M/S Desnil Engineers And Anr vs. The Secretary, Iba And 3 Ors
Held
The Court noted that the BTC had issued four orders sanctioning and releasing a total of Rs. 1,41,15,437.00 to the Executive Engineer, PWD, Chirang (R&B) Division, Kajalgaon, for the petitioner's consultancy fees. The Court inferred from these orders that the consultancy fee claimed by the petitioner had been paid. However, the Court acknowledged the possibility that the Executive Engineer might not have released these amounts to the petitioner. Therefore, the Court directed the Executive Engineer, PWD, Chirang (R&B) Division, Kajalgaon (respondent No. 4), to release the sanctioned amounts, totaling Rs. 1,41,15,437.00, to the petitioner within one month from the date of receipt of a copy of the order, in the event that these amounts had not yet been released. The writ petition was disposed of accordingly.
Facts
The petitioner, M/s Desnil Engineers, represented by its proprietor Jadumani Sarmah, filed a writ petition before the Gauhati High Court seeking the release of Rs. 1,41,15,916.00 towards consultancy fees for two projects: construction of an RCC bridge over river Aie and improvement of JSB Hospital at Kajalgaon, both under the NESIDS scheme in Chirang District, Bodoland Territorial Council (BTC). The BTC, through its counsel, submitted a covering letter dated 04.06.2025, along with annexures containing four orders. These orders indicated that the consultancy fee of Rs. 1,41,15,437.00 had been sanctioned and released by the BTC to the Executive Engineer, PWD, Chirang (R&B) Division, Kajalgaon (respondent No. 4). The BTC argued that since the dues had been paid, the writ petition should be closed.
Key Issues
1. Whether the consultancy fees claimed by the petitioner have been paid by the Bodoland Territorial Council (BTC) to the Executive Engineer, PWD, Chirang (R&B) Division, Kajalgaon, as per the sanction orders issued. Petitioner's Contention: The petitioner sought the release of Rs. 1,41,15,916.00 in consultancy fees. Respondent's (BTC) Contention: The BTC submitted that through four sanction orders dated 25.07.2022, 29.03.2024, and 26.03.2025, a total amount of Rs. 1,41,15,437.00 was sanctioned and released to the Executive Engineer, PWD, Chirang (R&B) Division, Kajalgaon, for the petitioner's consultancy work. Therefore, the BTC contended that the petitioner's dues had been settled and the writ petition should be closed. The BTC relied on the contents of the covering letter dated 04.06.2025 and the annexed orders.
Sections Cited
Section 129
AI-generated summary — verify with the full judgment below
Cause title — parties, addresses and appearances
2025 Heard Mr. M. Sarma, learned counsel for the petitio
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Gauhati High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.