Sri Ch. Chandraiah vs. The Secretary And 8 Others

WP/13288/2020HC TelanganaGSTCNR HBHC01021759202016 February 2021Bench: T.VINOD KUMAR,M.S.RAMACHANDRA RAO13 pages
AI SummaryAllowed

Held

The Court held that the respondents (1st to 6th) were liable to reimburse the petitioner GST at 12% on the value of work executed under the agreement dated August 5, 2017. The Court found no justification for adjusting the VAT amount of Rs. 11,93,172/- from the GST payable to the petitioner, nor for deducting TDS at 1% CGST and 1% SGST, especially since the work was completed before the TDS provisions became applicable. The Court also held that the action of the 7th and 8th respondents in not refunding the VAT amount paid by the 5th respondent was invalid. The Court reasoned that since the VAT Act was repealed, the amount remitted by the 5th respondent did not partake the character of tax and was collected without the authority of law, contravening Article 265 of the Constitution. Relying on Supreme Court judgments, the Court stated that refund of amounts collected without authority of law can be claimed in a writ petition. Therefore, the 7th and 8th respondents were directed to process the refund application for the mistakenly paid VAT amount. The Court allowed the writ petition, directing reimbursement of GST and release of the final bill within two weeks, failing which interest at 8% per annum would be payable. The 7th and 8th respondents were directed to process the refund within three weeks.

Facts

The petitioner, Sri Ch. Chandraiah, a civil contractor, entered into an agreement with the 5th respondent on August 5, 2017, for civil construction works valued at Rs. 2,75,45,328.54. A condition in the agreement stipulated that Value Added Tax (VAT) would be payable in addition to the contract amount at a rate of 5%. However, by the time the agreement was executed, the Telangana VAT Act, 2005, had been repealed and replaced by the GST Act, 2017. Despite this, the 5th respondent continued to deduct VAT at 5% from the petitioner's running bills and remitted it to the 8th respondent (Assistant Commissioner (ST)). The petitioner sought reimbursement of GST at 12% on the work done and the return of the deducted VAT amount with interest, arguing that VAT was no longer applicable post-GST implementation.

Key Issues

1. Whether the respondents are liable to reimburse the petitioner the GST at 12% on the value of work done, considering the agreement was entered into after the repeal of the VAT Act and the introduction of the GST Act? (Question of law turning on the applicability of GST provisions over repealed VAT provisions). 2. Whether the deduction of VAT at 5% from the petitioner's bills and its remittance to the 8th respondent was without the authority of law, and if so, whether the petitioner is entitled to a refund of this amount along with interest? (Question of law turning on the validity of tax collection post-repeal of the relevant Act). Petitioner's Arguments: The petitioner argued that since the GST Act replaced the VAT Act, VAT was not payable. The 5th respondent should have applied the GST rate of 12% and reimbursed the petitioner accordingly. The deduction of VAT was illegal and without authority. The petitioner also contended that the deduction of 1% CGST and 1% SGST as TDS was incorrect as the TDS provisions under GST were applicable only from October 2018, whereas the petitioner completed the work by June 30, 2018. Respondents' Arguments: The respondents (1st to 6th) did not dispute the facts but claimed that due to initial lack of clarity regarding GST rates and amendments, VAT was added to part bills and remitted. They argued that the petitioner would be entitled to credit for amounts deposited with the 8th respondent and that they had not acted arbitrarily. The 7th and 8th respondents argued that the refund application for VAT was filed beyond the 45-day period prescribed under the VAT Act.

Sections Cited

Article 265, Article 226

AI-generated summary — verify with the full judgment below

HIGH COURT FOR THE STATE OF TELANGANA AT HYDERABAD (Special Original Jurisdiction) TUESDAY, THE SIXTEENTH DAY OF FEBRUARY TWO THOUSAND AND TWENTY ONE PRESENT WRIT PETITION NO:13288 oF 2020 Between: Sri Ch. Chandraiah, Civil Contractor , #2-129, Chikatayapalem Village, Thorrur Mandal, lVahabubabad District ..PETITIONER AND

1.2.

J. 4. 5.

6.7.

The Secletary, Agricultural Market Committee, Government of Telangana, Cherial, Siddipet District. The Executive Enoineer. Agricultural Marketing, Government of Telangana, Wara nga l. The Executive Engineer, Agricultural Marketing, Government of Telangana, Niza mabad. Deputv Executive Enoineer, Agricultural tVlarketing, Government of Telangana, Wara rigal Superintend.ing Engineer, Agricultural Marketing, Officiating, Government of Telanqana, Waranqal. commrssioner and-Director of Agriculture Marketing, Government of relangana, Hyderabad. :11: jl]:lrlslg; rgp; gy Principat Secretary to covernment, Revenue (CT_il) uepanment, secretariat, Hvderabad. Assistant Commissioner (ST), It/ahabubabad Circle, Mahabubabad. unron ot tndia. reo. bv its secretary, [,4inistry of Finance, central Secretariat, New Delhi 8I ...RESPONDENTS Petitlon under Article 22

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Telangana High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.