M/S Pinki Construction And Anr. vs. The Executive Engineer, Pwd, Dakshin Dinajpur And Ors.

Original PDF →
WPA/872/2022HC CalcuttaGSTCNR WBCHCA001901202223 May 2025Bench: HON'BLE JUSTICE SMITA DAS DE4 pages
AI SummaryRemanded

Facts

The petitioner, M/s Pinki Construction & Anr., a firm registered under CGST and WBGST Acts, sought a mandamus from the Calcutta High Court directing the respondents, including the Executive Engineer, PWD Dakshin Dinajpur Division, to remit the GST on Works Contract Services provided after July 1, 2017. The petitioner contended that the respondent authorities wrongly invoked paragraph 3(iv) of a Notification, which applies only to pre-GST contracts, to deny reimbursement for post-GST contracts governed by paragraph 4 of the same Notification. The petitioner argued this denial was arbitrary and discriminatory, violating Article 14 of the Constitution. The State's counsel was unable to contradict the petitioner's submissions.

Held

The Court held that the reason provided by respondent No. 1 in its letter dated November 4, 2020, was contrary to the mandate of the Notification dated August 16, 2017, as the matter pertained to the post-GST regime. The Court found that the question of revising contractual values due to the change in tax rates from VAT/Service Tax to GST did not arise for post-GST contracts. A plain reading of Paragraph 4 of the Notification clearly indicated that for post-GST contracts or ongoing projects with estimates approved before July 1, 2017, GST rates would be applicable, requiring suppliers to pay WB GST and CGST. Consequently, the order passed by respondent No. 1 was deemed palpably wrong, ex facie bad, arbitrary, and unsustainable in law, as it was passed without proper application of mind and misconstrued the Notification's applicability. The Court set aside the order dated November 4, 2020, and directed respondent No. 4, The Secretary, Public Works Department, to revisit the petitioner's issue regarding the payment of GST on gross bills for the period from April 1, 2018, to March 31, 2019, in light of Paragraph 4 of the Notification. The Court clarified it had not gone into the merits but directed consideration of reimbursement of the GST component, requiring a reasoned order after hearing the petitioner within six weeks.

Key Issues

1. Whether paragraph 3(iv) of the Notification dated August 16, 2017, confined in its application to pre-GST contracts, can be invoked to deny reimbursement in respect of contracts executed after July 1, 2017, which are expressly governed by paragraph 4 of the same Notification? Petitioner's Arguments: The petitioner argued that the respondent authorities erred in applying paragraph 3(iv) of the Notification to post-GST contracts. They contended that paragraph 4 of the same Notification clearly governs post-GST contracts and ongoing projects where estimates were approved before July 1, 2017, mandating the applicability of GST rates. The petitioner further argued that the denial of GST reimbursement was arbitrary, unreasonable, and discriminatory, violating Article 14 of the Constitution. They relied on the judgment in Sushil Kumar Thard v. National Jute Manufactures Corporation Limited & Ors., affirmed by the Supreme Court, which held that State instrumentalities must act fairly and reasonably. Revenue/State's Arguments: The Learned Counsel for the State was unable to contradict the submissions made by the petitioners.

Sections Cited

Section 14

AI-generated summary — verify with the full judgment below

IN THE HIGH COURT AT CALCUTTA Constitutional Writ Juri iction (APPELLATE SIDE)

Present: The Hon’ble Justice Smita Das De

W.P.A. No. 872 of 2022

M/s Pinki Construction & Anr. Vs. The Executive Engineer, PWD Dakshin Dinajpur Division & Ors.

Smita Das De, J.:-

1.

The petitioner seeks a mandamus directing inter alia, the respondents to remit the amount of the GST on Works Contract Services provided on or after July 1, 2017. The petitioner in the instant case is the partnership firm registered under the CGST Act and WBGST Act. For the petitioner : Mr. Vinay Shraff,

: : : : : Mr. Himangshu Kumar Ray, Ms. Shiwani Shaw, Ms. Swarnwarshi Poddar, Mr. Animitra Roy, Mr. Anish Mandal.

