M/S. Pinki Construction And Anr. vs. Superintending Engineer, Pwd, Malda Nad Ors.

WPA/878/2022HC CalcuttaGSTCNR WBCHCA001914202223 May 2025Bench: HON'BLE JUSTICE SMITA DAS DE4 pages
AI SummaryRemanded

Held

The Court held that the respondent authorities had misconstrued the applicability of the Notification dated August 16, 2017. The Court found that paragraph 3(iv) of the notification is confined to pre-GST contracts and cannot be invoked to deny reimbursement for contracts executed after July 1, 2017. The Court's reasoning was based on a plain reading of paragraph 4 of the notification, which clearly states that for post-GST contracts or ongoing projects where estimates were approved before July 1, 2017, GST rates will be applicable, and suppliers must pay WBGS T and CGST. The Court noted that the question of revising contractual values due to the change from VAT/Service Tax to GST did not arise as per the notification. The ratio decidendi is that statutory notifications must be interpreted strictly according to their plain language, and provisions dealing with distinct periods (pre-GST vs. post-GST) should not be conflated. The Court directed respondent No. 4, The Secretary, Public Works Department, Nabanna, to revisit the petitioner's issue regarding the payment of GST on gross bills for the period from July 1, 2017, to March 31, 2019, in light of paragraph 4 of the Notification No. 5050-F(Y) dated August 16, 2017. A reasoned order was to be passed after hearing the petitioner, preferably within six weeks.

Facts

The petitioner, M/s Pinki Construction & Anr., a firm registered under the CGST and WBGST Acts, sought a mandamus directing the respondents, including the Superintending Engineer, PWD, Malda, to remit the GST on Works Contract Services provided after July 1, 2017. The petitioner contended that the respondent authorities wrongly applied paragraph 3(iv) of a notification, which they argued was confined to pre-GST contracts, to deny reimbursement for post-GST contracts governed by paragraph 4 of the same notification. The petitioner also argued this denial was arbitrary and discriminatory, violating Article 14 of the Constitution. The State's counsel was unable to contradict the petitioner's submissions. The dispute pertains to the period from July 1, 2017, to March 31, 2019.

Key Issues

1. Whether paragraph 3(iv) of the Notification dated August 16, 2017, can be invoked to deny GST reimbursement in respect of works contracts executed after July 1, 2017, when paragraph 4 of the same notification expressly governs post-GST contracts? (Question of law) Petitioner's arguments: The petitioner argued that paragraph 3(iv) of the notification applies only to pre-GST contracts and cannot be used to deny reimbursement for contracts executed after July 1, 2017. They contended that paragraph 4 of the same notification specifically addresses post-GST contracts, including ongoing projects where estimates were approved before July 1, 2017, and mandates the applicability of GST rates. The petitioner further argued that the respondents' action was arbitrary, unreasonable, and discriminatory, violating Article 14 of the Constitution. They relied on the judgment in Sushil Kumar Thard v. National Jute Manufactures Corporation Limited & Ors., affirmed by the Supreme Court, which held that State instrumentalities must act fairly and reasonably. Revenue/State's arguments: The Learned Counsel for the State was unable to contradict the submissions made by the petitioners.

Sections Cited

CGST Act, WBGST Act

AI-generated summary — verify with the full judgment below

1

IN THE HIGH COURT AT CALCUTTA Constitutional Writ Jurisdiction (APPELLATE SIDE)

Present: The Hon’ble Justice Smita Das De

W.P.A. No. 878 of 2022

M/s Pinki Construction & Anr. Vs. Superintending Engineer, PWD, Malda & Ors.

Smita Das De, J.:-

1.

The petitioner seeks a mandamus directing inter alia, the respondents to remit the amount of the GST on Works Contract Services provided on or after July 1, 2017. The petitioner in the instant case is the partnership firm registered under the CGST Act and WBGST Act. For the petitioner : Mr. Vinay Shraff,

: : : : : Mr. Himangshu Kumar Ray, Ms. Shiwani Shaw, Ms. Swarnwarshi Poddar, Mr. Animitra Roy, Mr. Anish Mandal.

For the State : : : :

Mr. Anirban Ray, Ld. GP, Mr. Md. T.M. Siddiqui, Ld. AGP., Mr. Tanoy Chakraborty, Mr. Saptak Sanyal.

Reserved on : 16/05/2025 Judgment on : 23/05/2025

2

2

2.

The case made out by the petitioner is that the respondent authorities have failed to appreciate that paragraph 3 (iv) of the Notification is confined in its application to Pre-GST contracts and cannot be invoked to deny reimbursement in respect of contracts executed aft

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Calcutta High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.