Unising Projects P.LTD vs. UOI & Anr.

W.P.(C)/7148/2008HC DelhiGSTCNR DLHC01146115200828 February 2025Bench: HON'BLE MS. JUSTICE PRATHIBA M. SINGH,HON'BLE MR. JUSTICE RAJNEESH KUMAR GUPTA8 pages
For Petitioner: Mr. R.S. Yadav and Mr. Abhishek Jaju, AdvocatesFor Respondent: Mr. Aditya Singla, SSC CBIC, Ms. Supriya Juneja and Ms. Arya Suresh Nair, Advocates
AI SummaryAllowed

Held

The Court held that the impugned show cause notice dated September 26, 2008, and the subsequent order-in-original dated February 28, 2019, were liable to be quashed due to the inordinate and unjustified delay in adjudication. The Court noted that despite the rejection of the Petitioner's stay application on July 22, 2009, the Adjudicating Authority kept the proceedings in abeyance, which was found to be without reason. The Court relied on its previous orders dated September 30, 2008, and September 10, 2018, which clarified that no stay was granted. The reasoning was further bolstered by the decisions in VOS Technologies India Pvt. Ltd. and Nanu Ram Goyal, which emphasize that matters involving financial liabilities cannot be kept pending for years and that lethargy or indolence in adjudication is not permissible. The Court found that repeated placing and removal of the matter from the call book did not constitute valid justification for the fifteen-year delay. Consequently, the show cause notice and the order-in-original were quashed. The Petitioner did not press the challenge to the amendment of Section 65(105) of the Finance Act, 2005, or seek any other reliefs.

Facts

The Petitioner, Unising Projects Pvt. Ltd., filed a writ petition in 2008 challenging an amendment to Section 65(105) of the Finance Act, 2005, and a demand of Rs. 35,40,956/- raised after an audit. Subsequently, a show cause notice dated September 26, 2008, was issued demanding Rs. 3,38,07,757/-. The Petitioner sought to amend the writ petition. While the stay application was rejected on July 22, 2009, the adjudication proceedings were kept in abeyance by the Adjudicating Authority, which the Court later found unjustified. An order-in-original was passed on February 28, 2019, which was also challenged via amendment. The Court noted the significant delay in adjudication, with the show cause notice being over fifteen years old.

Key Issues

1. Whether the impugned show cause notice dated September 26, 2008, and the subsequent order-in-original dated February 28, 2019, deserve to be quashed due to the prolonged delay in adjudication? (Question of law) Petitioner's arguments: The Petitioner contended that the adjudication proceedings were kept in abeyance without justification, despite the rejection of their stay application. They relied on the High Court's order dated September 10, 2018, which expressed surprise at the delay. The Petitioner further argued that the matter is covered by precedents like VOS Technologies India Pvt. Ltd. vs. Principal Additional Director General & Anr., 2024 SCC OnLine Del 8756, and Nanu Ram Goyal vs. Commissioner of CGST and Central Excise, Delhi, [(2023) 6 Centax 148 (Del.)], which emphasize the need for expedition in concluding adjudication proceedings and quashing them due to inordinate delay. Revenue's arguments: The judgment does not record any specific arguments made by the Revenue in response to the Petitioner's contentions regarding the delay and the applicability of the cited precedents.

Sections Cited

Section 65(105)

AI-generated summary — verify with the full judgment below

W.P.(C) 7148/2008 $~28 * IN THE HIGH COURT OF DELHI AT NEW DELHI Date of decision: 28th February, 2025 +

W.P.(C) 7148/2008 & CM APPL. 19092/2019

UNISING PROJECTS PVT. LTD

.....Petitioner

Through: Mr. R.S. Yadav and Mr. Abhishek Jaju, Advocates.

versus

UOI & ANR.

.....Respondents Through: Mr. Aditya Singla, SSC CBIC, Ms. Supriya Juneja and Ms. Arya Suresh Nair, Advocates.

CORAM:

JUSTICE PRATHIBA M. SINGH

JUSTICE RAJNEESH KUMAR GUPTA Prathiba M. Singh, J.(Oral)

1.

This hearing has been done through hybrid mode.

2.

This petition has been filed by the Petitioner-Unising Projects Pvt. Ltd. under Article 226 of the Constitution of India seeking quashing of the amendment made in Clause (105) of Section 65 by the Finance Act, 2005. 3. The present petition has a long history having been filed originally in the year 2008. The Petitioner is in the business of providing air-conditioning systems, DG sets, power backup systems, fire-fighting rooms, electric sub- stations, water tanks, transformers and installation

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Delhi High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.