For the State : : : :

Mr. Anirban Ray, Ld. GP, Mr. Md. T.M. Siddiqui, Ld. AGP., Mr. Tanoy Chakraborty, Mr. Saptak Sanyal.

Reserved on : 16/05/2025 Judgment on : 23/05/2025

2

2.

The case made out by the petitioner is that the respondent authorities have failed to appreciate that paragraph 3 (iv) of the Notification is confined in its application to Pre-GST contracts and cannot be invoked to deny reimbursement in respect of contracts executed after July 1, 2017 which are expressly governed by paragraph 4 of the very same Notification.

3.

It is further submitted that the action of the respondent in denying GST reimbursement to the petitioners is arbitrary, unreasonable and discriminatory violating the mandate of the Article 14 of the Constitution of India which is contrary to the principle of equality before the Law and equal protection of the Laws.

4.

The Learned Advocate for the petitioner relies upon a judgment of this Hon’ble High Court in the case of Sushil Kumar Thard v. National Jute Manufactures Corporation Limited. & Ors. (WPA 4751 of 2023) which was subsequently affirmed by the Hon’ble Supreme Court in the case of National Jute Manufactures Corporation Limited v. Sushil Kumar Thard SLP(C) 25436 of 2023 wherein it has been held that even on contractual matters, the State and its instrumentalities are bound to act fairly, reasonably and in a non-arbitrary manner.

5.

The Learned Counsel for the State is unable to contradict the submissions made by the petitioners.

6.

Having heard both the parties and considering the materials available on record I am of the view that the reason given by the respondent No. 1 vide letter dated November 4, 2020 (in reply to the various letters of the 3

petitioners) is contrary to the mandate of the Notification dated August 16, 2017 since the matter pertains to POST-GST regime. Therefore, the question of revision of any contractual values of the contract due to impact of change of tax rate with regard to VAT/ Service Tax to GST does not arise at all.

7.

From the plain reading of the Paragraph 4 of the Notification in question it clearly envisages that: “With regard to post-GST contracts or ongoing project where estimates have been approved before 1st of July 2017 then in those work order can be given for supply of goods or service or both work contract, GST rates will be applicable. In other words the suppliers of goods/services or both has to pay WBGST and CGST on all taxable goods / services.”

8.

In the light of the above Notification, the order passed by the respondent No. 1 is palpably wrong and the finding is ex facie bad, arbitrary and not sustainable in the eye of law. The respondent authority has passed the order without any proper application of mind and has misconstrued the applicability of the Notification in the context of the instant case. The respondents have failed to appreciate that Paragraph 3(iv) of the Notification is confined in its application to pre-GST contract and cannot be invoked to deny reimbursement in respect of contracts executed after July 1, 2017 which are expressly governed by Paragraph 4 of the same notification.

9.

In view of the aforesaid, the order dated November 4, 2020 is set aside directing inter alia, the respondent No. 4, The Secretary, Public works

4

Department, Nabanna to revisit the issue of the petitioner as mentioned in the letters dated October 19, 2020 and April 23, 2021 respectively with regard to the payment of the GST amount against the gross bill during the period from 01.04.2018 to 31.03.2019 as per GST Law. However, it is made clear that I have not gone into the merits of the case but since the petitioner has already made payment of the GST amount against the gross bills for the period 01.04.2018 to 31.03.2019 out of their own pocket, hence, I direct the respondent No. 4 to consider the issue of reimbursement of the GST component in the light of Paragraph 4 of the Notification dated August 16, 2017 being Notification No. 5050-F(Y) and shall pass a reasoned order in accordance with law upon giving opportunity of hearing to the petitioner preferably within a period of six weeks from the date of communication of the order.

10.

With the above observations and directions, the writ petition being WPA 872 of 2022 stands disposed of. No order as to costs.

11.

Urgent certified website copy of this order, if applied for, be supplied to the parties upon compliance with all requisite formalities.

(Smita Das De, J.)

Reproduced from the public record of the Calcutta High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.