Cfm Asset Reconstruction PVT. LTD. vs. Assistant Commissioner, CGST And C.Ex, Durgapur-I Division And Ors.

WPA/3564/2025HC CalcuttaGSTCNR WBCHCA006730202502 July 2025Bench: HON'BLE JUSTICE RAJA BASU CHOWDHURY8 pages
AI SummaryPartly Allowed

Held

The Court held that Section 26E of the SARFAESI Act, 2002, prevails over the recovery mechanisms of the CGST Act, 2017, due to its non-obstante clause and being a later enactment. The Court cited the Supreme Court's decision in *Kotak Mahindra Bank Limited v. Girnar Corrugators Private Limited & Ors.*, which clarified that when two enactments have competing non-obstante provisions, the later statute prevails. The Court found no irregularity in the CGST authorities attaching the property initially, given that the secured creditor had not taken possession. However, considering the priority established by Section 26E of the SARFAESI Act, the Court directed the CGST authorities to hand over possession of the secured asset to the secured creditor within one week. The secured creditor was permitted to proceed with enforcing its security interest under the SARFAESI Act. The CGST authorities' right to recover their dues was made subject to the secured creditor's interest, requiring the secured creditor to provide accounts of any transactions related to enforcing its rights. The order was passed without prejudice to the rights of the principal borrower and other pending legal proceedings.

Facts

Two writ petitions were filed before the High Court. The first, WPA 3564 of 2025, was by CFM Asset Reconstruction Pvt. Ltd. (the "secured creditor"), a registered entity acquiring non-performing assets. The second, WPA 26115 of 2024, was by Ma Chandi Durga Ispat Ltd. (the "principal borrower") and others. The principal borrower had availed credit facilities from IDBI Bank and State Bank of India, secured by a mortgage over a property. The principal borrower defaulted, and its accounts were declared non-performing assets. The secured creditor acquired the exposure from State Bank of India. Subsequently, the Principal Commissioner, CGST, invoked Section 79(1)(d) of the CGST Act, 2017, to attach the secured asset for recovery of government dues. The secured creditor challenged this attachment.

Key Issues

1. Whether Section 26E of the SARFAESI Act, 2002, which confers priority on secured creditors, prevails over the recovery mechanisms of the CGST Act, 2017, particularly when both enactments contain non-obstante clauses? Petitioner's Arguments: - The petitioner (secured creditor) argued that Section 26E of the SARFAESI Act, inserted in 2019, has a non-obstante clause and, being a later enactment, should prevail over the CGST Act. They relied on the Supreme Court judgment in *Kotak Mahindra Bank Limited v. Girnar Corrugators Private Limited & Ors.* and a Gujarat High Court judgment in *Central Bank of India v. State of Gujarat & Ors.*. - They also contended that they have the authority to invoke Section 14 of the SARFAESI Act without prior issuance of a notice under Section 13(4), citing *Standard Chartered Bank v. V. Noble Kumar & Ors.*. Revenue's Arguments: - The CGST authorities argued that since the secured creditor could not take possession of the property despite issuing a Section 13(2) notice, and statutory dues were payable, they were entitled to attach the property in accordance with the CGST Act. They asserted that the attachment was made in accordance with law.

Sections Cited

Section 26E, Section 13(2), Section 13(4), Section 14, Section 79(1)(d)

AI-generated summary — verify with the full judgment below

02.07.

2025 Item Nos AD 2 & 3 Saswata

WPA 3564 of 2025 CFM Asset Reconstruction Pvt. Ltd. versus Assistant Commissioner, CGST & C.EX, Durgapur-I Division & Ors. with WPA 26115 of 2024 Ma Chandi Durga Ispat Ltd. & Anr. versus Union of India & Ors.

Mr. Jishnu Chowdhury, Sr. Adv. Ms. Aasia Hasan Ms. Sakshi Tiwari …For the petitioner Ms. Manasi Mukherjee Mr. Tapan Bhanja Mr. Bijitesh Mukherjee …For the CGST authorities Mr. Joydeep Banerjee Ms. Sharmila Deb …For the State Mr. Arijit Chakraborty Mr. Bankim Pal …For the respondent nos. 5 & 6 Mr. Sayantan Bose Ms. Manisha Das Ms. Neha Mishra

….for the ADDA

1.

By consent of the parties both the writ petitions are taken up together for consideration.

2.

The writ petition being WPA 3564 of 2025 has been filed by the CFM Asset Reconstruction Pvt. Ltd. (hereinafter referred to as the “secured creditor”) while the writ petition being WPA 26115 of 2024 has been filed by private parties, amongst whom the petitioner no.1 in such petition appear to be the principal borrower who claims to be a lessee in respect of

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Calcutta High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.