M/S Pinki Construction And Anr. vs. The Executive Engineer, North Bengal Development Department

WPA/875/2022HC CalcuttaGSTCNR WBCHCA001909202223 May 2025Bench: HON'BLE JUSTICE SMITA DAS DE4 pages
AI SummaryRemanded

Held

The Court held that the respondent authorities had misconstrued the applicability of the notification. The Court found that paragraph 3(iv) of the Notification dated August 16, 2017, is confined to pre-GST contracts and cannot be invoked to deny reimbursement for contracts executed after July 1, 2017, which are expressly governed by paragraph 4 of the same notification. The Court noted that paragraph 4 clearly states that for post-GST contracts or ongoing projects where estimates were approved before July 1, 2017, GST rates will be applicable, and suppliers must pay CGST and WBGST. The Court also observed that the question of revising contractual values due to the change from VAT/Service Tax to GST does not arise as per the notification. The Court did not go into the merits of the case but directed respondent No. 4, The Additional Chief Secretary, North Bengal Development Department, to revisit the issue of reimbursement of the GST component for the period from July 1, 2017, to March 31, 2019, in light of paragraph 4 of the notification. A reasoned order was to be passed after giving the petitioner an opportunity of hearing, preferably within six weeks.

Facts

The petitioner, M/s Pinki Construction & Anr., a firm registered under the CGST and WBGST Acts, sought a mandamus from the High Court at Calcutta directing the respondents, including the Executive Engineer, North Bengal Development Department, to remit the Goods and Services Tax (GST) on Works Contract Services provided on or after July 1, 2017. The petitioner contended that the respondent authorities incorrectly applied paragraph 3(iv) of a notification, which they argued was confined to pre-GST contracts, to deny reimbursement for post-GST contracts governed by paragraph 4 of the same notification. The petitioner also argued that the denial of GST reimbursement was arbitrary and discriminatory, violating Article 14 of the Constitution. The tax period in dispute pertains to the period from July 1, 2017, to March 31, 2019. The petitioner had made payments of GST from their own pocket.

Key Issues

1. Whether paragraph 3(iv) of the Notification dated August 16, 2017, can be invoked to deny GST reimbursement for works contract services executed after July 1, 2017, when paragraph 4 of the same notification expressly governs post-GST contracts? (Question of law) 2. Whether the action of the respondent authorities in denying GST reimbursement to the petitioner is arbitrary, unreasonable, and discriminatory, violating Article 14 of the Constitution of India? (Question of mixed law and fact). Petitioner's arguments: The petitioner argued that paragraph 3(iv) of the notification is applicable only to pre-GST contracts and cannot be used to deny reimbursement for contracts executed after July 1, 2017, which are governed by paragraph 4. They further contended that the denial of reimbursement is arbitrary and discriminatory, violating Article 14 of the Constitution. The petitioner relied on the judgment in Sushil Kumar Thard v. National Jute Manufactures Corporation Limited & Ors., affirmed by the Supreme Court in National Jute Manufactures Corporation Limited v. Sushil Kumar Thard, which held that State instrumentalities must act fairly and reasonably. Revenue/State's arguments: The Learned Counsel for the State was unable to contradict the submissions made by the petitioners.

Sections Cited

Section 14

AI-generated summary — verify with the full judgment below

IN THE HIGH COURT AT CALCUTTA Constitutional Writ Jurisdiction (APPELLATE SIDE)

Present: The Hon’ble Justice Smita Das De

W.P.A. No. 875 of 2022

M/s Pinki Construction & Anr. Vs. The Executive Engineer, North Bengal Development Department & Ors.

Smita Das De, J.:-

1.

The petitioner seeks a mandamus directing inter alia, the respondents to remit the amount of the GST on Works Contract Services provided on or after July 1, 2017. The petitioner in the instant case is the partnership firm registered under the CGST Act and WBGST Act. For the petitioner : Mr. Vinay Shraff,

: : : : : Mr. Himangshu Kumar Ray, Ms. Shiwani Shaw, Ms. Swarnwarshi Poddar, Mr. Animitra Roy, Mr. Anish Mandal.

For the State : : : :

Mr. Anirban Ray, Ld. GP, Mr. Md. T.M. Siddiqui, Ld. AGP., Mr. Tanoy Chakraborty, Mr. Saptak Sanyal.

Reserved on : 16/05/2025 Judgment on : 23/05/2025

2

2.

The case made out by the petitioner is that the respondent authorities have failed to appreciate that paragraph 3 (iv) of the Notification is confined in its application to Pre-GST contracts and cannot be invoked to deny reimbursement in respect of contract

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Calcutta High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.