M/S Bhardwaj Constructions Thru. Its Authorized Representative Alok Mani vs. State Of U.P. Thru. Its Secy. P.W.D. Lko. And 4 Others

/32/2023HC AllahabadGSTCNR UPHC02008706202307 February 2023Bench: SANGEETA CHANDRA,MANISH KUMAR3 pages
For Petitioner: Vaibhav Krishna
AI SummaryRemanded

Held

The Court disposed of the writ petition with a direction to the petitioner. The petitioner is required to make a fresh representation to respondent no. 2. Respondent no. 2, in turn, shall seek clarification from the Engineer-in-Chief and respondent no. 1 (State of U.P. Thru. Its Secy. P.W.D. Lko.). Subsequently, respondent no. 2 is to decide the petitioner's representation by a reasoned and speaking order within a period of two months from the date of the fresh representation. The Court did not directly adjudicate on the liability to pay the GST amount or the specific amount claimed by the petitioner, but rather directed a procedural mechanism for resolution. No issue was expressly left undecided, as the Court provided a clear path for the petitioner's grievance to be addressed.

Facts

M/s Bhardwaj Constructions, a partnership firm, undertakes works contracts for the State of Uttar Pradesh. The petitioner claims that while running bills for these contracts have been paid, the Goods and Services Tax (GST) component on these payments has not been remitted by the respondents. The petitioner asserts that prior to the GST regime, VAT was paid after deducting Tax Deducted at Source (TDS). Following the introduction of GST, Government Orders dated 09.11.2017 and a clarification dated 26.10.2021 stipulated that existing contracts would also be governed by GST, with an additional tax burden to be computed and paid to the contractor, who would then deposit it with the department. The petitioner alleges that respondents no. 3 to 5 have only paid the principal amount on their invoices, deducting only 2% (1% CGST and 1% SGST) as TDS, which is a partial deduction. This has resulted in the petitioner being unable to deposit the full GST liability, leading to potential recovery proceedings against them. The petitioner's representations to various Executive Engineers have remained pending.

Key Issues

1. Whether the respondents are liable to pay the full GST amount on works contracts awarded before the GST regime, in accordance with Government Orders dated 09.11.2017 and clarification dated 26.10.2021? (Question of law and fact, concerning the interpretation and application of Government Orders and GST provisions). Contentions: Petitioner: Argues that the respondents are obligated to pay the full GST amount as per the aforementioned Government Orders and clarification, which govern existing contracts. They contend that the partial TDS deducted is insufficient and has led to their inability to deposit the entire GST liability, exposing them to recovery actions. They seek a mandamus to compel payment of the outstanding GST amount of Rs. 7,97,88,026.31/- along with interest, or alternatively, for necessary action to be taken regarding pending payments as per the Government Orders. Respondent: The judgment does not record any specific arguments made by the respondents.

AI-generated summary — verify with the full judgment below

Court No. - 2 Case :- WRIT TAX No. - 32 of 2023 Petitioner :- M/S Bhardwaj Constructions Thru. Its Authorized Representative Alok Mani Respondent :- State Of U.P. Thru. Its Secy. P.W.D. Lko. And 4 Others Counsel for Petitioner :- Vaibhav Krishna Counsel for Respondent :- C.S.C. Hon'ble Mrs. Sangeeta Chandra,J. Hon'ble Manish Kumar,J.

1.

Heard Sri J. N. Mathur, learned Senior Counsel assisted by Sri Nishant Mishra and Sri Vaibhav Krishna, learned counsel for the petitioners and Learned Standing Counsel for the State Respondents.

2.

This petition has been filed with the following main prayers:- "A- Issue a writ, order or direction in the nature of mandamus commanding respondents no. 2 to 5 to forthwith pay an amount of Rs. 7,97,88,026.31/- to the petitioner alongwith interest, at such rates, as may be determined by this Hon'ble Court; B- In the Alternative, Issue a writ, order or direction in the nature of mandamus commanding respondents no. 2 to 5 to forthwith take necessary action in respect of pending payments of the petitioner in terms of clarification dated 26.10.2021 issued by respondent no. 1 and/or Government Orders dated 09.11.2017 and that of 2019 issued by responden

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Allahabad High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.