M/S. Triveni Constructions vs. Military Engineer Services

ARBAPPL/176/2022HC TelanganaGSTCNR HBHC01051821202203 January 2024Bench: C.V. BHASKAR REDDY16 pages
AI SummaryAllowed

Held

The Court held that it has the power to appoint an arbitrator under Section 11(6) of the Arbitration and Conciliation Act, 1996, as the respondents had failed to appoint an arbitrator and had effectively denied the applicant's claim by stating that further claims were waived after the final bill. The Court reasoned that the applicant had raised a dispute regarding the deduction of statutory taxes shortly after the settlement of the final bill, and the respondents' response indicated a failure to resolve the dispute amicably, thus giving rise to a cause of action for arbitration. Regarding the limitation aspect, the Court found that the application was not barred by limitation. It was established that the Limitation Act, 1963, applies to arbitration proceedings, and the residual provision under Article 137, providing a three-year limitation period, would apply. Since the final bill was settled on 06.09.2022 and the dispute was raised before the expiry of this period, the claim was within time. The Court further stated that whether the claim is barred by lapse of time is a matter to be decided by the Arbitrator. Consequently, the Court appointed Sri Tariq Khan, Advocate, as the Sole Arbitrator to adjudicate the disputes between the parties and directed the Arbitrator to complete the proceedings within six months.

Facts

M/s. Triveni Constructions, a partnership firm registered under the MSMED Act, 2006, was awarded a contract by the Military Engineer Services (MES) for replacing AC sheets in store buildings for Rs. 2,16,91,366. The applicant contended that the bid amount excluded GST at 12% and labour welfare cess at 1%, which were expressly agreed to be paid over and above the bid amount. However, the MES deducted these taxes from the principal bid amount. The applicant raised this discrepancy, requesting the release of the deducted taxes with interest. The MES, through its Accounts Officer, stated that the applicable taxes had been credited to the public fund account. The applicant reiterated their claim, treating their letter as a notice under Condition No. 70 of IAFW-2249. The MES responded that disputes should be referred to a serving officer appointed by the Engineer-in-Chief, and since the applicant accepted the final bill without protest, arbitration would be at their own risk. The applicant then filed an Arbitration Application seeking the appointment of a sole arbitrator.

Key Issues

1. Whether the Court has the power to appoint an arbitrator under Section 11(6) of the Arbitration and Conciliation Act, 1996, when the respondents have refused to appoint an arbitrator as per the contract terms? - The applicant argued that the respondents' refusal to appoint an arbitrator and their contention that the applicant accepted the final bill without protest necessitated the Court's intervention under Section 11(6) of the Act. They relied on the principle that the Court's intervention is to minimize intervention at the stage of appointing an arbitrator, as incorporated in Section 11(6-A). - The respondents argued that the applicant had accepted the final bill process on 08.02.2022 without protest, and therefore, taking recourse to arbitration under Condition No. 70 of IAFW-2249 would be at the applicant's own risk. They also contended that as per Condition 65 of IAFW-2249, further claims made after the submission of the Final Bill are deemed waived and extinguished. 2. Whether the dispute raised by the applicant regarding the deduction of GST and labour welfare cess is barred by limitation? - The applicant contended that they raised the dispute soon after the settlement of the Final Bill and that the application was filed within the limitation period prescribed by Article 137 of the Limitation Act, 1963. - The respondents argued that the applicant's claim was raised after the lapse of almost 2 years and that accepting the final bill without protest extinguished any further claims.

Sections Cited

Section 11(6), Section 11(6-A), Section 16, Section 43, Article 137

AI-generated summary — verify with the full judgment below

\\ IN THE HIGH COURT FOR THE STATE OF TELANGANA AT HYOERABAD WEDNESDAY ,THE THIRD DAY OF JANUARY TWO THOUSAND AND TWENTY FOUR PRESENT THE HONOURABLE SRI JUSTICE C.V. BHASKAR REDDY ARBITRATION APPLICATION NO: 176 OF 2022 Between: M/s. Triveni Constructions, having its registered office at # 2150,1st floor, Section-o1 (Phase-Vll),SAS Nagar, Mohail Punjuab-160062, Rep.by its Partner, Sri Amit Anand, S/o. Late Sh. Sant Swarup Anand, Aged about 44 years, R/o. # 2150, 1st floor, Section-61 (Phase-Vll), SAS Nagar, Mohail Punjub-160062. ...APPLICANT AND 1. Military Engineer Services, Asst Garrison Engineer (lndep) Fy Ordnance Factory Post Eddumilaram - 502 205 Dist Sangareddy (Telangana)

2.

Chief Engineer (FY), Hyderabad Opp: Parade Ground, Sardar Patel Road, Secunderabad - 500 003. 3. AGE (l) Fy, Ordnance Factory Estate, Yeddumallaram- 5O2 2O5. ...RESPONDENTS Arbitration Application Under Section 11 (6) of the Arbitration and Conciliation Act 1996 ( Act 26 of 1996 ) praying that this Hon'ble Court may be pleased to i) To appoint a Sole Arbitrator to adjudicate the claims and disputes between the Applicant and Respondents. ii) To award the costs of application lA NO:J Ol 2023 Petition un

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Telangana High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.