M/S Kundan Kumar (Civil And Electrical Contractor) vs. The State Of Bihar Through The Principal Secretary Shri Kumar Ravi Building Construction Department
Held
The Court noted the submission made by the learned counsel for the petitioner. The counsel stated that the order previously passed by the High Court in C.W.J.C. No. 12913 of 2024 on April 11, 2025, has been complied with, and the grievance of the petitioner has been redressed. Based on this submission, the Court found no reason to proceed with the contempt proceedings. Therefore, the contempt petition was closed. The Court did not delve into the specifics of the compliance or the nature of the grievance redressed, relying solely on the petitioner's counsel's statement.
Facts
The petitioner, M/s Kundan Kumar (Civil and Electrical Contractor), filed a writ petition (C.W.J.C. No. 12913 of 2024) before the Patna High Court. The present case, Miscellaneous Jurisdiction Case No. 2814 of 2025, is a contempt petition filed by the petitioner. The petitioner claims that an order previously passed by the High Court in C.W.J.C. No. 12913 of 2024 on April 11, 2025, has been complied with by the opposite parties, and their grievance has been redressed. The opposite parties include various officials from the State of Bihar, including the Principal Secretary, Building Construction Department, Managing Director of Bihar State Building Construction Corporation Ltd., and the Commissioner, Bihar Goods and Services Tax.
Key Issues
1. Whether the order passed by this Court in C.W.J.C. No. 12913 of 2024 dated 11.04.2025 has been complied with by the opposite parties. 2. Whether the grievance of the petitioner has been redressed as per the previous order of this Court. Petitioner's Contention: The petitioner's counsel submitted that the order of this Court dated 11.04.2025 has been complied with and the petitioner's grievance has been redressed. Revenue/State's Contention: No specific arguments were recorded for the opposite parties regarding compliance or non-compliance.
AI-generated summary — verify with the full judgment below
IN THE HIGH COURT OF JUDICATURE AT PATNA Miscellaneous Jurisdiction Case No.2814 of 2025 In Civil Writ Jurisdiction Case No.12913 of 2024 ====================================================== M/S Kundan Kumar (Civil and Electrical Contractor) having its Office at - Ramdayalu Nagar, P.S.-Sadar, P.O.-Ramana, District-Muzaffarpur through its authorized signatory Kundan Kumar Mishra @ Kundan Kumar. ... ... Petitioner/s Versus
The State of Bihar through the Principal Secretary Shri Kumar Ravi Building Construction Department New Secretariat, Government of Bihar, Patna.
Shri Kumar Ravi, Managing Director, Bihar State Building Construction Corporation Ltd., having its Office at - Shastri Nagar, P.S. - Shastri Nagar, District-Patna.
Shri Anil Kumar, Chief General Manager, Bihar State Building Construction Corporation Ltd., having its Office at - Shastri Nagar, P.s. - Shastri Nagar, District-Patna.
Shri Sunil Kumar, General Manager (North), Bihar State Building Construction Corporation Ltd., having its Office at - Shastri Nagar, P.S. - Shastri Nagar, District-Patna.
Shri Ashutosh, Deputy General Manager, Bihar State Building Construction Corporation Ltd., Project Implement
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Patna High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.