The Superintending Engineer vs. M/S Gropu Engineers Corporation
Held
The Court held that the respondent award holder is entitled to payment of GST. The Arbitrator correctly determined that the time of supply of goods is the date of issue of invoice by the supplier, which is the relevant date for tax liability. The Court reasoned that the GST Act came into force on July 1, 2017, and the supply of transformers occurred within the stipulated 90 and 120-day periods from the work order dated May 11, 2017, meaning some supplies were made after the GST implementation. Therefore, the clause stating prices were firm and final inclusive of all taxes did not disentitle the respondent from claiming GST, especially considering the provision for actual payment of changes in tax structure. The Court found that the interpretation of the contract by the Arbitrator, in light of the applicable provisions of the GST Act, was within his jurisdiction and did not warrant interference under Section 34 of the Arbitration and Conciliation Act, 1996. The District Judge also correctly upheld the award. The ratio is that the time of supply, as determined by the GST Act, governs tax liability, and contract clauses must be interpreted in conjunction with statutory provisions, particularly when tax laws change during the performance of a contract.
Facts
The Superintending Engineer (appellant) is appealing an order of the District Judge, which upheld an arbitral award in favour of M/s. Group Engineers Corporation (respondent/award holder). The dispute concerns the respondent's entitlement to payment of GST on transformers supplied under a works contract. The work order was issued on May 11, 2017, with supply periods of 90 and 120 days. The Goods and Services Tax Act, 2017 (GST) came into force on July 1, 2017. The contract contained a clause stating prices were firm and final, inclusive of all taxes, but also allowed for payment of actuals for any changes in tax structure within the valid period. The respondent supplied transformers within the stipulated and extended periods, some of which fell after the GST implementation date. The appellant argued that the 'firm and final' price clause disentitled the respondent from claiming GST.
Key Issues
1. Whether the respondent award holder is entitled to payment of GST applicable as per the Goods and Services Tax Act, 2017, notwithstanding the contract clause stating that the price quoted shall be firm and final inclusive of all taxes and duties. Contentions: Petitioner/Appellant: Argued that Clause 1 of the contract, stipulating that the price quoted shall be firm and final inclusive of all taxes and duties, disentitles the claimant from claiming payment of GST. Respondent/Award Holder: Relied on the Arbitrator's finding that the time of supply of goods is the date of issue of invoice by the supplier, and for tax liability, the invoice date is the relevant date. Further, the respondent contended that since GST came into force on July 1, 2017, and some supplies were made within the valid or extended period after this date, the clause regarding changes in tax structure would apply. The respondent also pointed to Section 12 of the GST Act, 2017, which determines the time of supply based on the invoice date or date of receipt of payment.
Sections Cited
Section 34, Section 37, Section 12, Section 13, Section 31
AI-generated summary — verify with the full judgment below
IN THE HIGH COURT AT CALCUTTA [ CIRCUIT BENCH AT PORT BLAIR ] ***
FMAT(ARBAWARD)/1/2024
The Superintending Engineer
Vs.
M/S. Group Engineers Corporation
Mr. Rakesh Kumar
… for the appellant
Mr. Tapan Kumar Das
… for the respondent
March 18, 2025 [SR] Item No.8
This appeal is arising out of an order passed by the learned District Judge on 12th October, 2023 in an application under section 34 of the Arbitration and Conciliation Act, 1996. In view of the nature of the award, the only issue survives for consideration is whether the respondent award holder is entitled to payment of GST applicable as per the Goods and Services Tax Act, 2017. We are not required to go into other issues as claims that have been rejected by the learned Arbitrator are not under challenge.
It is an admitted position that under the works contract, the award holder was required to supply different kind of transformers. The department issued the work order on 11th May, 2017. Under the contract, the contractor/claimant was required to supply different kinds of transformers within the time period of 90 and 120 days as the case may be.
The cl
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Calcutta High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.