months, the vacant and peaceful possession would be handed over to BIADA. If that is not done, the matter had to be reported to the Court by BIADA.

20.

The Court by introducing such term in the order only ensured that the writ petitioner did not run away from his responsibility and not face the Court for its contempt.

21.

The order dated 22.11.2022 cannot be read as putting any restraint on the BIADA for seeking permission of the Court before cancelling the allotment.”

9.

Therefore, the contention of the petitioner that the respondent-BIADA ought to have passed fresh orders of cancellation before taking possession is without any legal basis. Though the counsel for the petitioner has argued at length on the merits of the case, a perusal of the document filed by the petitioner does not show that any manufacturing of any allopathic drugs is being undertaken in the unit. The perusal of the invoices reveal that the petitioner is dealing mostly in canto calcium 5kg chemical which is mainly used for veterinary 12/13 purposes. Further, the perusal of the monthly electricity consumption bills also reveal that the consumption of electricity is very minimal and does not in any manner establish that the unit of the petitioner is functioning. Had the unit been functioning the monthly consumption of electricity could have been very high. However, in this case they are very minimal. That insofar as the contention of the petitioner that the principles of natural justice and equity have not been followed is concerned, the inspection reports dated 20.10.2023 & 03.11.2023 clearly points out to the fact that the unit of the petitioner was not functional. Though the counsel for the petitioner has stated that the inspection dated 20.10.2023 was a holiday and even if that report is ignored, the second inspection report also points out to the fact that the unit is not functioning as rightly pointed out by the counsel for the respondent-BIADA, the petitioner appears to be simply trading in animal feed/ canto calcium 5kg and not really manufacturing any allopathic drugs. The GST returns also do not substantiate the contention of the petitioner that the unit is functional. Further, it is to be noted that that the possession of the subject unit was on 23.11.2023 and allotted to the respondent No. 7 on 21.12.2023 and it could not be prudent on part of this Court to restore the possession of the 13/13 subject property at this point of time, when it is clearly established that the petitioner has reasonably failed to start commercial production as per the undertaking given to this Hon’ble Court in the earlier round of litigation.

10.

Having regard to the above discussion, this Court does not find any merit in the present writ petition which warrants any interference by this Hon’ble Court under Article 226 of the Constitution of India. Accordingly, the present writ petition stands dismissed, however, without any costs.

11.

The respondent BIADA is directed to return all the articles, machinery, furniture etc. that was in the unit at the time of taking possession from the petitioner and as per the inventory preponed.

12.

All pending I.As., if any, are deemed to have been disposed of.

Ayush/- (A. Abhishek Reddy, J) U

Reproduced from the public record of the Patna High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.